HomeMy WebLinkAbout1974-1718 PEDESTRIAN MALLORDINANCE. NO. f7a
AN ORDINANCE adopting a plan for the establishment of a pedestrian
mall.
WHEREAS, R.C.W. Chapter 35.71 vests authority in the City to
establish pedestrian malls and requires, in considering the establish-
ment of a pedestrian mall that a plan therefor be formulated and
that a public hearing be held on such plan, and
WHEREAS, the City has caused a plan to be formulated for the
establishment of a pedestrian mall in the downtown area of the City,
and
WHEREAS, on October 21, 1974, the Yakima City Council did adopt
Resolution No. D-3200 fixing November 12, 1974, as the date for a
public hearing on such plan, all pursuant to and in accordance with
applicable laws, and
WHEREAS, pursuant to such Resolution No. D-3200, and after due
notice in accordance with applicable laws, the City Council held a
public hearing on November12, 1974, to consider such plan; and as
a result of such public hearing, the,City Council finds and deter-
mines that the public interest, safety and convenience will be best
served by the establishment of such a mall that the vehicular traffic
will not be unduly inconvenienced thereby, that property abutting
on and in the vicinity of the mall will benefit from its establishment,
that the plan for establishment of such a mall is consistent with
the intent of the General Plan of the City of Yakima as heretofore
adopted, and that the such a mall should be established, now, therefore,
BE IT ORDAINED BY THE CITY OF YAKIMA:
Section 1. That the plan to acquire, construct and finance off
street parking facilities, improvements to pedestrian spaces and
general improvements in the central business district, as prepared
by N. G. Jacobson & Associates, Inc., in a report dated September,
1974, and now on file with the City, is hereby approved.
Section 2. This ordinance shall be in full force and effect
30 days after its passage, approval and publication as provided by
law and by the City Charter.
PASSED BY THE CIT COUNCIL, signed and approved this
glib
daY o / .1100%/Wed 974.
ATTEST:
•
Mayor
• ••• • • • •• . • • ••
• •
•
•
. •••• .•• . • • , •
, • . • • •
YAKIMA, WASHINGTON
•
C.B.D. PARKING
& GENERAL IMPROVEMENT
PROGRAM SUMMAR
• PARKII\G. ANALYSIS..
• PARKING & GENERAL IMPROVEMENTS• • ..s.•••••••••••,,
• BUDGET •COST ESTIMATES •
• FINANCING •• ••••• !•••••••••••:•••••••••:•••••••:......: •;•••• • ••• •
• • PRELIMINARY • ASSESSMENT .RQL
..::•••• • .PARKING '
..•
•
•
• .
,0 lice of the Mayor
CITY OF YAKI A
April 25, 1974
Dear Property Owner:
CITY HALL, YAKIMA, WASHINGTON 98901 Phone: (509) 248-2620
We are pleased to announce that the proposed Central Business
District Improvements Report is now completed and ready for
review. Please find enclosed a summary of that report.
Two informational meetings are scheduled for presentation
of the full report on --
Tuesday, May 7, 1974 - 10:00 a.m.
and
Wednesday, May 8, 1974 - 7:30 p.m.
Both meetings will be held in the Capitol Theatre at 19 South
Third Street in Yakima.
The purpose of the -meetings is to familiarize you with the
proposed project, answer your questions, and receive sugges-
tions for changes or improvements to the plans.
BERT BROAD
Mayor
LEE SEMON, JR., CI&irman
Downtown Advisory
Redevelopment Commission
Yakima, Washington
CBD Parking
& General Improvement Program
April, 1974
CITY COUNCIL
Bert Broad Mayor
Wray Brown
Betty Edmundson
W. K. "Pete" Moore
Charles Rich
Don Schussler
Bill Whitaker
DOWNTOWN ADVISORY REDEVELOPMENT COMMITTEE (DARC)
CITY STAFF
Lee Semon, Jr.
Gus Williams
Mike Mercy
Bruce Beaudoin
Adolph Frank
Vern Halversen
Thomas Hargis, Jr., AIA
Herb Hill
Craig McMicken
Jay Otto
Richard Hill
D. Larry Wright
PRINCIPAL CONSULTANT
N. G. Jacobson &
Associates, Inc.
ARCHITECTURAL CONSULTANT
Doudna.Williams, AIA
URBAN DESIGN CONSULTANT
Henry Steinhardt, AIA
Chairman
1st Vice Chairman
2nd Vice Chairman
Cliff Miller
Al Pruett
Hans Skov
Richard Tweten
Ed Wissman
City Manager
Director of Community
Development
Principal Planner
Associate Planner
(CBD Project Coordinator)
Consulting Engineers
Seattle, Washington
Architects
Yakima, Washington
Architect/Urban Designer
Mercer Island, Washington
N. G. JACOBSON & ASSOCIATES, INC.
CONSULTING ENGINEERS
414 Skinner Building is Seattle,Washington 98101
Phone: (Area Code 206) 624-7863
April 24, 1974
City of Yakima
City Hall
Yakima, Washington 98901
Attn: Mr. Craig McMicken, City Manager
Gentlemen:
RE: CBD Parking and General Improvement Program
We are pleased to submit our report on the CBD Parking and General
Improvement Program which proposed on- and off-street parking improve-
ments and general improvements for the CBD that in our opinion will help
revitalize the downtown. This concludes the work that was authorized in
your November 2, 1973, letter and modified in your April 4, 1974, letter.
We would like to thank the DARC Committee and the City staff for the
considerable amount of time, effort, inputs, and cooperation which every-
one gave to make this report possible. We would especially like to thank
Mr. Lee Semon, Jr., Chairman, and the other members of the DARC Committee,
who attended many meetings in order that we could present our ideas and
could receive the benefit of their recommendations as to what they felt
was best for the improvement of the CBD. Mr. Craig McMicken, Mr. Jay Otto,
and Mr. D. Larry Wright were among the many people on the City staff who
gave us a very considerable amount of help and gathered much of the data
on which this study was based.
Foster and Marshall, Inc., financial consultant for the City of Yakima,
was consulted for current bond interest rates. Mr. Richard Thorgrimson
and Mr. Forrest Walls of the firm Preston, Thorgrimson, Ellis, Holman &
Fletcher, the City of Yakima bond counsel, have reviewed the proposed
assessment program.
City of Yakima
Page 2 April 24, 1974
Our recommendations include the implementation of the following capital
improvements:
General CBD Improvements
Strdet trees, intersection treatments $ 673,750
General Alley Improvements
Paving, canopies, lighting
Off -Street Parking Improvements
Parking Lot 1 - paved, lighted, landscaped
Parking Lot 2 - paved, lighted, landscaped
Parking Lot 3 - lighted, landscaped
Total Improvements for L.I.D. Financing
General CBD Improvements Proposed for
Municipal Funding
Street lights and signalization, plazas,
waste receptacles, bus shelters
Total Improvements Proposed
646,250
652,000
1,407,825
191,875
$3,571,700
467,500
$4,039,200
Property owners within the proposed CBD Local Improvement District will
benefit considerably from the proposed improvements. The general improve-
ments will answer many of the needs of the CBD and will enhance its appear -
for both customers and employees; today there is insufficient parking to
meet present needs. The proposed improvements closely follow and largely
implement the CBD plan that was adopted by the Yakima City Council in 1967.
Unlimited free customer parking under a centralized parking management is
recommended for the enforcement of the parking program and the control of
paid monthly parking. City management of CBD on- and off-street parking
under this centralized parking program will help relieve many of the present
parking and business problems in the downtown. It is recommended that the
operating cost of this program be paid for by downtown businesses using an
annual levy.
City of Yakima
Page 3 April 24, 1974
Philip Keightly, who is project manager for this study, and I will be happy
to give further assistance to the City of Yakima as needed for explanation
and implementation of the proposed program and in the final design of the
improvements.
We have enjoyed doing the work in developing this program and look forward
to seeing its implementation in the near future.
Very truly yours,
N. G. JACOBSON & ASSOCIATES,
N#man G. Jacob
President
NGJ:sh
Enclosures
).
TABLE OF CONTENTS
Page
Description
1
INTRODUCTION
4
Drawing 1, Existing CBD Buildings & Parking Stalls
5
Analysis
7
Proposed Improvements
8
Plate 1, Yakima CBD Proposed Improvements
10
Financing
12
Assessment
16
Plate 2, Assessments in Dollars per Square Foot
17
Operations
19
RECOMMENDATIONS
19
_ Analysis .
21
General CBD Improvements
25
Parking Improvements
26
Financing
27
Operations
29
Implementation
1
.,, ..........;•,e......:;•:......Z., ' ' •
1
I SUMMARY
INTRODUCTION
The Yakima CBD serves a large market area that is mostly without
public transportation. The automobile is, therefore, the dominant
means of transportation and is likely to be in the near future. The
increased use of the automobile has created traffic congestion in
the streets of Yakima and has overloaded available parking in the
CBD.
The City arterial street plan presently being implemented will solve
much of the traffic congestion problem. However, it is not until the
planto route traffic on Yakima Avenue around the CBD is implemented
that the CBD will be able to change from its present automobile domina-
tion to become a pedestrian oriented area.
This study recommends a scheme to provide sufficient parking to relieve
the parking problem in the CBD. It also recommends other improvements
that are needed to create a more attractive and vital downtown and to
help reverse the trend of businesses moving out of the CBD.
The CBD should have a visual identity and distinctive character of
its own. This can be done by having a uniformity of street trees,
new lighting, street furniture, and signing throughout the CBD. The
trees will also add color and shade to the sidewalks and visually
reduce he width of the streets. The physical width of the streets
needs to be reduced at intersections for pedestrian safety by designing
2
YAKIMA AVENUE
• t.
The heavy through traffic on Yakima Avenue bisects
the CBD, reduces pedestrian safety, takes away
possible on -street parking, and does little to
encourage drivers to get out of their cars and
become customers of CBD businesses.
3
intersection treatments which will also help make the CBD more pedes-
trian oriented.
A pedestrian circulation system is needed that incorporates the alley-
ways, which at present appear cluttered, dingy, and dirty. These alleys
provide an exciting potential for use as bright, colorful, covered
pedestrian walkways connecting parking areas to other parts of the CBD.
Plazas on 2nd Street on both sides of Yakima Avenue are needed to give
a focal point in the center of the CBD. These should be places that
people enjoy being in, where they can meet friends, watch children
play, sit on benches in the shade of trees, and be a place for such
events as outdoor art shows. These plazas will highlight the intended
pedestrian nature of the CBD.
New off-street parking lots should have plenty of trees to give shade
to people and cars and also to reduce the visual expanse of the parking
areas. Parking lots can be made both attractive and functional.
Drivers who enter the CBD should be quickly directed to areas with
sufficient parking near where they want to go. People can only become
a client or customer of CBD businesses once they are out of their cars.
Once on foot, peoplemeed to be able to walk safely, quickly, and
comfortably to their destination. This can be achieved by having
pleasing surroundings with shade in summer, shelter in winter, and
adequate light at nighttime. People must also feel free to stroll
J. II 1.1 1.3
- • r.• r".
. 11...
&JACKS AVE.
10
pt11.46,01.1
I ;!•-:
. ..........S. NAH AVE,
40P!,!!'; • Sti fj
41 li:.
° • 'I r
... L -....j. r Ji,...i...1.7...7-171-Lt..1.7,"4191...........„,
1. 1 r: —1....t ' - Fri 1. rj-•-•—•*""'
i j ' * 1 ;.., •j-' '1- -":"""
,...,
4th'
•
754,-7-'•"""- ........ - • r
r1,4
0114,411.1
...414.11,41 atom
mutIJAJ +ape.
......
• 70 • .1
tjb TY • ,
a.
k4046,.!
LjJL
T.'
• s•,, •sfir
• - • - ••• •
,
r
j °ih
14 P
••
; !LI 91! ;•!;!, j,„.
11; . ; !
• • • j•ia•M• •;;1- -17•116•M ;•-1-•'• ................. •
GMr
•••
h MP
111-1117—'="
Lr .
1 rjL,!!!
.-7••• •!!!!./tm
-om
T.
S. 1st ST
° •111•1•.10 ahem...
Jw
1 --- .
ir
• :7t -.111T.
Vtal dtrw:
...... 1-JyyJyyyyyyy,
N. G. Jacobson & Associates, Inc.
‘ting — ere
LEGEND
NUMBER OF
PARKING SPACES
P PRIVATE PARKING
METERED PARKING
Y2 HOUR METER
ALL OTHERS 2-4 HR )
EXISTING C.B.D. BUILDINGSIiisic STALLS
1
5
around and to chat with friends when they are not in a hurry. The
creation of a stimulating visual and physical environment in the CBD
can be achieved by careful architectural and landscaping design.
These key elements are needed to achieve a more vital CBD and to
encourage people to return to conduct their business, shop or visit
restaurants and places of entertainment. This report recommends capital
improvements that incorporate these key elements and a method of financing
to carry them out. It is intended to be the foundation of a practical
action plan that is needed to implement the proposed improvements,
which closely follows and in fact implements the CBD plan adopted by
the Yakima City Council in 1967.
Throughout the development of the proposed improvements, the consultant
met with DARC Committee members and City staff to discuss and modify
proposed improvements to best meet the needs of the public, businesses,
property owners, and the City. General consensus was reached on what
should be proposed. The report and its conclusions have, therefore,
in general been agreed upon by DARC Committee members and the City staff.
Analysis
The parking needs of the CBD derived have been based on a comprehensive
analysis of downtown parking with each block analyzed separately. The
surplus or deficiency of parking in the downtown was first calculated
and then divided up so that this surplus or deficiency for customer
and employee parking could be analyzed separately in each block.
Parking that is presently available is shown on Drawing 1.
6
An overall deficiency of 1,171 parking stalls was found for the CBD.
This indicated that there was a considerable parking problem. The
blocks on either side of Yakima Avenue between 1st and 4th Streets
have the greatest deficiencies of parking in the downtown with the
greatest single deficiency. in Block 50. Some surplus parking was found
in the north, east, and south corners of the CBD.
The extent of the problem was best identified by looking at the cus-
tomer and employee parking requirements. It was found that 149 employee
parking stalls were required in the whole CBD area with the greatest
need for employee parking near the center of the CBD itself. There
was a customer deficiency of 583 stalls in the CBD. This deficiency
was almost entirely caused by the blocks on Yakima Avenue between 1st
and 4th Streets. There is, therefore, a need for a total of 732 stalls
in the center of the CBD.
After careful analysis of areas in the downtown that may be available
for off-street parking improvements, it was concluded that improve-
ments should best be made at Parking Lots 1 and 2 as shown on Plate 1.
These two lots provide an additional 398 off-street parking stalls in
the area. This, together with 87 on -street parking stalls provided
by center street or diagonal parking, give a total of 485 additional
parking stalls in the CBD.
Since Parking Lots 1 and 2 require the demolition of buildings, the
parking demand decreases by the amount of parking demand that those
buildings generated. This parking demand, based upon full utilization
of these buildings, amounts to 237 parking stalls; this gives a net
7
•
increase of 237 stalls in the CBD. The total number of additional
parking stalls made available by proposed parking improvements is
722 stalls. Because only 732 stalls are required to correct existing
parking deficiencies, it appears that the proposed parking will be
almost sufficient to meet present parking needs.
This additional parking was divided such that there will be 148 employee
stalls and 574 customer stalls added to the downtown. This means that
the improved parking lots with the present distribution will have about
25% of their spaces taken up by monthly employee parking, which provides
for expansion of short-term customer parking in the future.
Proposed Improvements
Plate 1 shows the location and kinds of improvements proposed.
The estimated $673,750 in general CBD improvements to be financed by
L.I.D. improvements bonds include the planting of street trees in all
sidewalks in the CBD, the placement of irrigation to all street trees,
major street furniture, signing, and intersection treatments that
use pedestrian -textured paving at intersections and crosswalks and
such techniques as changing the location of corner curbs or placing
pedestrian islands to reduce the width of the streets that the pedes-
trian has to cross so as to improve pedestrian safety.
The $467,500 in general CBD improvements for municipal funding include
new street lights and traffic signalization, the 2nd Street plazas on
8
N. G. Jacobson & Associates, Inc.
Consulting Engineers
... .0. •**. .. *It
XI •
6
.4
..,
YAKIMA
MALL
---
• AI ft* *. 111.F.
.41.114, • it
01[110441$*!***Itti4
It
S***********0
LEGEND
•
INTERSECTIONS
PLAZA
X**4.1 WWW411
PARKING
LIGHTING
TREES
89 BLOCK N9
muffin@ ALLEYS
E. YAKIMA AVE.
200
scale
0
HI 3rd STREET
(...\ SITE FOR FUTURE CONVENTION
) CENTER ABOVE PARKING
400
feet
YAKIMA C. B. D. PARKING IMPROVEMENTS
YAKIMA C.B.D. PROPOSED
IMPROVEMENTS
PLATE
9
both sides of Yakima Avenue, waste receptacles that are now required
by recent legislation, and bus shelters on Yakima Avenue. The design
of the lighting needs to be used to help establish the unique character
of the downtown. The undergrounding of street light wiring should be
done at the same time as the placement of irrigation lines for street
trees to save cost. The plazas include pedestrian -textured paving,
trees, planters, irrigation, and various items of street furniture
and are intended to be designed so that they become a focal point of
the downtown.
The $646,250 cost of general alley improvements in Blocks 30, 31, 50,
51, and 71 are for financing by L.I.D. improvement bonds by assessing
the improvement costs to all property owners in these blocks. The
improvements include pedestrian -textured paving, lighting, canopies
for shadelin summer and protection from rain and snow in winter,
general improvements and some improvements to the appearance of over-
head utilities. These improvements will make the alleys colorful,
bright, cheerful and safe places to walk in and could encourage business
to put in alley entrances to their stores or even establish businesses
that only face the alleys.
The general alley improvements include $155,000 to improve alley
utilities; the estimated additional cost to underground all alley
utilities is $670,000. Alley utility undergrounding is recommended
if property owners abutting alley improvements wish to pay for these
improvements. These costs have not been included in proposed assess-
ments in the CBD.
10
The intent of proposed off-street parking improvements is to provide
convenient parking in pleasing surroundings with trees to provide
shade for people and cars. The improvements proposed are intended to
minimize costs and maximize the benefits from them.
Parking Lots 1 and 2 contain 161 and 398 parking stalls respectively.
Their locations are shown on Plate 1. They both require the demolition
of existing buildings, the filling of basements, asphalt paving,
drainage, trees and landscaping with irrigation, safe levels of lighting,
and such miscellaneous items as signing. Parking Lot 3 contains 52
parking stalls and only requires minor portions of these improvements
as it is an existing paved parking lot; the improvements primarily
are for landscaping, trees, and associated installation costs.
The estimated cost of Parking, Lot 1 is $652,000 which includes $195,250
in construction costs and $456,750 for property acqUisitions. The
estimated cost of Parking Lot 2 is $1,407,825 which includes $474,375
in construction costs and $933,450 for property acquisitions. The
estimated cost of Parking Lot 3 is $191,875 which includes $34,375 in
construction costs and $157,500 for property acquisition. The cost
per stall of lots 1, 2, and 3 is $4,050, $3,537, and $3,690 respectively.
Financing
The most suitable method of financing the proposed improvements was
found to be through the use of Washington State Pedestrian Mall legis-
lation under Chapter 35.71. This law has already been used to put in
11
the center -street diagonal parking on 2nd Street; the two-hour free
parking and this method of parking appears to have been well received
by customers and businesses.
This law allows the change of the CBD from a vehicle -dominated area
to the pedestrian use of the streets. It also allows the formation
of L.I.D.'s under Title 35 legislation to finance improvements.
Municipal funding for improvements can include general obligation bonds,
general fund, and other available monies.
The $467,500 in general CBD improvements for street lights and traffic
signalization, plazas, waste receptacles, and bus shelters are for
municipal funding..
The $3,571,700 in improvements for general CBD improvements, general
alley improvements,'and off-street parking improvements need funding by
L.I.D. improvement bonds, which are likely to be sold at about a
7-1/4 percent interest rate for a 20 -year period.
12
Assessment
The assessment method used is one that spreads the various proposed
improvement costs to property owners in the assessment district in
accordance with the benefits they receive from these various improve-
ments. The best method to do this was found to be to develop five
separate assessment rolls for each kind of improvement and distribute
the costs of an improvement only to those properties which benefited
by that particular improvement. All assessment costs were distributed
on these five assessment rolls in accordance with the property area
of the assessable parcels of land within the assessment district.
Four of these separate assessment rolls were then combined into a
Summary Assessment Roll for the total CBD improvements proposed.
Assessment Roll 1 is for general CBD improvements in the amount of
$673,750. These improvements include street trees with irrigation
and intersection improvements• and are proposed for the whole of the
CBD. Since all properties benefit equally from the improvements,
the costs are distributed equally to all assessable properties based
on their square footage of property area. These assessments are
$0.41 per square foot.
Assessment Roll 2A is for general alley improvements in the amount of
$646,250. These improvements are proposed for Blocks 30,31, 50, 51,
and 71. The costs of these improvements are distributed equally to
all assessable properties with these blocks. The assessments are
$1.76 per square foot of property area.
13
Assessment Roll 2B is for the undergrounding of alley utilities in
the same blocks as Assessment Roll 2A. The $670,000 cost for these
improvements and the $1.83 per square foot assessment cost is not
included in the summary assessment roll as these improvements are
not recommended for construction at this time.
Assessment Roll 3 is for the 2nd Street parking improvements in the
amount of $2,059,825. In order that only those properties that receive
benefit from the improvements are assessed, the assessment district
for this assessment roll only included the blocks on both sides of
2nd Street and properties generally facing the improvements
The total amount of benefit a property within the assessment district
for Assessment Roll 3 receives from the proposed 2nd Street parking
improvements is proportional to the amount of benefit received from
each of three significant kinds of benefit. Property assessments
are based on these three benefits, which are general benefits, distance
benefits, and parking benefits. The costs associated with these three
benefits are distributed separately to the assessable properties in
this assessment district as follows:
GENERAL BENEFITS are assessed at one-third of the total 2nd Street
parking improvement costs which is $686,609. Since the general
benefits are received equally by all properties, all assessable
properties within this assessment district are equally assessed
general benefit costs.
14
DISTANCE BENEFITS are assessed one-third of the total 2nd Street
parking improvement costs which is $686,608. The amount of benefit
received by a property bears a direct relation to the distance the
property is from the proposed parking improvements. The distance
benefits received by properties is obtained by using 100, 67, and
33 percent distant benefit zones. The square footage obtained by
multiplying the property area square footage by the distance percentage
zone of the property is used to distribute the distance benefits cost
to all properties within this assessment district.
PARKING BENEFITS were assessed at one-third of the total 2nd Street
parking improvement costs which is $686,608. These are benefits
received by a parcel of property from the parking added by the improve-
ments. If a parcel has no off-street parking, it will receive a
large amount of benefit from the parking improvements and vice versa.
The amount of parking benefit is obtained by using 100, 67, and 33
percent parking benefit zones. Credit is given for existing off-
street parking by deducting 300 square feet for each off-street parking
stall provided from the total property square footage; the remaining
square footage was multiplied by the parking benefit percent zone to
give the actual square footage assessed for parking improvements.
Parking benefit.costs were distributed to all properties in proportion
to these resulting square footages.
Assessment Roll 4 is for the 4th Street parking improvements in the
amount of $191,875. Only those properties that receive benefit from
15
these improvements are assessed. The assessment district for Assess-
ment Roll 4 is, therefore, limited to the blocks on both sides of
South 4th Street from East Yakima Avenue to East Walnut Street. The
method of assessment is identical to Assessment Roll 3.
Assessment Roll 5 is for the purchase of the Yakima Mall Parking
Garage using a purchase price of $2.9 million. The costs are distri-
buted to properties in Blocks 70 and 90 as these are the only properties
that would receive significant benefit from the purchase of the Garage.
The method of assessment used is the same as for Assessment Roll 3.
The $9.45 per square foot assessment cost for People's Store and
$11.45 per square foot assessment cost for other Mall properties was
felt to be unreasonable for the benefits obtained. Therefore, the
Yakima Mall Garage purchase is not included in the Summary Assessment
Roll and is not_recommended forpurchase• at this time unless the
property owners should wish to make the purchase.
The Summary Assessment Roll is the sum of the total assessment costs
for each piece of property or parcels of property on Assessment Rolls
1, 2A, 3, and 4. The total estimated cost of all improvements that
are distributed to properties within the CBD is $3,571,700. See
Plate 2 for the approximate total assessment in dollars per square
foot of property area in the CBD.
16
N. G. Jacobson & Associates; in.
Consulting Engineers
.4erairAr,iir
?f•e'
W.......
0.0.4...
.440.9*0
....0.0.
00000.0.
000000.0
*0000000*
*04.0.000
44440*
***4..,*
LEENID
r
40**0
4****
0.41 $/SQ. FT.
0,4.2 — 1.49 VSQ.
1.50 — 2.99 55/5Q. FT.
3.00 —4.49 V561. FT.
4.50 — 6.18 5/sq. FT,
PROPOSED PAR.KINCI IMPROVEMENTS
mim
ASSESSMENT DISTRICT BOUNDARY
200
scale
0
400
feet
NOTE
THESE ASSESSMENT COST
ZONES ARE ONLY APPROX..
SEE ASSESSMENT ROLL
FOR ACTUAL ASSESSMENTS
IN /SQ. FT.. THE SQ. P.7,
IJSE IS THE ASSESSAELE
PROPERTY AREA WITHIN
THE ASSES5MENT
YAKIMA C. B. D. PARKING IMPROVEMENTS
ASSESSMENTS IN
DOLLARS PER SQUARE FOOT
PLATE 1
2
17
Operations
All -day free parking for clients and customers of downtown businesses,
two-hour free parking for employees, and carefully regulated monthly
parking in off-street parking lots is proposed for the downtown using
centralized parking management.
Parking checkers would record the license plate number, location, time,
and date of all cars that park for more than two hours in the downtown;
this data would be processed and fed into the City's computer, which
would summarize the number of times a particular license plate number
was noted over a predetermined period of time. If for example, a car
with a particular license plate was found to park for more than two
hours every day in the downtown, it is most unlikely this person would
be a shopper. On the second violation, a fine of up to about $25 could
be cited against the owner of this particular vehicle.
The rates for monthly parking in downtown lots could vary from about
$5 to $15 per month depending upon location, with higher rates in the
most central locations. The number of monthly parkers allowed in these
lots could also be varied to adapt to changes in their use by customers
and employees and also to allow more customer parking at Christmas.
The City should manage as many private off-street parking lots as
possible for the property owners under some lease agreement to improve
control over downtown parking.
A new City Council appointed "pedestrian mall organization" or the
existing DARC Committee should be directed to establish and recommend
the basic procedures and guidelines for the centralized parking management.
A City staff person should be appointed to manage downtown parking and
18
to supervise a private parking operator who employs the parking checkers.
It is estimated that the monthly operating costs of .the centralized
parking management would be about $13,800. This does not include the
lease of off-street parking lots. However, these lease costs would be
largely offset by the revenues from monthly parking fees.
A levy is being assessed at present for downtown parking enforcement
based on the number of employees that are employed by downtown businesses.
Using this same method, the levy for the operating costs of the centralized
parking management would be $45.25 per year per employee.
19
RECOMMENDATIONS
Analysis
1. Every effort should be made to more fully utilize the Yakima Mall
Parking Garage. Actively promote monthly parking. Devise programs
to promote the use of the garage. Encourage the Mall to offer free
parking to its customers in conformity with the proposed CBD plan
for municipal parking.
2. Parking is badly needed on either side of Yakima Avenue between
1st and 4th Streets, especially in Block 50, to relieve the large
deficiency of parking'spaces in this area.
3. It is necessary to preserve the parking behind the Capitol Theater
and beside the Pacific National Bank on 1st Street as these two lots
are both in blocks that already have a considerable deficiency in
parking spaces. If in the future these two parking lots are being
considered for uses other than parking, they should be purchased
so as to preserve them for. parking.
4. The City of Yakima should consider the removal of approximately
29 meters near the intersection of East Lincoln Avenue and North
Front Street, and approximately 27 meters outside the core area
on South Naches Avenue and East Walnut Street near their inter-
section. These meters are under-utilized. The parking spaces could
be made available for all day parking without harming nearby businesses.
5. Consider restricting the all -day parking of approximately 27 on -
street parking stalls near the YWCA because of the considerable
deficiency in the area. This parking restriction could be achieved
by including the area in the proposed centralized management of CBD
parking.
20
TRAFFIC/PEDESTRIAN CONFLICTS
Yakima Avenue and 3rd Street have
heavy traffic and, like all CBD
streets, are wide. This reduces
pedestrian safety and discourages
people from crossing streets and
from walking around the CBD to shop
or conduct business. Intersection
treatments are needed to increase
pedestrian safety and to encourage
people to leave their cars and walk
around the CBD in comfort and in
pleasing surroundings.
21
General CBD Improvements
1. The CBD should be designated as the area bounded by Naches Avenue,
East Walnut Street, 1st Street,and East "A" Street.
2. Develop an attractive environment with a unifying theme that gives
the CBD a visual identity and a distinctive character of its own.
When people drive near the CBD they should be able to say, "Oh,
there is our downtown." Do this by establishing uniform design
standards for all CBD street trees, street furniture, lighting, and
signing. Develop a signing ordinance for the CBD.
3. Complete the city arterial plan as soon as possible so that CBD
traffic on Yakima Avenue can be considerably reduced by encouraging
traffic to circulate around the CBD.
4. Design systems for CBD traffic circulation and for signing and
routing that enables drivers entering the CBD to be quickly directed
to parking areas within it.
5. Design a pedestrian circulation system that includes the use of
alleys to allow people to move freely, safely, and conveniently
from parking areas to their destination in the CBD. Develop special
intersection treatments to make pedestrian crossings safer.
6. Study vehicle and pedestrian circulation elements and movements data
to propose integrated traffic and pedestrian circulation systems
that minimize points of automobile traffic and pedestrian conflict.
Change the CBD from being vehicle dominated to a pedestrian
oriented area.
7. Propose that the air rights over Parking Lot 2 be made available
for a future convention center providing grade level parking is
still available underneath the building.
WHAT CAN BE DONE TO THE CBD
Naches Avenue is a splendid
example of how trees add great
beauty to a street.
Alleys presently appear
cluttered, dingey and dirty
and do not invite pedestrians
to use them. The alleys offer
the CBD an exciting potential
for use as bright, colorful
pedestrian covered walkways,
joining parking areas to
businesses, adjacent alleys,
and to distant blocks.
8. Finance the installation of street trees and intersection improvements
with $673,750 in L.I.D. improvement bonds. All assessable properties
within the CBD should be equally assessed $0.41 per square foot of
property area for the cost of these improvements since all properties
receive equal benefit from them.
9. Municipally fund the $467,500 in proposed improvements for new street
lights and traffic signalization, plazas, waste receptacles and bus
shelters on Yakima Avenue. Underground street light wires by using
the same trench as that used to install the irrigation for street
trees.
10. Finance the $646,250 in proposed general alley improvements for
pedestrian-textured paving, canopies, lighting, general and utility
improvements using L.I.D. improvement bonds. The cost of alley
improvements should be equally assessed to all properties that abut
on these improvements.
11. Develop an ordinance to restrict deliveries in improved alleys in
the CBD to early morning and evening hours so that pedestrians may
move freely and safely in them during the day.
12. The undergrounding of overhead utilities is only recommended for
inclusion in proposed improvements if property owners abutting the
alley improvements should agree to spend the $670,000 that is over
and above the cost of general alley improvements to do this work.
13. Bus ridership and an enlarged public transportation system should
be encouraged so that fewer people will drive downtown and more
valuable downtown parking spaces will be available. The use of such
programs as allowing stores to sell discounted books of bus tickets
to encourage ridership is recommended.
24
YAKIMA MALL GARAGE
The Yakima Mall Parking
Garage has about 1200
off-street parking stalls.
The parking analysis showed
that this facility was
about the correct size to
accommodate the parking
needs of businesses in the
Mall block and was, there-
fore, of no great benefit
to surrounding properties.
25
Parking Improvements
1. Design and install the 161 -stall Parking Lot 1. See Plate 2 for
the location of proposed parking lots. The total estimated cost of
Parking Lot 1 improvements is $652,000; finance the cost of these
improvements with L.I.D. improvements bonds by assessing benefited
properties.
2. Design and install the 398 -stall Parking Lot 2. Finance the
$1,407,825 cost of Parking Lot 2 improvements with L.I.D. improvement
bonds by assessing the cost against benefited property owners.
3. Design and install the 52 -car Parking Lot 3 improvements. Finance
the $191,875 cost for Parking Lot 3 improvements with L.I.D.
improvement bonds by assessing the costs against benefited property
owners.
4. Design and complete Center Street parking improvements for 2nd Street.
Design and install Center Street parking improvements on South 4th
street from Yakima Avenue, to East Walnut Street.
5. Carry out careful analyses of Yakima Avenue and 3rd Street and then
design special treatments to best suit both the long- and short-range
objectives for the use of these heavily traveled streets.
6. Since it appears from the parking analysis that the parking needs
of businesses within the Yakima Mall block should be approximately
equal to the parking supply within the block, there will be no
significant benefit derived by surrounding properties from the
parking provided by the Yakima Mall Garage. The purchase of the
Yakima Mall Garage, therefore, must be assessed against properties
within the Yakima Mall block as these are the only properties that
26
receive significant benefit from the purchase. If a $2.9 million
purchase cost is used, the assessment for the properties in the
Mall block would be approximately $11 per square foot of property
area. The purchase of the Yakima Mall Garage is only recommended
if property owners within the Yakima Mall block should petition
the City Council for the purchase at an agreed price with the Mall
Corporation.
Financing
1. Washington State Pedestrian Mall legislation in Chapter 35.71 should
be used to change the CBD from an automobile -dominated area into
a pedestrian -oriented area. This will allow Center Street parking.
Second Street has already been designated as a pedestrian mall
under this legislation when the existing Center Street parking was
carried out.
2. Finance $3,571,700 of proposed improvements by using L.I.D. improve-
ment bonds for 20 years. This is comprised of $673,750 for general
CBD improvements that include street trees with irrigation and
intersection treatments, $646,250 for general alley improvements,
and $2,251,700 for proposed off-street parking improvements.
3. Municipally fund $467,500 in general CBD improvements under the
Pedestrian Mall legislation which allows the use of such financing
methods as general obligation bonds, and general fund and other
available monies.
4. Distribute L.I.D. assessment costs to all assessable properties in
the CBD in accordance with the amount of benefit received by these
properties from proposed improvements as recommended in this report.
Operations
1. Direct a new "pedestrian mall organization" or use existing DARC
Committee to establish and recommend basic operating procedures and
guidelines for the centralized management of all on- and off-street
parking in the downtown.
2. Institute a parking program goal that offers unlimited free parking
for the customers and clients of downtown businesses; two hours
free parking to employees, employers, residents, and hotel and
motel guests; and provides paid monthly parking with rates that increase
from $5 to $15 depending on how near the parking is to the center
of the CBD. Use fines of about $25 for parking offenders who have
already received a warning for their first offense.
3. Use a City staff person to manage the operations program and to
supervise the parking operator who employs the parking checkers.
4. Finance the parking operation program using an annual levy against
businesses in the downtown and distribute costs in proportion to the
number of employees that each business employs. This method of
levy is presently being used in the CBD to pay for parking enforce-
ment costs in the area.
5. The City should attempt to control as much off-street parking in
the downtown as possible. This may require the need to enter lease
agreements with property owners in order to manage their parking
lots.
6. Implement the operating program proposed even if the capital improve-
ments proposed in this report are not carried out.
28
IMPROVING THE CBD
On 3rd Street there is the historical Capital Theater and
the Federal Building, both of which are Yakima landmarks.
Trees in front of the Federal Building add beauty. Some
treatment is needed to reduce the apparent width of this
and other CBD streets, to add shade from the sun for
pedestrians and cars, and to give safe but attractive
lighting at night.
Some businesses are already using architectural effects
and landscaping to enhance their buildings and parking
areas. The overhead wires in the alleys spoil the effect.
29
Implementation
1. Proceed with the legal steps required to complete the L.I.D.
financing recommended and resolve the method of funding improve-
ments that are recommended for municipal funding.
2. Direct the new "pedestrian mall organization" or the existing
DARC Committee to carry out Recommendation 1 under Operations.
3. Select an architectural -engineering design team to formulate a
practical action plan that would include the integrated design of
CBD, vehicular, and pedestrian circulation plans; establish archi-
tectural design standards for CBD street trees, street furniture,
lighting, and signing to give the CBD a distinctive character of its
own; draft an amenity program to locate plantings, street furniture,
lighting, canopies, etc.; carry out parking planning all the way
through to preliminary design; and make cost estimates of proposed
improvements.
4. Carry the action plan into final design and construct the proposed
improvements.