Loading...
HomeMy WebLinkAboutR-2020-002 Stormwater Pipe Rehabilitation - Contract with Michels CorporationRESOLUTION NO. R-2020-002 A RESOLUTION authorizing a contract with Michels Corporation for City Project No 2496 Stormwater Infrastructure Rehabilitation WHEREAS, two thousand and sixty (2,060) linear feet of failed clay and concrete stormwater drainage pipe comprising segments of former Drainage Improvement Districts Nos 4, 29, and 38 requires lining to prevent back-ups and flooding caused by root intrusion, and WHEREAS, HLA Engineering and Land Surveying, Inc. has provided the plans and contract documents under City Contract No 2019-099 for the drainage pipe lining using cured -in - place (CIPP) technology, and WHEREAS, the City of Yakima used the procedures established by Washington State law for the bidding and awarding of public capital improvement projects during the selection of the contractor for this project; and WHEREAS, Michels Corporation submitted the low bid and has the ability and expertise to correctly line the stormwater drainage pipe at a cost of Two Hundred Forty -Four Thousand Four Hundred Ninety -Five Dollars ($244,495), and WHEREAS, the City's Chief Engineer has recommended awarding the contract to Michels Corporation to accomplish the installation of the improvements, and WHEREAS, the City Council finds that it is in the best interests of the City of Yakima and its residents to rehabilitate the stormwater infrastructure described in the contract attached hereto and incorporated herein by this reference, now, therefore BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA: The City Manager is hereby authorized and directed to execute the attached and incorporated contract with Michels Corporation, in the amount of Two Hundred Forty -Four Thousand Four Hundred Ninety -Five Dollars ($244,495) for City Project No 2496 for the rehabilitation of failed stormwater pipe. ADOPTED BY THE CITY COUNCIL this 7th day of January, 2020. ATTEST. Sonya ClaakTee, City Clerk Patricia Byers, Mayor / CONTRACT THIS AGREEMENT, made and entered in triplicate, this dayof C , 20, by and between the City of Yakima , hereinafter called the Owner, and It t te,--, t - a 5� Wee4ifigton Corporation, hereinafter called the Contractor yc� WITNESSETH: That in consideration of the terms and conditions contained herein and attached and made a part of this agreement, the parties hereto covenant and agree as follows: I The Contractor shall do all work and furnish all tools, materials, labor and equipment for THE BID AMOUNT OF $ 24,4 '1,15.Z( for DID CIPP Rehabilitation, City of Yakima Project No. 2496, all in accordance with, and as described in the attached plans and specifications and the 2020 Standard Specifications for Road, Bridge, and Municipal Construction which are by this reference incorporated herein and made a part hereof, and shall perform any alterations in or additions to the work provided under this contract and every part thereof Work shall start within ten (10) days after the Notice to Proceed and shall be completed in Twenty-five (25) working days. If work has not commenced within the ten (10) days after the notice to proceed, the first chargeable working day shall be the eleventh (11th) working day after the date on which the City issues the Notice to Proceed If said work is not completed within the time specified, the Contractor agrees to pay to the Owner the sum specified in the Standard Specifications for each day said work remains uncompleted after expiration of the specified time, as liquidated damages. The Contractors shall provide and bear the expense of all equipment; work and labor of any sort whatsoever that may be required for the transfer of materials and for constructing and completing the work provided for in this contract and every part thereof, except such as are mentioned in the specifications to be furnished by the City of Yakima . II The City of Yakima hereby promises and agrees with the Contractor to employ, and does employ the Contractor to provide the materials and to do and cause to be done the above described work and to complete and finish the same according to the attached plans and specifications and the terms and conditions herein contained and hereby contracts to pay for the same according to the attached specifications and the schedule of unit or itemized prices hereto attached, at the time and in the manner and upon the conditions provided for in this contract. III INDEMNIFICATION The Contractor shall defend, indemnify, and hold harmless the City, its officers, elected officials, employees and agents from and against all claims, causes of action, damages, losses, and expenses of any kind or nature whatsoever, including but not limited to, attorney's fees and court costs, arising out of, relating to, or resulting from The Contractor's performance or non-performance of the services, duties and obligations required of it under this Agreement. IV The Contractor for himself, and for his heirs, executors, administrators, successors, and assigns, does hereby agree to the full performance of all the covenants herein contained upon the part of the Contractor V It is further provided that no liability shall attach to the City of Yakima by reason of entering into this contract, except as expressly provided herein IN WITNESS, WHEREOF the parties hereto have caused this agreement to be executed the ctay`aaye'a'frh, first herein above written Countersigned.c�CITY OF YAKIMA CONTRACTOR this OS day of49-jT 20.�� Attest: ity Manage City Clark CICONTRACT NO. 9°00 -003 R OLUTION NO: R.,',9O,90--0 .Z �cice.\.&e0Lg. o ctor By JG� t (A)es0e14- Felt (Print Name) Its. (5 ion jO (President, Owner, etc.) Address: l 1 tS. t bT` £ $ E 4-2 S VA\ OW-- g 3c -z_ G-\PROJECTS\2019\19107\Spec\19107 Spec.docx 1 ITEM TITLE: SUBMITTED BY: BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEM ENT Item No. 7.D. For Meeting of: January 7, 2020 Resolution authorizing a contract with Michels Corporation for City Project No. 2496 Stormwater Pipe Rehabilitation Scott Schafer, Director of Public Works David Brown, Assistant Director of Public Works Mike Price, Wastewater/Stormwater Manager, 249-6815 SUMMARY EXPLANATION: City Project No. 2496 (Project) rehabilitates 2,060 linear feet of stormwater pipe that is experiencing severe root intrusion. The failed clay and concrete pipe, comprising sections of former Yakima County Drainage Improvement Districts Nos. 4, 29 and 38, requires frequent and extensive root removal efforts by City Stormwater crews to maintain water flow and avoid back- ups. The Project will utilize cured -in -place (CI PP) technology to line the existing pipe with a continuous liner to prevent the intrusion of roots. HLA Engineering and Land Surveying, Inc. provided the Project design and bid documents under City Contract No. 2019-099. The City utilized the procedure established by the State of Washington for competitively bidding projects. Three contractors submitted bids, with Michels Corporation submitting the lowest bid of $244,495. The attached resolution and contract provide the specific elements of the agreed upon pipe rehabilitation. The project is funded through the Stormwater Capital Fund 442. ITEM BUDGETED: Yes STRATEGIC PRIORITY: Public Safety APPROVED FOR SUBMITTAL BY THE CITY MANAGER RECOMMENDATION: Adopt resolution ATTACHMENTS: Description Upload Date Resolution 12117/201 o r Memo Type 2 D Cootract 17/1712012 avirrdcl