10/13/2026 07.B. Resolution - accept Change Order 004 with Interwest Construction Inc. for Nelson Pipeline Phase 2
!, ift7-'-''.... . 1:.:',4) � F BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEMENT Item No. 7.B. For Meeting of: October 13, 2026 ITEM TITLE: Resolution authorizing the City Manager to accept Change Order 004 with Interwest Construction Inc. for Nelson Pipeline Phase 2 SUBMITTED BY: Scott Schafer, Public Works Director *Daniel Tiliano, Water/Irrigation Manager SUMMARY EXPLANATION: Change order 004 updates the Phase 2B contract to correct the original contract amount, incorporated a July 2026 sales tax rate increase, and revise project schedule requirements. It establishes a new milestone date, extends overall contract time to accommodate funding availability, and adjusts Phase 2B scope due to necessary changes in pipeline alignments as well as coordination between Yakima County and WSDOT. Additional labor, equipment, and material costs are included to address construction challenges along Powerhouse Road. Retainage provisions are updated to reflect the contractor's retainage bond for the Nelson Phase 2 project. ITEM BUDGETED: Yes STRATEGIC PRIORITY 24-25: A Resilient Yakima RECOMMENDATION: Adopt Resolution. ATTACHMENTS: Resolution_accept change order 004 w Interwest Construction Inc_Nelson Pipeline Ph2 City of Yakima Change Order 004.pdf Nelson Dam Removal PH2 - Change Order 004.pdf 23 RESOLUTION NO. R-2026- A RESOLUTION authorizing the City Manager of the City of Yakima to accept Change Order No. 004 for the Nelson Dam Removal Phase 2 Project (Contract No. IC2010), with Interwest Construction, Inc., in the amount of$1,333,123.03 (including sales tax), and approving the modifications to the contract price and contract time as outlined in the Change Order. WHEREAS, the City of Yakima ("City") previously entered into Contract No. IC2010 with Interwest Construction, Inc. for the Nelson Dam Removal Phase 2 Project; and WHEREAS, Change Order No. 004 was issued on September 22, 2026, to incorporate necessary modifications to the contract including a correction to the original phase 2B contract amount, a sales tax rate adjustment, revision scope of work associated with CPR 008 (Powerhouse Road Pipeline Realignment), and adjustments to contract times; and WHEREAS, Change Order No. 004 provides for: • Correction of the original Phase 2B contract amount by $2.00, from $2,729,160.17 to $2,729,162.17; • Incorporation of the Washington State and local sales tax rate increase to 8.6% effective July 1, 2026; • Approval of CPR 008Rev-Powerhouse Road Pipeline Realignment in the amount of$1,220,590.26(excluding sales tax); • Application of sales tax and contract adjustments for a total Change Order cost of $1,333,123.03; • Addition of Milestone 3 (phase 2B work per CPR 008) and a completion date of November 19, 2026; • Extension of the contract completion dates to February 1, 2028 for Substantial Completion and April 1, 2028 for Final Payment, subject to funding availability; and WHEREAS, the Director of Community Development and project management staff recommend acceptance of Change Order No. 004 as necessary for continued construction and successful completion of the Nelson Dam Removal Phase 2 Project; and WHEREAS, the City Council finds it to be in the best interest of the City to authorize the City Manger to accept Change Order No. 004; now therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA: The City Manager is hereby authorized to accept Change Order No. 004 to Contract No. IC2010 with Interwest Construction, Inc., in the amount of$1,333,123.03, which incorporates: • Correction of the Phase 2B contract amount, • Sales tax rate adjustments, • CPR 008Rev-Powerhouse Road Pipeline Realignment, and • Adjustments to contract times as detailed in the Change Order. • The City Manager is further authorized to execute all documents necessary to carry out the intent of this resolution, including future administrative amendments that do not materially alter the scope or cost beyond what is authorized herein. 24 ADOPTED BY THE CITY COUNCIL this 13th day of October, 2026. Matt Brown, Mayor ATT EST: Rosalinda Ibarra, CMC, City Clerk 25 cG N Change Order k �� City of Yakima \,.. ,�' Change Order Number 004 Project ame: Nelson Dam Removal Phase 2 Change Order Date 09/22/2026 Project Number: 1480 Contract Number IC2010 Contract Date 09/23/2024 Contractor: Interwest Construction, Inc. Address: 609 North Hill Blvd. City,State, Zip: Burlington,WA 98233 You are directed to make the following changes in this Contract: Please see Nelson Dam Removal PH2 - Change Order No. 004 attachment. Below are the topics for the following changes in this contract. - SALES TAX RATE ADJUSTMENT - CONTRACT TIMES: DATES - PHASE 2B ONE-TIME ADJUSTMENT - PHASE 2B ADDITIONAL LABOR, EQUIPMENT, AND MATERIAL COSTS - RETAINAGE Not valid until signed by both the Approving Authority and Contractor. Signature of the Contractor indicated agreement herewith, including any adjustment on the Contract Sum or Contract Time. The original Contract Sum was $ $9,887,791.25 Net change by previous Change Orders $ $176,489.11 The Contract Sum prior to this Change Order $ $10,064,280.36 The Contract Sum will be: IN Increased ❑ Decreased ❑ Unchanged by this Change Order $ $1,333,123.03 The New Contract Sum including this Change Order will be $ $11,397,403.39 The Contract Time will be: ❑ Increased 0 Decreased ❑ Unchanged by 11 working days The New Contract Time will be 65 working days Contractor ik Approval Recommended Approval Recommended Project E)nte:ty City of Yakima-Division Director BY i:.-.--, -.e_f_....,/, Title o wiha By � By Date /D_g^2-024 Date President City of Yakima-Division Manager Approved Date 09/30/2026 City Manager By By Date Date Based on Original to: 0 Contractor Copies to: 0 Region 0 Construction Administrator DOT Form 570-001 EF 0 OSC AccountingCityEngineering Revised 08/2021 0 g g EJCDC ENGINEERS JOINT CONTRACT DOCUMENTS COMMITTEE Change Order No. 004 Date of Issuance: 09/22/2026 Effective Date: 09/22/2026 Owner: City of Yakima Owner's Contract No.: IC2010 Contractor: Interwest Construction, Inc. Contractor's Project No.: 1480 Engineer: HDR Engineering, Inc. Engineer's Project No.: 10415845 Project: Nelson Dam Removal Phase 2 Contract Name: Nelson Dam Removal Phase 2 The Contract is modified as follows upon execution of this Change Order: Description: ORIGINAL PHASE 2B CONTRACT AMOUNT CONTRACT AMOUNT Description Cost Time 001 CONTRACT INCREASE $ 2.00 0 Days SALES TAX Description Cost Time 001 SALES TAX ADJUSTMENT $ 7,560.01 0 Days SUBTOTAL $ 7,560.01 0 Days CPR Description Cost Time 008 PHASE 2B- POWERHOUSE ROAD PIPELINE REALIGNMENT $ 1,220,590.26 0 Days SUBTOTAL $ 1,220,590.26 0 Days SALES TAX(8.6%) $ 104,970.76 0 Days SUBTOTAL WI SALES TAX $ 1,325,561.02 0 Days CHANGE ORDER TOTAL(WI SALES TAX) $ 1,333,123.03 0 Days ORIGINAL PHASE 2B CONTRACT AMOUNT The original Phase 2B Contract Amount is hereby corrected and increased by$2.00, from $2,729,160.17 to $2,729,162.17, consistent with the Contractor's Bid Sheet. SALES TAX RATE ADJUSTMENT Effective July 1, 2026,the local sales tax rate in the City of Yakima increased one-tenth of one percent(0.1%). This increases the Washington State Sales Tax Rate from 8.5%to 8.6%for work performed after July 1, 2026 for this project. This Change Order formally incorporates this sales tax rate increase into the current contract price as indicated above. CONTRACT TIMES: DATES Add to Agreement (Section 00 52 13, Article 4.02B) Milestone 3: November 19, 2026—Phase 2B work per Change Proposal Request 008.The work associated with CPR 008 was originally scheduled for 76 calendar days utilizing a standard 40-hr work week. An accelerated construction schedule has been adopted and is estimated to be 65 calendar days. The Contract Time is hereby being extended with Substantial Completion as February 1, 2028 and Final Payment as April 1, 2028 to provide for continued performance of the Contract Work, subject to the availability of project funding.The City of Yakima acknowledges that the duration of this extension may be further modified as necessary to align the contract schedule with the availability and timing of project funding. EJCDC®C-941,Change Order. Prepared and published 2013 by the Engineers Joint Contract Documents Committee. Page 1 of 2 27 EJCDC ENGINEERS JOINT CONTRACT DOCUMENTS COMMITTEE PHASE 2B ONE-TIME ADJUSTMENT The City of Yakima and Interwest Construction, Inc. mutually agree to remove paragraphs F and H of Article 6.01 of the Executed Agreement (Section 00 52 13) as they pertain to Phase 2B due to substantial changes to the project scope and planned implementation.The original Phase 2B pipeline alignment was to extend across Powerhouse Road with minimal restoration to the roadway and then through private property. Easements could not be acquired for this pipeline alignment outside of Powerhouse Road. Therefore, a revised pipeline alignment was provided to Interwest Construction, Inc. for a price proposal (CPR 008) to extend the pipeline alignment within Powerhouse Road between South Naches Road and Ackley Road. Interwest Construction, Inc. price proposal for the Phase 2B project scope is in 2026 dollars. PHASE 2B ADDITIONAL LABOR, EQUIPMENT,AND MATERIAL COSTS The original contract amount for Phase 2B is$2,520,002.00 (without sales tax). Interwest Construction, Inc. price proposal for Phase 2B is additional to the original contract amount listed above. The original scope of work associated with Phase 2B has been significantly modified due to unforeseen construction logistics associated with easement acquisition near Powerhouse Road. Below is a table summarizing the changes in major work items associated with Phase 2B. Additional labor and equipment costs for the new alignment are associated with additional traffic control, reduced production rates, labor overtime pay(5—12 hour days), Powerhouse Road restoration, limited workspace, haul truck constraints, additional rock excavation, and additional excavation due to deeper pipe. Additional equipment incudes light plants, paver, roller, grader and dump trucks. Additional materials included piping, pipe zone and backfill material, asphalt, aggregates, pipe fittings and shoring. RETAI NAG E The current executed contract (Specification Section 00 52 13) between the City of Yakima and Interwest Construction, Inc. per Article 7.02 indicates that the Owner may withhold prior to Substantial Completion 95 percent of the value of the Work completed (with the balance being retainage) and 95 percent of the cost of material and equipment not incorporated in the Work(with the balance being retainage). The City of Yakima and Interwest Construction, Inc. mutually agree this does not apply as Interwest Construction, Inc. procured a retainage bond for Nelson Dam Removal Phase 2 (all three phases). Attachments: Sales Tax Adjustment Calculation CPR 008Rev—Powerhouse Road Pipeline Realignment EJCDC®C-941,Change Order. Prepared and published 2013 by the Engineers Joint Contract Documents Committee. Page 2 of 2 28 EJCDC ENGINEERS JOINT CONTRACT DOCUMENTS COMMITTEE Phase 2B Avg Trench Avg Trench Original SOW-Standard 40-HR work week Depth Width Material Pipe Installation Method Approx 1,250 feet of straight 42-inch HDPE pipe installed Bottom =6.5 feet Fine-grained soils, Open trench excavation within adjacent to existing pipe 7 feet Top= 10 feet minimal dewatering WSDOT ROW without trench boxes. Approx 2,028 feet of straight 42-inch HDPE pipe installed Bottom =7.5 feet required Benched side slopes to meet OSHA in new trench 7 feet Top= 12 feet safety requirements. One road crossing of Ackley Road 30-foot long crossing Avg Trench Avg Trench CO-004 SOW-Accelerated 60-HR work week Depth Width Material Pipe Installation Method Fine-grained/cobble Install one set of trench boxes at pipe Approx 1,200 feet of 42-inch HDPE pipe installed within W. mixture & bedrock, invert and bench/slope sides from Bottom =8.5 feet Powerhouse Road, multiple angled fittings required for 18+feet significant dewatering top of trench boxes to existing grade. Top=30 feet alignment anticipated Stack trench boxes during single lane closure event. Four-week closure of Ackley Road with single-lane closure of W. Powerhouse Road Seven-week closure of W. Powerhouse Road Approx 1,300 feet of full two-lane road restoration for portions of Ackley&W. Powerhouse Roads EJCDC®C-941,Change Order. Prepared and published 2013 by the Engineers Joint Contract Documents Committee. Page 1 of 1 CD EJCDC 0 ENGINEERS JQI77 CONTAWC1 OOCUh1ENTS COMM{/TEE CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIMES (note changes in Milestones if applicable] Original Contract Price (w/Sales Tax) Phases 2A& 28 : Original Contract Times: Substantial Completion: February 1, 2026 $9,887,791.25 Ready for Final Payment: April 1, 2026 days or dates [Increase] [Decrease] from previously Phase 2A approved [Increase] [Decrease}from previously approved Change Change Orders No. 0 to No. 3 : Orders No. 0 to No. 3 : Substantial Completion: February 1, 2027 $ 176,489.11 Ready for Final Payment: April 1, 2027 days or dates Contract Price (w/Sales Tax) prior to this Change Order Contract Times prior to this Change Order: (Phases 2A&2B): Substantial Completion: February 1, 2027 $ 10,064,280.36 _ Ready for Final Payment: April 1, 2027 days or dates [Increase] [Decrease] of this Change Order(w/Sales Tax): [Increase] [Decrease}of this Change Order: Substantial Completion: February 1, 2028 $ 1,333,123.03 Ready for Final Payment: April 1, 2028 days or dates Phase 26 Contract Price incorporating this Change Order Contract Times with all approved Change Orders: (w/Sales Tax): Substantial Completion: February 1, 2028 $ 11,397,403.39 Ready for Final Payment: April 1, 2028 days or dates R M EN ED. ACCEPTED: F PTED: ' By: C By: By: /L Engineer ineer(if r quired) Owner(Authorized Signature) Contr or(A orized Signature) g � 1 � ) Title: Project Manager Title Title President Date: 09/22/2026 Date Date 9/30/2026 EJCDC'C-941,Change Order. Prepared and published 2013 by the Engineers Joint Contract Documents Committee. Page 1 of 1 F September 18, 2026 Interwest Construction, Inc. 609 North Hill Blvd. Burlington,WA 98233 Attn: Zach Rose, Project Manager Re: City of Yakima Nelson Dam Removal Phase 2 CPR 008Rev—Powerhouse Road Realignment Engineer's Decision Zach, We have reviewed your cost proposal for CPR 008Rev—Powerhouse Road Realignment. We have found your submitted cost proposal to be acceptable. A total cost of$ 1,220,590.26 (w/o sales tax) and a total of 0 calendar days will be included in a forthcoming Change Order. The total cost of the Powerhouse Road Realignment will be included in a forthcoming Change Order. Sincerely, HDR Engineering, Inc. Troy Gibbs, PE Construction Manager cc: Daniel Tiliano—City of Yakima Chad Redick—City of Yakima Rich Sanislo—City of Yakima Ryan Roberts—HDR Mike Garello—HDR hdrinc.com 4717 97th St,Gig Harbor,WA 98332 (253)432-5024 31 INTERWEST CONSTRUCTION INC. September 9,2026 Change Proposal Request 008Rev Troy Gibbs,P.E. Construction Manager HDR Engineering,Inc. 835 N Post Street Spokane,WA 99201 RE: CPR No.008Rev—West Powerhouse Road Realignment Nelson Dam Removal Phase II -Conveyance Improvements Contract Number IC2010 HDR Project No. 10173276 Mr. Gibbs: Interwest Construction,Inc. (Interwest)hereby submits Change Proposal Request(CPR)No. 008Rev for the realignment of the 42-inch HDPE pipeline along West Powerhouse Road,from approximately STA 4+25 to STA 16+85. This change is required to facilitate successful installation of the pipeline along West Powerhouse Road. Attached are the itemized labor,equipment, and material costs associated with the additional work required to construct the revised alignment,including increased trench depth, additional pipe quantity,extra connections and pipe fusing,expanded traffic control requirements, and shoring. Except as specifically identified in this CPR, all other work items are assumed to be performed and compensated in accordance with the Contract and the current Schedule of Values. • West Powerhouse Rd.Realignment: S1,220,590.26 LS (excl.WSST) Interwest has priced this CPR based on 60-hour workweeks using a 5-12 schedule. Pricing excludes double shifts,24-hour operations, and schedule acceleration costs. If additional hours or weekend work become necessary,Interwest can provide the applicable cost premium upon request. The estimated overtime premium (8-weeks x 20 hrs. per week)for the 5-12 schedule has been included. This CPR has also been prepared with the understanding that West Powerhouse Road will be fully closed to traffic during construction. Traffic will be detoured in accordance with the attached West Powerhouse Road closure plan.As an additional precaution,temporary chain-link fencing will be placed around the work zone. An anticipated schedule identifying the estimated construction duration and expected traffic impacts is also attached. Interwest respectfully requests the City's review and written approval of CPR No. 008Rev so that the revised scope and associated Contract modifications can be executed and incorporated into the Contract by Change Order. (360)757-7574 Fax(360)757-6464 E-mail: bids@interwest.biz 609 North Hill Blvd.•Burlington,WA 98233 An Equal Opportunity Employer Contractor License INTERCI121OF 32 Please provide written acceptance,or consolidated comments and questions, at your earliest convenience so Interwest can proceed with the proposed work. Interwest remains committed to working collaboratively with the City and HDR to keep the project moving forward and to minimize traffic disruptions to the extent practicable. Should you have any comments,concerns,or questions regarding this CPR,please contact the undersigned at 360-391-6140. Respectfully Submitted, INTERWEST CONSTRUCTION,INC. ay¢-- Zach Rose Project Manager (360)757-7574 Fax(360)757-6464 E-mail: bids@interwest.biz 609 North Hill Blvd.•Burlington,WA 98233 An Equal Opportunity Employer Contractor License INTERCH21OF 33 INTERWEST ICI CONSTRUCTION INC. 609 North Hill Blvd.,Burlington,WA 98233 Cost Proposal 360-757-7574 Phone-360-757-6464 Fax Summary Project Number Project Name Client/General Contractor 1480 Nelson Dam Phase 2 Date of the Work Item Number Item Name TBD Change Proposal Request#08Rev Description of Work Performed CPR#08Rev-VVest Powerhouse Road Realignment Pipeline Scope.CPR based on 5x12 work schedule Time Worked Record Labor Hours VVorked Name of Workers Occupation Reg. OT DT Reg.Rate O.T.Rate D.T.Rate Amount Project Management 1 $ 30,000.00 Project Adminstration 1 $ 20,000.00 Operator Foreman 368 160 $ 101.59 $ 136.28 $ 170.49 $ 59,189.92 Equip Operator-Group 2 348 320 $ 95.97 $ 127.91 $ 159.43 $ 74,328.76 Laborer-Group 5 275 160 $ 63.59 $ 85.47 $ 102.13 $ 31,162.45 Laborer-Group 3 277 160 $ 60.15 $ 80.60 $ 100.29 $ 29,557.55 Lowboy&Other Trucks 80 $ 69.93 $ 100.49 $ 131.05 $ 5,594.33 Superintendent 264 $ 119.41 $ 163.05 $ 206.09 $ 31,524.24 Laborer-Group 2C 278 160 $ 63.55 $ 85.41 $ 106.97 $ 31,332.50 Laborer-Group 2B 286 160 $ 59.91 $ 80.01 $ 99.82 $ 29,935.86 Dump Truck&Trailer 320 $ 74.38 $ 101.24 $ 128.09 $ 32,396.80 Labor Subtotal $ 375,022.41 Markup @ 15% $ 56,253.36 Labor Total $ 431,275.77 Equipment Hours VVorked Equipment#/Type/Size Reg. Standby Reg.Rate SB Rate Amount 06-142 2024 Komatsu PC490LC-11 164 $ 232.46 $ 77.22 $ 38,123.44 06-109 2018 Caterpillar 323 150 $ 136.24 $ 44.30 $ 20,436.00 06-139 2024 Komatsu PC238LC 96 $ 128.78 $ 42.94 $ 12,362.88 06-130 2022 Caterpillar 335 124 $ 165.95 $ 51.11 $ 20,577.80 07-39 2017 Caterpillar 938M 166 $ 84.42 $ 24.01 $ 14,013.72 05-19 2006 Caterpillar CS-573E Single Drum Roller 64 $ 74.33 $ 15.62 $ 4,757.12 08-179 2023 4X2 30KGVW DSL Flatbed Truck 400 $ 50.78 $ 8.30 $ 20,312.00 10-19 2007 Lay-mor 8H C Street Sweeper 40 $ 67.52 $ 19.02 $ 2,700.80 08-174 2019 4X2 Light Duty Traffic Control Truck 352 $ 23.49 $ 1.27 $ 8,268.48 24-08 2013 Kenworth T370 4000 Gal Water 56 $ 61.07 $ 10.95 $ 3,419.92 50-23 NPK C83 24 In.Q/C Excavator Plate Compactor 142 $ 14.21 $ 4.01 $ 2,017.82 51-06 Kent KHB50G Hammer for 400 Class Excavator 88 $ 85.14 $ 29.03 $ 7,492.32 11-03 2003 Caterpillar 140H Grader 16 $ 89.48 $ 20.46 $ 1,431.68 62-08 2011 Screw Sucker 6"pump 176 $ 54.66 $ 11.38 $ 9,620.16 14-05 2004 Multiquip/Whisperwatt DCA-25SSIU Generator 176 $ 19.28 $ 2.13 $ 3,393.28 03-45 2007 Kenworth T800 Dump Truck 16 $ 94.90 $ 11.28 $ 1,518.40 17-29 2018 Portable Light Plant 704 $ 6.90 $ 1.65 $ 4,857.60 15-11 2006 Volvo A35D Articulated Off-Road Dump Truck 80 $ 189.88 $ 53.31 $ 15,190.40 03-60 2018 Peterbilt 567 Lowboy Tractor 80 $ 87.02 $ 13.21 $ 6,961.60 04-100 Aspen Lowboy 80 $ 31.13 $ 9.60 $ 2,490.40 Equipment Subtotal $ 199,945.82 Markup @ 15% $ 29,991.87 Equipment Total $ 229,937.69 Materials! Description Supplier Invoice Quantity Unit Unit Price Amount CSBC 2985 Ton $ 12.50 $ 37,312.50 Pipe Bedding 365 Ton $ 10.00 $ 3,650.00 Pipe Fittings 1 LS $ 75,713.43 $ 75,713.43 Haul Aggregates 3350 Ton $ 9.00 $ 30,150.00 Dump Fee Soil 1504 CY $ 6.00 $ 9,024.00 Haul VVaste Soil 1504 CY $ 10.00 $ 15,040.00 Haul VVaste Asphalt 495 Ton $ 9.00 $ 4,455.00 Dump Fee Asphalt 495 Ton $ 15.00 $ 7,425.00 Track Mounted Drill 1 EST $ 35,000.00 $ 35,000.00 Shoring Rental 2 MO $ 59,814.51 $ 119,629.02 Shoring Freight 8 EA $ 1,300.00 $ 10,400.00 Materials Subtotal $ 347,798.95 Markup @ 15% $ 52,169.84 Materials Total $ 399,968.79 Subcontractor Work Description of Work Subcontractor Invoice Quantity Unit Unit Price Amount Asphalt 1 EST $ 128,500.00 $ 128,500.00 VVire Fence 1 EST $ 5,000.00 $ 5,000.00 Pavement Markings 1 LS $ 5,000.00 $ 5,000.00 Sawcut 12300 INFT $ 0.65 $ 7,995.00 Pipe Fusing 1 EST $ 30,350.00 $ 30,350.00 Electrical 1 LS $ 10,000.00 $ 10,000.00 Dewatering 1 LS $ 35,000.00 $ 35,000.00 Subcontractor Subtotal $ 221,845.00 Markup @ 5% $ 11,092.25 Subcontractor Total $ 232,937.25 SHEET SUBTOTAL $ 1,294,119.50 4%Insurance,Bond,B&O Tax,Small Tools $ 51,764.78 5%Mobilization(Safety,Dispatch,Temp Facilities) $ 64,705.98 Orginal VVest Powerhouse Rd Restoration Credit Per 2A SOV $ (190,000.00) 'SHEET TOTAL $ 1,220,590.26 Notes: 34 ATTACHMENT A DESCRIPTION OF WORK 35 Ackley Road and West Powerhouse Road Construction Phasing and TCP Proposal General Requirements: 1. Light plants will be utilized at flagging stations and at the construction site during work hours beginning 1 hour prior to sunset and ending%hour after sunrise. 2. Notification for full road closures will be posted in the Yakima Herald a minimum of three days prior to the closure. 3. PCMS signs will be placed at each end of traffic control zones 7-10 days prior to TCP implementation. The Contractor will install the 42"HDPE pipe in three(3) phases. • Phase 1 will install the pipe across Ackley Road and approximately 100 feet of the West Powerhouse Road northern lane. • Phase 2 will fully install the pipe in Powerhouse Road. • Phase 3 will be the final roadway restoration. A more detailed plan of work in each phase is provided below. Phase 1 1. During this phase,Ackley Road will be closed to all traffic(see attachments 02T05 and 02T06). 2. West Powerhouse Road will be reduced to a single lane/two-way closure during working hours controlled by naggers(see attachment C/TCP1). 3. At the end of each work shift,the pipe trench on West Powerhouse Road will be protected with steel plates and West Powerhouse Road will be open to traffic for both directions. 4. Once the pipe is installed across Ackley Road,the trench will be backfilled and compacted and Ackley Road will be paved. 5. Ackley Road will now be fully open and accessible. Phase 2 1. During this phase,West Powerhouse Road will be closed to all traffic(see attachments 02T02, 02T03,02T03 and 02T08). Ackley Road will remain fully open and accessible. The southbound stop at the intersection of Ackley Road and West Powerhouse Road will be removed, making the left-turn movement from Ackley Road onto West Powerhouse Road free flowing. 2. Install pipe in West Powerhouse Road to connection south of West Powerhouse Road. Phase 3 1. During Phase 3, southbound traffic on Ackley Road shall have nagger priority.Traffic queue shall not be allowed to extend to US 12 and all queued traffic shall be cleared before next stoppage. 2. Upon completing the 42"pipe installation,the Contractor will perform a hydrostatic test. 36 3. Following a passing hydrostatic test,the Contractor will proceed with final trench line/roadway restoration. 4. Final roadway restoration will be completed in accordance with the Plans provided by Yakima County. 5. Flagging will occur during work hours,as needed (see attachment TCP1). 6. Both roads will remain fully open outside of work hours. 37 ATTACHMENT B ROAD CLOSURE AND TRAFFIC CONTROL PLANS 38 o) M 1 2 3 4 5 6 7 8 44 - _ NOTES: • s ACCEPTED AS NOTED N IMPLEM�DRB RESPONSIBLE ATION OF FULL /\ PROPOSED DANDOPERANDD DETOUR ..Or ' 1r - , Dg taEy B BO by Samue Robert AA SOWN NDA PROVED A PERMITTING AS SHOWN AND APPROVED BY PERMITTING GENCIES. - �'t uS,x ANDW _ . _ S�BIR berl@WSDOT.wa.Dv, IN. ©POWERHOUSE ROAD. - k Samuel Robert6=WSDOT OUT rtalon 6 /, a CLOSURE ANDIOR EOPOSEANSALT RN �� CLOBUREAND,9R DETOUR PLANS ALTERNATIVE / \ 02'.i '3 i -111. 6R be bna OMce,CN SamuBl PLANS SHALL BAELL SUBMITTED APPl1cABIE PERMITTINGAND / \ « - Man' R4 151'1'16 57-DTI,O' APPROVAL PERMAGENITTING AGENCIEB FULL�PROVIES AI.LL BE GRANTED FROM LE D \ ' W SDOT TRANSPORTATION OPERATIONS PRIOR GIMPLEMENTATION. v� • 9. ALL SIGNAGE AND SPACING REQUIREMENTS \ /�� i 9 ' _ .• SHALL MEET THE MOST CURRENT VERSION OF \\ - � ithinWSDOTRight-of-Way/Limited Access Only DEVICES.DA'iFORUNIFDRMTRAFFIccoN,ROL Yakima County luzglinam 5hlI Also Accept l T. PROVIDE PCMS A MINIMUM OF TWO WEEKS IN - • ADVANCE OF ACKIEY ROAD CLOSURE.PCMS -- - - - - - SHALL BE LOCATED APPROXIMATELY I/4 MITE BEFORE EX.AS SHOWN.MESSAGE SHALL ALTERNATE'ACKLEV R CLOSED AHEAD'AND 'USE ALT ROUTE'AT 2.0 SECONDS EACH. w°°N :}.. = r APPROVED e \IF. ;.' \ "`'4'} - '4,. e_. )U �' Melissa Vantrease/o9.15.ao26 i \\\ 4 �.UPOVJERHOUSE ROADi . �Z' A.� C \,1,q • � / \\ \ 0202,1,�'413 ^ 1.�' �" • �_ r��NbTH AVF�iFRUUTNALE BLVD ET_ / YAKIMA COUNTY ROADS k �' / \\ ` '` �•• TRAFFIC ENGINEERING DEPARTMENT *. / — \ / e— '/�yl\� \\ ACKLEV ROAD ` O / . \\. 1 / \ U e ix W{q�OWD _ oz� oz7k \\J ' ' " AIL 4D 1 1 i ♦, • Vr '.00 IL- ov ot w 1 i fly A_ L Irs . r` 414,.. b ►N. l � � * - - . ,' �, rat A �m.R; ,i 'I ,_ n i a. DODO - ;. - Y ti'!V;_ C i:.___ ` 1 �'-+• S>> 3 .� y T •` it r/,tll II ,`/ .. a r�� 2B '�' A 'y '! 3 J =.A y a At r f A h y '..it.‘. y; �;�' F S r_r` 1 I .. mr 7 I f r ¢� s 1 �r f E�` 1 1 FRO.IEOT MEADER MICHAEL OARELLO,PE DESIGNED BY IL GARELLO NELSON DAM REMOVAL PROJECT: TRAFFIC CONTROL 811 CHECKED BY R.ROBERTS WATER SUPPLY,FISH PASSAGE,AND CHECKED BY TCIBBe `'`'4''' RIVERINE PROCESS IMPROVEMENTS ACKELY ROAD CLOSURE PLAN �V5;„„ DRAWN BY N.SZISER PHASE II - CONVEYANCE Knowwhats below. B w1MMA CONFORMED FOR CONSTRUCTION - IMPROVEMENTS FLENAME 4xl3S.AeN SHEET Call before you dig. A wrormoA ISSUED FOR BID F` ® SCALE r=Der 02T02 ISSUE DATE DESCRIPTION PROJECT NUMBER 1017327E CITY OF YAKIMA,WASHINGTON 0 1 2 3 4 5 6 7 8 -y... _ _ uDTE& d jI 1 CONTRACTOR IS IMPLEMENTATION AND OPERATION FFULL "IF :jet • .:...7 I ACCEPTED A'S NOTED PROPOSED ROAD CLOSURE AND DETOUR PLANS ,.�8 I AS SHOWN AND APPROVED BY PERMITTING •,- t�'• 4 i - s�T,� , DOBBIN signed by Samuel Robert AGENCIES t Close US 12 westbound DN.C•US B CONTRACTOR MAY PROPOSE ALTERNATIVE ' q • „� /. \ 1 ' left-turn lane per _ __ E�emUB Robe11�WSDOT.Ws.Dov, CLOSURE AND/OR DETOUR PLANS ALTERNATIVE •I -F MUTCDANSDOT - Samuel Robe Ct OfINTIZ 0611, InspDNa On PLANS 81MLL BE SUBMITTED FOR REVIEW AND - l Operations Office,CN Samuel Robert APPROVAL WALL APPLICABLE PERMITTING DETOUR —- '• -•r,I I A--, . •.,YIsa__4-, - ,. ,+ _ -standards ......_ Date:202Roe.lslaar13-07D• AGENCIES.FULL APPROVAL FROM APPLICABLE -,-_ PERMITTING AGENCIE881NLL BE GRANTED D PRIOR TO IMPLEMENTATION. _. IIs,z WE3TBOuaD a WSDOT TRANSPORTATION OPERATIONS 3. ALL SIGNAGE AND SPACING REQUIREMENTS US 12 EASTBOUND ME B 0\ .-- �_ -. TXE MANUALET TFOR HE UN�FORM TRAFFRENT ILRSLOMRION OL 1 -� IINe ir'aT RFP.�_ s NACRES ROAD RHPuce KEmrnE: ;. �ahT �► f.� - ,/, Rhin WSDOT RI`ht-of-Wty/Umited Access Only DEVICES. .' 4 411 SBIGNAGE WITH KEYNOTE IIGMIGE CURING CLOSURE '.)/• �' / // Yakima County Shall Also Accept KE ppapyl E81GN SEQUENCE BELOW.DIRECTON OF ARROW VARIES AND SHALL GUIDE TRAFFIC 1 ALONG DETOUR ROUTE SHOWN.SIGNS SHALL BE • O ,-, 2(4:1141:4'6' '§ (...- - SIGNS GATED IMLL BE IB"XOB"AND MO-8 SHALL BE j ACKL•FORSIDNS LOGTED ON US13. EY ROAD I - ///' •T t' :• �} CLOSED DETOUR I.moue 7 N ,::A+. I / / Fy' •41, i. 4 rr ,.<_ t i sees. AHEAD �- :S' k11111. z. PROVIDE DETOUR AND ROAD SIGN AS SHOWN APPROVED I• i __ :.� BELOW.W GU1pECTRAFFION�L AEON ARROW VARIES EROUTE EroDR '. �• _ SHOWN. l y tf�- C ACKLEY ROAD •. Melissa Vantrease/o9.15.2o26 ? � O r .� rr DETOUR W f YAKIMACOUNTY ROAD :.'S '"' 9. PROVIDE ADVANCED NOTIFICATION SIGNS W H TRAFFIC ENGINEERING DEPARTMENT 'r ►®; A�TD OATDVANCEES OF OF CLOSURE.E A MINIMUMOF mMO WEEKS ��' , IN ADVANCE OF CLOSURE. �.�_. ACKLEY ROAD WILL BE - US 12 AND W POWERHOUSE ROAD 1 NETOD EOM T TFM FROM _ SCAE:,•=,Sa• 02 no 3 it K PROVIDE BARRICADE AT EACH END of CLOSED SECTION OF ROAD. If- `4 s 'B* ,_.+f "" + — 1r�aimt— — -- r CLOSED_1 l B Oa - � — 3. NO USED :IRS{ 8. PROVIDE MIS A MINIMUM OF TWO WEEKS IN I-- - r r -- ADVANCE OF ROAD CLOSURE.MESSAGE SHALL © U9,]WEBTBWNp CONTAIN NAME OF ROAD BEING CLOSED. O ,OUR -' . INTERSECTING ROADS OF CLOSED PROTON OF a - - _ ROAD.AND DATES OF FULL CLOSURE. • ,. } NamHAVE -0 0 it., , _______„ /i p /._ ,' .' ' • '.i SI ;_f,„1"--, *--..' 4 F OIL* A US 12 AND W POWERHOUSE ROAD a N(15 2 B N 40TH AVE �z /- SCALE.I.=ION 02 zoz 3 SCALE:,•=,SD ozroz�ozroa N 7IF PROJECT MANAGER MICHAEL DARELLO,PE 1 DESIGNED BY M.GARELLO NELSON DAM REMOVAL PROJECT: TRAFFIC CONTROL 8 DESIGNED BY R.GIBSRT0 WATER SUPPLY,FISH PASSAGE,AND CHECKED BY rAGES RIVERINE PROCESS IMPROVEMENTS ACKLEY ROAD CLOSURE, �Vif�' F)1 PHASE II - CONVEYANCE DRAWN BY N.SZIGET y DETOUR SIGNAGE DETAILS 1 Know What's below. a e11ML1A CONFORMED FOR CONSTRUCTION IMPROVEMENTS D z. FLENAME MOEN. SHEET Cell before you dig. A 81100020 ISSUED FOR BID ® SCALE- 02T03 ISSUE DATE oESCRIPnaN PROJECT NUMBER 10173238 CITY OF YAKIMA,WASHINGTON 1 112.7 2I 3 Pa I 4 6 6 7 8 4�•1 / i ems- -'1 NOTES: riadN -le alig; f- lielle51P-.. _ `I '• . ` � �� a . di . ':' i N 1 LOMRALTOR IS FULL IMPLEMENTATION AND OPEIRATIONBLE OF �. • - PROPOSED ROAD CLOSURE AND DETOUR PLANS A •1`rorf , a/Yl � , ' , jiirills: � - a 'S AGENCIES.AS SHOWN AND APPROVED BY PERMITTING + . � . • .w 'M _ •. _ /' • -��� t CONTRACTOR MAY PROPOSE ALTERNATIVE �T •. IT.•t+.4 CLOSURE AND/OR DETOUR PLANS.ALTERNATIVE PLAN68HALLBE8UBMITTED FOR REVIEWANDAPPROVALBYALLAPPIYABLE PERMTfTING L•, �• ERMITTINGAGENCIE881MLL EGRANIED LED `' {?� PRIOR TOIMPLEMENTATION.U6 t2 ANO 3. ALL SIONAGE AND SPACING REQUIREMENTS©W SEROAD SWILL MEET THE MOST CURREM VERSIDN OF r \ 02'Q ,: , DEVICEBUAL FOR UNIFORM TRAFFIC CONTROL 6A P . ;�..4 w� A BNALHEB ROADANO '•- - - . 'AO 02 04;F06 -n C t .-F - .. �\ ey, usi2AuoW • POWERHWBE ROAD , ' p ` `\ \\ DETOUR \ W POWERHOUSE ROAD \ \ US I2 WEST BOUND CLOSURE \N. \ NISTH AVE POST \ ACNLEY ROAD �? / US 12 WESTBOUND N40TX AVE EXR \\\\J/� Ile 33 y"mg . 4/# uliW _ , ,,.... -_7 4. • �III _`,' ACCEPTED AS NOTED 1 MIA PECNSCANYDN RAID AND -- I i■ Digitally signed by Samuel Robert ' W POWERHOUSE ROAD © I f • DN:C US, .' I 02,6 I ., t Samuel RobertE=8amueLRobert•WSDOT.Wa.B0Y, A Dp6m202300.l151397:25-07 0. APPROVED mi Date:2026.09.16 T397:25-0T00' '� A , - . a 0200026 , -"I • — . y�WSDOT TRANSPORTATION OPERATIONS'� Melissa Vantrease/09.15.2026 -} - ithin WSDOT Right-of-Way/Limited Access Only $ YAKIMA COUNTY ROADS r, Yakima County Shall Also Accept'• TRAFFIC ENGINEERING DEPARTMENT ' • PROJECT MANAGER MICHAEL GARELLO,PE 1 DESIGNED BY M.GARELLO NELSON DAM REMOVAL PROJECT: TRAFFIC CONTROL DESIGNED BY R.ROBERTS WATER SUPPLY,FISH PASSAGE,AND 0iH0Y`0�s CHECKED BYN.GMB. ,„ RIVERINE PROCESS IMPROVEMENTS W POWERHOUSE ROAD C3 11/1.02 REVISED TRAFFIC CONTROL PLAN \�� W i1/14I2M3 REVISED TRAFFIC CONTROL PLAN DRAWN By N.MGM CLOSURE PLAN C2 1/2.025 REVISED TRAFFIC CONTROL PLAN PHASE!! - CONVEYANCE CI t2/1N20N REVISED TRAFFIC CONTROL STRU PLAN SHEET Know what's below. F)1 B WiMMA CONFORMED FOR CONSTRUCTION IMPROVEMENTS FEM ME OTM../0 Cell before you dig. A Wt ISSUED FOR BID ® 02T04 ISSUE DATE OESCRIPTTGM PROJECT NUMBER 101T3278 CITY OF YAKIMA,WASHINGTON SCALE- N 1 2 3 4 5 6 7 8 NOTES: JI RECOMMENDED BOON SPADING•X 1. CONTRACTOR IS RESPONSIBLE FOR FULL IMPLEMENTATION AND OPERATION OF RURAL lUGHWAYS 6040►IPII BOOB PROPOSED ROAD CLOSURE AND DETOUR PLANS �_ S S_5AS SHOWN AND APPROVED BY PERMITTING I RURAL.ROADS LOJU / 5 MPH 50o't AS SOIEs. I - Ill ALL SPACIND MAT BE STED TO ACCOMMODATE -• = -� -, .' • l Si NS INTFRCNT}F PAH=AT(IR3DE M FC TFRSIONR AMC DRhFWA ER YS U. CONTRACTOR MAY PROPOSE ALTERNATIVE •DETOUR O ! CLOSURE ANDOR DETOUR PLANS.ALTERNATIVE + CLOVER LANE ' PLANS SMLL BE SUBMITTED FOR REVIEW AND =EMI -'. - YAK CHANNELIZATION APPROVAL BY.APPLICABLE PERMITTING O . _ - DEVICE�A AGENCIES.FULL APPROVAL FROM APPLICABLE D MEAD PERMITTING AGENCIES BEMLL BE GRANTED USI2 WESTBOUND MPH TAPER TANGENT PRIOR TO IMPLEMENTATION. U813 OADTBOUND 50.70 40 Eo 3. ALL STRAW*.SPACING REQUIREMENTS 45 30 60 SWILL MEET THE MOST CURRENT VERSION OF IU 1 MA THE NUAL FOR UNIFORM TRAFFIC CONTROL POIYERIKI + W - DEVICES. ALL SIGNS ON US.SHALL BE 08=8•UNLESS OTHERWISE KEYED NOTES DES I/,� ZONATED 1. PROVIDE SIGN SEQUENCE BELOW.DIRECTOR q,_ " '3 2 ALL MONS ON US IR SHALL BE POST MOUNTED OR MEET CI=SIGN REQUIREMENTS PER WSDOT BTANMRUSPECIFILATONS.A OF ARROW VARIES AND SHALL GUIDE TRAFFIC DE ACIY ROAD CLOSURE _ I "IO ALONG DETOUR ROUTE SHOWN. — I IW.POWFRHOUSE RD. i V:'.,, I A CROA D DETOUR C DETOUR •�" ' _ Y AHEAD AHEAD 11.6 - « 2 0, PROVIDE DETDMRAND ROM BIDN AB SHOWN t,' f ,r _ SHALL• BELOW GUIDE TIONTRAP IC ARROW VARIER AND DETOUR SHALL GUIDE TRAFFIC ALONG DETOUR BONNIE -{ i SHOWN. C ,�..Om. X `iI. _ w.POWERHOUSE= V _. -• 19 , /S -.. - _ DETOUR W 3. PROVIDE ADVANCED NOTROATTON SIGNS WITH '�FFn. DATES OF CLOSURE A MINIMUM OF TWO WEEKS IN ADVANCE OF CLOSURE. v O W.POWERHOUSE RD.WILL BE CLOSED BETWEEN ACKLEY RD. A ANDS NACRES RD.FROM TOM N US 12AND W POWERHOUSE ROAD /� A. PROVIDE BARRICADE ATE CHENDOFCLOSED SCALE 1"=150' 0 04 02 05 ', SECTION OF ROAD. jE y r I LOSOU H ®" ' 1 5. PROVIDE CLOSURE LOCATION SIGN AT B t• ', 4 o ACCEPTED A. " _,,..�,- _:-, INTERSECTION. t ,?' DETOUR / 3 Dblts5 signed by Samuel RobertXACKLEYR0.1 DN:C-US, 11 I Samuel RobertE-SaMQeI.Rohe®WBDOT.Wa.UGH 6 L�ER6DGTHBDDND ACKLEY RDADSTOP SIGN 4\ 4. .,„ ��r O=tIUSETEriSDOT,OU=TD127:36-DD Operations Mks,CN-Samuel Robert AT W POWERHOUSE ROAD. ` Date:2026.09.15 T387:36-07YJ0' ir i n SDOxROL WSDOT TRANSPORTATION OPERATIONS DEVICES.TRAFFICEs.TYP' 0• Within WSDOT Right-of-Way/Limited Access Only S 0 '0 DES Yakima County Shall Also Accept • w40 • MO APPROVED A Melissa Vantrease/o9.15.2o26 N PECKS CANYON ROAD / N A (7...) eb ACKLEY ROAD AND W POWERHOUSE ROAD f 1 SCALE 1•=,w ® YAKIMA COUNTY ROADS SCALE 1•-100 o2TOA o3TDs 02104 azT05 TRAFFIC ENGINEERING DEPARTMENT PROJECT MANAGER MICHAEL GARELLO,PE 1 DESIGNED BY M.GARELLO NELSON DAM REMOVAL PROJECT: TRAFFIC CONTROL 8DESIGNER BY R.RODENTS WATER SUPPLY,FISH PASSAGE,AND C9 OOHN2026 REVIBEDTRAFFICCONIFtOLPEAII CHECKED BY T.GIBBB RIVERINE PROCESS IMPROVEMENTS W POWERHOUSE ROAD CLOSURE ��/ IM)1 c4 11HAIf026 REVISED TRAFFIC CONTROL PUN DRAWN BY N.SZIGETI DETOUR SIGNAGE DETAILS 7 CI 1 42025 REVISED TRAFFIC CONTROL PLANPHASE II - CONVEYANCE CI t3HN20N REVISED TRAFFIC CONTROL STRU PLAN SHEET Know What's below. B Wi.= CONFORMED FOR CONSTRUCTION IMPROVEMENTS FEMME ORDIESNR Call before you dig. A 13111M24 ISSUED FOR BID ® 02T05 ISSUE DATE DESCRISTON PROJECT HUMBER 10173278 CITY OF YAKIMA,WASHINGTON SOULS- M 1 I2 I3 I 4 I 5 I 6 I7 I8 _ - - NOTES: APPROVED 1. CONTRACTOR IS RESPONSIBLE FOR FULL IMPLEMENTATION AND OPERATION OF PROPOSED ROAD CLOSURE AND DETOUR PLANS Melissa Vantrease/o9.15.2o2,6 I AS SHOWN AND APPROVED BY PERMITTING AGENCIES. 2. CONTRACTOR MAY PROPOSE ALTERNATIVE IF OALTERNATIVE CLOSURE ANMOR DETOUR PLANE. APPROVAL.BE SUBMITTED FOR REVIEW AND PERMUTING YAKIMA COUNTY ROADS 't • AGENCIES.FULL APPROVAL FROM APPLICABLE D £ • PPERMITONGRIOR M L AGENCIES HALL BE GRANTED TRAFFIC ENGINEERING DEPARTMEN`` w;'� Y IE AND SPACING REQUIREMENTS �/ .�'; - B SHALLALL EET THE MOST CURRENT VERSION OF ACCEPTED AS NOTED , r TNEMANUAL FOR UNIFORM TRAFFIC CONTROL DEVICES. • ti DIDBeIIy el ine11 by Samuel Robert *lit w-...-A KEYED NOTES DN:Cain, rad,y ±( 1. PROVIDE SIGN SEQUENCE BELOW.DIRECTION E=Bemuel RObe11@w6ortalo eDOv, �., '. OF ARROW VARIES AND SHALL GUIDE TRAFFIC Samuel Robert�wSDDT DD Tane�MDn ALONG DETOURRQUTESHOwN. — Operations Office,Cal-Samuel Robert IW.POWERHOUSE RD. Date:202808.15193750-OT00' "' ' ' � i',_ A OR C • • WSDOT TRANSPORTATION OPERATIONS iy © ] T DEED DE OUR • AHEID Within WSDOT Right-of-Way/Limited Access Only - • 60 2 1,x PROVIDE DETOUR AND ROAD SIGN AS SHOWN Yakima County BELOW.DIRECTION OF ARROW VARIES AND Shall Also Accept ;,:yD � SHALL GUIDE TRAFFIC AIDNG DETOUR ROUTE i' J ,�' eHwAW. .? - wPowBRHOusEawD aosuRE ] 4]a Iw.IwwBRIKxuB NMI M'f 'u ?p- ]8n. DETOUR J 'o M • B. PROVIDE ADVANCED NOTIFICATION SIGNS WITH DATES OF CLOSURE AMINIMUM OF TWO WEEKS IN ADVANCE OF CLOSURE. NI W.PM/38 OM RD.WILL BE CLOSEt e AAE6 BEIWEFM AGQEY RD. S NACHES ROAD AND W POWERHOUSE ROAD 2 roDNAMESTM.FROMma — ScnlE:r=1IK,• 02 02 PROVIDE BARRICADEAT EACH END OF CLOSED SECTION OF ROAD. Q ROAD I ' _ �. ♦ r CLoaED, •� ' - A I I .!-Iin �.,� ?s. IZEKEMI1 - -_ - B. PROVIDE CLOSURE LOCATION 81GN AT B �2 QQQ"' INTERSECTION. -— NLDTHAVE 0 • ' ,• ' ti W.POWNNHDII6E RD.1 O • . CLD6EDATMME k 2 R 12 WESTBOUND DETOUR, 'x 6. PROVIDE PLNSA MINIMUM OF TVO WEEKS . _ .�- I PRIOR TO ROAD CLOSEDBNALLCONTAIN 1��`�///�v���)) NAME OF ROAD BEING CLOSED,INTERSECTING AlfM US 12 EASTBOUNDiVait 4_t ��� •' V ROAD AT CLOSURE.AND DATE OF CLOSURE O OO O - NbTN AVE O \iiT 2 �e O. W POWERHOUSE ROAD IC , • ` OO _p • 1NOTE:CONTACT WSDOT SOUTH CENTRAL REGION g N. Pp '"'SIONALENOINEER(ROBERT HALL 50Be1&]t5C) MINIMUMS DAM PRIOR TO IMPLEMENTING THE r A ROAD CLOSURE. '� • 'r `� • US 12 AND W POWERHOUSE ROAD a N SCALE:+'=100 O2T 6 1, N 40TH AVE 4 1441 - SCALE:1'=160' O 6 / \_ PROJECT MANADER MICHAEL OARELLO,PE 11 DESIGNED BY M.GARELLO NELSON DAM REMOVAL PROJECT: TRAFFIC CONTROL DESIGNED BY R.ROBERTS WATER SUPPLY,FISH PASSAGE,AND cs Iw1N2D26 REVISED TRAFFIC CONTROL PLAN 050c0ED BY T.ROBS W POWERHOUSE ROAD CLOSURE a uwrmas REVISED TRAFFICCONIFtOLPIAN RIVERINE PROCESS IMPROVEMENTS ��/ F)1w ,vlAnoxs REVISED TRAFFIC CONTROL PUN DRAWN BY N.MGM, * DETOUR SIGNAGE DETAILS 2 cz M.O. REVISED TRAFFIC CONII20LPLW I PHASE II - CONVEYANCE CI t2XN2D2G REVISED TRAFFIC CONTROL PVJI + SHEET Know what's below. 8 6118/2020 CONFORMED FOR CONSTRUCTION IMPROVEMENTS 3 z. FEMME ORTDI.tlwp Call before you dig. A 811v1120 ISSUED FOR BID - ® 02T06 IT ISSUE DATE DESGRIOM PROJECT NUMBER 10173278 CITY OF YAKIMA,WASHINGTON acALE- 41. 41. 1 I 2 I 3 I 4 I 5 I 6 I 7 I 8 NOTES: ,E� _ - - - 1. CONTRACTOR IS RESPONSIBLE FOR FULL -i `•thiji" �4 Y` ��,�,_.� PROPOSED ROAD CLOSURE DETOUR PLANS _ _ AS SHOWN AND APPROVED BY PERMITTING - Close US 12 westbound AGENCIES. . _ � -• ... - US WESTBOUND' r��. ..•_ le11-hlln lane Per 2. CONTRACTOR MAY PROPOSE ALTERNATIVE r,.,' ._ _ CLOSURE ANLVOR DETOUR PLANS.ALTERNATIVE ..`_'f— -_ DAYTIME WORK AREA �T PLANS SHALL BE SUBMITTED FOR RENEW AND APPROVAL BY ALL APPLICABLE PERMITTING r • TECT W. W -- UB EASTBOUND T \ SAT END OFS E` 1 standards AGENCIES FULL APPROVAL FROMAPPLICABLE MUTCDMB PERMITTING AGENCIES SHALL BE GRANTED ROAD PRIOR TO IMPLEMENTATION. g�.'. '. ♦..'���� ♦ ROADCLOBURE !!���:!:!i!i!%is•��.�0���i���•�����:%i!i!i!i!:!::::��0�:�:�0:!i!i!i!%%%iiili!D� �TWA,...... \ 3 ALL S MEETTNAGE E SPACING REQUIREMENTSNVERSION.1.....1 SHALL MEET THE MOST CURRENT VERBpN OF .. . .i♦♦ THE MANUAL FOR UNIFORM TRAFFIC CONTROL ''.�..�.�.�.. . DEVICES. •♦•••1•..!�1!�.1�'1� Y.����. ' �•�, RAGGER. A PLANVERS NOTIELL MEET THE MOST ORE ZONE. ALL REFERENCED WSDOT TRAFFIC COURRENT �......��.�.. TYP CONTROL GUIDELINES FOR MAINTENANCE N O ��.....��.�p��.�, OPERATIONS MSLM. 6. WORK HOURS ARE DEFINED AS 7AM TO 7PM, PHASE 1 TRAFFIC CONTROL PLAN (7)1.� 1 MONDAY TO FRIDAY,EXCLUDING HOLIDAYS. — ilROAD \ -FULL WORK AREA SHOWN. WENT OF WORK AREA AND PHASE 1 TRAFFIC CONTROL SCHEDULE YARYDMLY CLOSURE MILL TIME OF DAY ACIGEY ROAD W POWERHOUSE ROAD DURING WORK HOURS FULL CLOSURE AND DETOUR PER SHEETS ONE-LANE,TWO-WAYFLAOOIND PER WSOOT O2T02U2TG3 TCPf C ONSIDE WORK HOURS PEN FULL CLOSURE AND DETOUR PER SHEETS OPENO2T02.02T03 ANTICIPATED PHASE 1 DURATION:20 WORKING DAYS US 12 WESTBOUND ROAD 1 .• _ CLOSURE POWERHOUSE - - US 12 EASTBOUND w r WBEROgD~_p J ark? At �..'.� .•• ••• .'.�.Y".•Y.•sue..• • T ueE ROAD 1�.�...1...�.�....1..1..1.1.1..1...�.t....1 ial�ili�i�1�.�.�.�....1.�.., .!.'i.:..�.•.•.:.:A..�. 8 .=...,, :..._. LGEURE ACCEPTED AS NOTED Digitally signed by Samuel Robert •Q.•O.�O�i•.. ON:C=US, A._ - .��'•••!%%�% E=sBD,GBLrm°BrlOwsoor.wB.ow. /� N . Samuel Roberto-wsooT,oU=TraD6POImIGn PHASE 2 TRAFFIC CONTROL PLAN I - 1 oDat:2026.rations 09I15 13 38 01-07M•DDRODan SCALE:1'=76' -I- t Wp,y�W sz R� W -•• H WSDOT TRANSPORTATION OPERATIONS PHASE 2 TRAFFIC CONTROL SCHEDULE Within WSDOT Right-of-Way/Limited Access Only TIME OF DAY ACKLEY ROAD W POWERHOUSE ROAD Yakima County DURING WORK HOURS OPEN FULL CLOSURE AND DETOUR PER SHEETS Shall Also Accept °2T°602T0° OUTSIDE WORK HOURS OPEN FULL CLOSURE AND DETOUR PER SHEETS 02T0 6O2`°° APPROVED ANTICIPATED PHASE 2 DURATION:2B WORKING DAYS A Melissa Vantrease/o9.i5.2o26 YAKIMA COUNTY ROADS TRAFFIC ENGINEERING DEPARTMENT PRD,EDTHAMMIER MICHAEL OARELLO,PE 811 DESIGNED BY M.GARELLO NELSON DAM REMOVAL PROJECT: TRAFFIC CONTROL CHECKED BY T.ROBERTS WATER SUPPLY,FISH PASSAGE,AND 1 CHECKED BY T.cIBEs .�' 1 RIVERINE PROCESS IMPROVEMENTS PHASE 1 AND 2 �OF� F)1 DRAWN BY N.MOM PLAN PHASE II - CONVEYANCE Know what's below. IMPROVEMENTS m FLENAME D2Taw SHEET Call before you dig. ® STALE- 02T07 ISSUE DATE OESGRISTOS PROJECTHUMBER 101n276 CITY OF YAKIMA,WASHINGTON U, 1 I 2 I 3 I 4 I 5 I 6 I 7 I8 NOTES: - - - 1. CONTRACTOR IS RESPONSIBLE FOR FULL IMPLEMENTATION AND OPERATION OF —--- -- PLANSPROPOSED ROAD CLOSURE AND DETOUR PS - - - - AS SHOWN AGENCIES.AND APPROVED BY PERMITTING 3. CONTRACTOR MAY PROPOSEALTERNATNE _. - - _ — CONTRACTORCLOSURE ANWOR DETOUR PLANS.ALTERNATIVE PLANS SHALL BE SUBMITTED FOR RENEW AND WE5re APPROVAL BY ALL APPLICABLE PERMITTING _ AS EASTBOU 0;. - -- , AGENCIES FULLAPPROVAL FROM APPLICABLE PERMITTING AGENCIES SI=GRANTED D -V• ROAD - £••- r �`1T W° �IV` I PRIOR TO IMPLEMENTATION. Irifrt .�".-_-. !"!"!� ♦�!.-__ TUGGERS AS NEEDED Z .•••••••r......___ •••••• ..-••••••••••••• 3 ALL SIGNAGE AND SPADING REQUIREMENTS "i'i'i'iii'i'i'i'i'i'i'i'i'i'i'ii'i'i'i'i'iii'i'i'iiii'i'i'i'i'ii•ii'i'ii�i'i'i'i'i'i�iii•i s•• iOF A.."'V.V.%.L•��..t••!4.•��•t•-.—4,4gt -l�l��. L w w••�-l-l-•t•0��W4f.:t•••••••OO•••O•••i s.'.. THE MANUAL F E MOST CURRENT IC CONTROL O THE SHALLMEET FOR UNIFORM TRAFFIC CONTROL •,, �••••••.. RENCEDWSDOT TRAFFIC CONTROL .44•��V•�•....I•I�•,,...,,l VERSIOS NOIE SHALL MEET WORKZOMOST CURRENT V. '•'���•itiiiii iS ��••�•�•�•� CONTROL GUIDELINES FOR MAINTENANCE •.•�••�••••,,,.•••••••••••� OPERATIONS MSLM.. PHASE 3 TRAFFIC CONTROL PLAN 1 1 N •�•�•'•'•.:�i-,-.4 5. ONDAYO MY DEFINED TO — Scue:r.75 _0000, _ WORK AREA AND SINGLE-LANE CLOSURE B.AOMeY Rd 38 shall have flapper priority.T queue shall not be allowed to extend to FULL WORK AREA SHOWN.EXTENT OF USC 12 12 and ail Queued traffic shall be cleared before nett stoppage. WILL RY DAILY. ROAD AI LNOT BEAN ROADE Dw POWERHOUSE PHASE 3 TRAFFIC CONTROL SCHEDULE FLAGGED SIMULTANEOUSLY. TIME OF DAY ACKEY ROAD W POWERHOUSE ROAD DURING WORK HOURS GNEawNE,TWO-WAY FLAGGING AS NEEDED PER ONE-LANE,TWO-WAY FLAGGING AS NEEDED WSDOT TCPf PER WSOOT TCPf D OUTSIDE WORK HOURS OPEN OPEN ANTICIPATED PHASE 3 DURATION:5 WORKING DAYS B ACCEPTED AS NOTED Digitally signed by Samuel Robert DN:C=US, El'Eg.Roberl�W.spoM a.gay. Samuel Robert O=w3DOT,Dce,CR Samun Operations Office,CNSamAM Robot Data:2028.Og.151338:12-07'00' WSDOT TRANSPORTATION OPERATIONS Within WSDOT Right-of-Way/Limited Access Only Yakima County Shall Also Accept APPROVED A Melissa Vantrease/o9.15.2o26 YAKIMA COUNTY ROADS TRAFFIC ENGINEERING DEPARTMENT PROJECT MANAGER MICHAEL IMRE..PE 811 DESIGNED BY M.GARELLO NELSON DAM REMOVAL PROJECT: TRAFFIC CONTROL 1 DESIGNED BY T..ROBESnU WATER SUPPLY,FISH PASSAGE,AND CHECKED BY TGMBe/ F)1RIVERINE PROCESS IMPROVEMENTS DRAWN BY N.SZIGETI PLAN PHASE II - CONVEYANCE PHASE 3 AND 4 Know what's below. '+ ,• IMPROVEMENTS FEMME 021maw1 SHOT Call before you dig. - ® 02T08 ISSUE DATE oESCRIPnaN PROJECT NUMBER 101T5278 CITY OF YAKIMA,WASHINGTON SCALE- ATTACHMENT C WSDOT STANDARD TRAFFIC CONTROL PLANS 46 ti „ * —i to CO SIGN SPACING=X(1) LONGITUDINAL BUFFER SPACE=B Lt. _"I 22 73,.��•, SPEED(MPH) - -- 35 t3 LENGTH(feet) 250 Z.— --- 5 0 0 HIGHWAYS,ROADS,&STREETS I 35-40 MPH 350'•/-I PROTECTIVE VEHICLE ROLL AHEAD DISTANCE=R Q% N 50' TO 100' ---- --- ,-, 4d-80'RECOMMENDED C 41§1‘ 6 DEVICE MIN. STRATEGICALLY'OSITION WORK VEHICLE TO PROT:2I WORK CREW. 7C O 0)IF NECESSARY,SPACING SHOULD BE ADJUSTED(INCREASED OR DECREASED) 0 FOR FIELD CONDITIONS OR BASED ON ENGINEERING JUDGEMENT STATIONARY TRANSPORTABLE"TTENI I�T N to __--- __---_.__..___.__.. _....__...—_--_- _ -_ --- �.�R ROLL AHEAD DISTANCE=R p y -` ` HOST VEHICLE WEIGHT HOST VEHICLE WEIGHT 0 ALL SIGNS ARE 48"X 48"BLACK ON ORANGE 9,900 TO 22,0nC lbs. 2 001•lbs. 0 Cet O= ., ® UNLESS OTHERWISE DESIGNATED - UP TO 40 MPH 15 MPH 60+MPH UP TO 40 MPH 45-55 IVu Y I 60•MPH (D ® WO' 123' 172' 74' 100' lbi: O"b♦p, MAXIMUM CHANNELIZING G .` rQ, 'P DEVICE SPACING(feet) 71C �PQ0' MPH TAPER TANGENT G CO \CZ 1 20-40 f 20 I 40 S. `` '` e 6 DEVICE MI,. 1/ cp `�a W20-7 0 �' ` PCMS ` W3-4 a) O .` B E (OPTIONAL IF 40 MPH OR LESS) 1 2 S. v1P{' ® ® ® PREPARED FLAGGER WATCH 4 rr 3 1 MILE STOPPED (� �c� -I- TO STOP W20-4 AHEAD TRAFFIC 7 tto c ' 4, ONE LANE 2.0 SEC 2.0 SEC -s O -+- ROAD'Cs A PCMS IS RECOMMENDED — ... AHEAD W20-1 I IN EACH DIRECTION 1 MILE H- C tto ROAD FOR QUEUE WARNING ON G ,/o 4,jr" HIGH VOLUME ROADWAYS S w20-7 H r. PREPARED 4.- AHEAD ?1 0.1 X ' - TO STOPBQ / W3-4 7Q Ui (OPTIONAL IF 40 MPH OR LESS) fD Is. ' to P. ROAD \ Ida WORK i AHEAD ONE LANE ROAD NOTES W20-1 AHEAD W20-4 1. Night work requires additional roadway lighting at flagging stations. 2. Recommend extending channelizing device taper across shoulder.Channefzing devices at flogger stations recommended. LEGEND . , ,. ,, . 7: ; 4. For low-volume roadways with short-duration work zones on straight roadways where the flogger is visible to road users approaching from both directions,a single flogger,positioned to be visible from both FLAGGING STATION directions may be used. DI SIGN LOCATION 5. Extend the buffer space to locate the flogger station in advance of a curve,if necessary.Approaching ® co o CHANNELIZING DEVICES motorists need to see the flogger station of a distance no less than the longitudinal buffer space distance. t9 6. Flaggers shall provide control and direction for pedestrians. I- 1LL1 -- -- -----''---- 7. Sign sequence is the same for both directions of travel on the roadway. g ONE-LANE,TWO-WAY TRAFFIC CONTROL WITH FLAGGERS m. a TCP 1 APPROVED AS NOTED 32Lcb N Melissa Vantrease/o9.15.2026 w N YAKIMA COUNTY ROADS TRAFFIC ENGINEERING DEPARTMENT ATTACHMENT D APPROXIMATE SCHEDULE 48 NELSON DAM PHASE 2 CPR 08:WEST POWERHOUSE(5X12)SCHEDULE 08-Sep-26 Activity ID Activity Name Onginal Remaining Actual Start Finish Late Start Late Finis Total Calendar September 2026 October 2026 November 2026 Duration Duration Duration Roat I 13 I 20 I. 27 04 I 11 18 I 25 01 08 15 l 22 r 29 NELSON DAM PHASE 2-W POWERHOUSE RD.REALIGNMENT CPR 76 65 0 14-Sep-26A 19-Nov-26 21-Sep-26 19-Nov-26 0 5x12 N - (19-Nov-26,NELSON DAM PHASE 2-W POWEF WORKING DAYS 76 65 0 14-Sep-26A 19-Nov-26 21-Sep-26 19-Nov-26 0 5x12 N (19-Nov-26,WORKING DAYS MOBILIZATION&START UP 15 4 0 14-Sep-26A 23-Sep-26 21-Sep-26 23-Sep-26 0 5x12 N 123-Sep-26,MOBILIZATION&START UP A1000 PUBLIC TRAFFIC NOTICE 0 0 0 14-Sep-26A I21-Sep-26 1 I 5x12 t PUBLIC TRAFFIC NOTICE A1010 MOBILIZATION 4 4 0 21-Sep-26 23-Sep-26 21-Sep-26 23-Sep-26 0 5x12 MOBILIZATION A1020 ESTABLISH&VERIFY PIPE ALIGNMENT-SURVEY 2 2 0 21-Sep-26 22-Sep-26 22-Sep-26 23-Sep-26 2 5x12 STABLISH&VERIFY PIPEALIGNMBJT-SURVEY A1030 INSTALL TESC MEASURES 2i 2I OI21-Sep-26 122Sep-26 22-Sep-26 23-Sep-26 21 5x12 I STALL TESC MEASURES TRAFFIC CONTROL 611 611 OI 23-Sep-26 19-Nov-26 23-Sep-26 19-Nov-26 i 01 5x12 N /19-Nov-26,TRAFFIC CONTROL I A1060 ACKLEY ROAD CLOSURE FOR PIPE CROSSING 9 9 0 23-Sep-26 01-Oct-26 23-Sep-26 01-Oct-26 0 5x12 n ACKLEY ROAD CLOSURE FOR PIPE CROSSING A1070 SINGLE LANE CLOSURE WEST POWERHOUSE ROAD 11 11 0 23-Sep-26 02-Oct-26 23-Sep-26 02-Oct-26 0 5x12 ►, INGLE LANE CLOSURE WEST POWERHOUSE ROAD A1100 WEST POWERHOUSE ROAD CLOSURE 50 50 0 05-Oct-26 19-Nov-26 05-Oct-26 19-Nov-26 0 5x12 +! - WEST POWERHOUSE ROAD CLOSURE A1160 REMOVE TC DEVICES&FULLY OPEN ROAD 0 0 0 19-Nov-26 19-Nov-26 �0 5x12 LEMOVE TC DEVICES&FULLY OPEN ROAD ACKLEY ROAD CROSSING 11 11 0 23-Sep-26 02-Oct-26 23-Sep-26 02-Oct-26 I 01 5x12 N , •2-O b26,ACKLEY ROAD CROSSING A1230 SAWCUT&REMOVE ASPHALT 1 1 023-Sep-26 24-Sep-26 23-Sep-26 24-Sep-26 0 5x12 SAWCUT&REMOVE ASPHALT A1240 EXCAVATE PIPE TRENCH 2 2 0I24-Sep-26 25-Sep-26 24-Sep-26 25-Sep-26 0 5x12 EXCAVATE PIP ETRENC-I A1250 INSTALL SHORING 2 2 0!24-Sep-26 25-Sep-26 24-Sep-26 25-Sep-26 0 5x12 TALL SHORING A1260 FUSE&DE-BEAD 42"HDPE PIPE 2 21 OI 23-Sep-26 24-Sep-26 124-Sep-26 ,25-Sep-26 I 11 5x12 it 1 FUSE&DE-BEAD 42"HDPE PIPE A1270 INSTALL 42"HOPE PIPE TO STA 14+80 2 2. 01 25-Sep-26 28-Sep-26 125-Sep-26 12&Sep-26 01 5x12 INSTALL 42"HDPE PIPE IO STA 14+80 A1280 CONNECT42"HDPE PIPE TO 45 DEGREE BEND @ STA 16+27 1 1 OI 28-Sep-26 28-Sep-26 128-Sep-26 128-Sep-26 0 5x12 NNECT 42"HDP E PIPE TO 45 DEGREE BEND @ STA 16+27 A1290 !BACKFILL PIPE TRENCH&REMOVE SHORING 2 2 0 29-Sep-26 30-Sep-26 !29-Sep-26 30-Sep-26 0 5x12 BACKFILL PI PE TRENCH&REMOVE SHORING A1300 RESTORE ACKLEY RD 2 2 0 01-Oct-26 02-Oct-26 01-Oct-26 02-Oct-26 0 5x12 L. EST(REACKLEY RD WEST POWERHOUSE RD.STA 14+80 TO STA 6+80 39 39 0 25-Sep-26 30-Oct-26 29-Sep-26 30-Oct-26 0 5x12 N I 30-Oct-26,WEST POWERHOUSE RD.STA14+80 TO STA6+80 A1320 POTHOLE EXISTING UTILITIES 2 2 0 30-Sep-26 01-Oct-26 30-Sep-26 01-Oct-26 0 5x12 POTHOLE EXISTING UTILITIES A1330 I SAWCUT&REMOVE ASPHALT 2 21 01 01-Oct-26 02-Oct-26 I01-Oct-26 IO2-Oct-26 0 5x12 SAWCJT&REMOVE ASPHALT A1340 EXCAVATE PIPE TRENCH 3 3 0'05-Oct-26 06-Oct-26 I05-Oct-26 I06-Oct-26 0 5x12 EXCAVATE PIPE TRENCH A1350 INSTALL SHORING 3 3 0 05-Oct-26 06-Oct-26 05-Oct-26 06-Oct-26 0 5x12 STALL SHORING A1360 FUSE&DE-BEAD 42"HDPE PIPE 8 8 0 25-Sep-26 02-Oct-26 29-Sep-26 06-Oct-26 4 5x12 +I I FUSE&DE-BEA 42"HDPE PIPE A1370 CONNECT TO 45 DEGREE BEND @ STA 14+80(FLANGE) 1 1 0 07-Oct-26 07-Oct-26 07-Oct-26 07-Oct-26 0 5x12 CONNECT TO 45 DEGREE BEND@ STA 14+80(FLANGE) A1380 INSTALL42"HDPE PIPE ALONG WEST POWERHOUSE RD.TO-STA 12+80 21 21 0 07-Oct-26 08-Oct-26 07-Oct-26 08-Oct-26 0 5x12 INSTALL42"HDPE PIPE ALONG WEST POWERHOUSE RD.TO-STA 12+80 A1390 BACKFILL PIPE TRENCH&REMOVE SHORING 3 31 0,08-Oct-26 12-Oct-26 08-Oct-26 12-Oct-26 0 5x12 _ BACKFILL PIPE TRENCH&REMOVE SHOPoNG A1400 EXCAVATE PIPE TRENCH 3 3 0I12-Oct-26 14-Oct-26 12-Oct-26 14-Oct-26 0 5x12 EXCAVATE PIPE TRENCH A1410 INSTALL SHORING 3 3 0 12-Oct-26 14-Oct-26 12-Oct-26 14-Oct-26 0 5x12 STALL SHORING A1420 CONNECT VIA FLANGE @ STA 12+80 1 1 0 14-Oct-26 1 14-Oct-26 1 14-Oct-26 1 14-Oct-26 0 5x12 CONNECT VIA FLANGE @ STA 12+80 A1430 INSTALL42"HDPE PIPE ALONG WEST POWERHOUSE RD.TO-STA 10+80 2 2 0 14-Oct-26 15-Oct-26 14-Oct-26 15-Oct-26 0 5x12 INSTALL 42'HDPE PIPE ALONG WEST POWERHOUSE RD.TO-STA 10+80 A1440 BACKFILL PIPE TRENCH&REMOVE SHORING 2 2 0,15-Oct-26 16-Oct-26 15-Oct-26 16-Oct-26 0- 5x12 BACKFILL PIPE TRENCH&REMOVE SHORING A1450 EXCAVATE PIPE TRENCH 3 3 0I19-Oct-26 20-Oct-26 19-Oct-26 20-Oct-26 I 0 5x12 EXCAVATE PIPE TRENCH A1460 INSTALL SHORING 3 3 0 19-Oct-26 120-Oct-26 19-Oct-26 20-Oct-26 0 5x12 STALL SHORING A1470 'CONNECT VIA FLANGE @ STA 10+80 1 1 0 21-Oct-26 21-Oct-26 I21-Oct-26 121-Oct-26 0 5x12 CONNECT VIA FLANGE @ STA 10+80 A1480 INSTALL42"HDPE PIPEALONG WEST POWERHOUSE RD.TO-STA 8+80 2 2 0 21-Oct-26 22-Oct-26 21-Oct-26 22-Oct-26 0 5x12 INSTALL42"HDPE PIPE ALONG WESTPOWERHOUSE RD.TO-STA 8+80 A1490 BACKFILL PIPE TRENCH&REMOVE SHORING 2 2 0,22-OG-26 23-Oct-26 22-Oct-26 23-Oct-26 0 5x12 BACKFILL PIPE TRENCH&REMOVE SHORING A1500 EXCAVATE PIPE TRENCH 3 3 0I23-Oct-26 27-Oct-26 23-Oct-26 27-Oct-26 I—Td 5x12 EXCAVATE PIPE TRENCH A1510 INSTALL SHORING 3 3 0 23-Oct-26 27-Oct-26 23-Oct-26 27-Oct-26 0 5x12 STALL SHORING A1520 CONNECT VIA FLANGE @ STA 8+80 1 1 0.27-Oct-26 1 28-Oct-26 127-Oct-26 128-Oct-26 0 5x12 CONNECT VIA FLANGE @ STA 8+80 A1530 INSTALL42"HDPE PIPEALONG WEST POWERHOUSE RD.TO-STA6+80 2 2 0!27-Oct-26 28-Oct-26 27-Oct-26 28-Oct-26 0 5x12 INSTALL42"HDPE PIPE ALONG WEST POWERHOUSE RD.TO-STA6+80 A1540 BACKFILL PIPE TRENCH&REMOVE SHORING 3 3 0 29-Oct-26 30-Oct-26 29-Oct-26 30-Oct-26 0 5x12 BACKFILL PIPE TRENCH&REMOVE SHORING WEST POWERHOUSE RD.STA 6+80 TO STA4+25 15 15 0 02-Nov-26 13-Nov-26 02-Nov-26 13-Nov-26 0 5x12 N I 13-Nov-26,WEST POWERHOUSE RD.STA6+80 TO STA4+25 A1550 EXCAVATE ACROSS WEST W ERHOU SE RD.TOWARD BORE PIT 3 3, 0,02-Nov-26 03-Nov-26 02-Nov-26 03-Nov-26 0 5x12 EXCAVATE ACROSS WEST FOINERHOUSE RD.TOWARD BORE PIT A1560 INSTALL SHORING 3 3 OI 02-Nov-26 I 03-Nov-26 02-Nov-26 03Nov-26 0 5x12 STALL SHORING — A1570 CONNECT VIA FLANGE @ STA 6+80 1 1 0 04-Nov-26 04-Nov-26 04-Nov-26 04-Nov-26 0 5x12 CONNECT VIA FLANGE @ STA 6+80 — A1580 INSTALL42"HDPE PIPE TO BORE PIT-STA4+25 2 2 0.04-Nov-26 05-Nov-26 04-Nov-26 05-Nov-26 0 5x12 INSTALL42"HDPE PIPE TO BORE PIT-STA 4+25 A1590 BACKFILL PIPE TRENCH&REMOVE SHORING W THIN WEST POWERHOUSE 3 31 0I 05-Nov-26 09-Nov-26 I05-Nov-26 09-Nov-26 Io 5x12 I BACKFILL PIPE TRENCH&REMOVE SHORING WTHINWEST POWERHOUSE RD. A1600 FUSE ONA BLIND FLANGE WITHATEST PORT 1 1 0 05-Nov-26 05-Nov-26 I05-Nov-26 I05-Nov-26 0 5x12 FUSE ON A BLIND FLANGE WTHA TEST PORT A1620 I REMOVE BLIND FLANGE 1 1 0.11-Nov-26 11-Nov-26 11-Nov-26 11-Nov-26 0 5x12 REMOVE BLIND FLANGE A1630 I CONNECT42"HDPE PIPE VIA ELECTROFUSION COUPLER @-STA 4+25 1 1 0 12-Nov-26 12-Nov-26 12-Nov-26 12-Nov-26 0 5x12 CONNECT 42"HDPE PIPE VIA E-ECTROFUSION COUPLER @-STA 4+25 A1640 I BACKFILL PIPE TRENCH&REMOVE SHORING 2 2 0.12-Nov-26 13-Nov-26 12-Nov-26 13-Nov-26 0 5x12 BACKFILL PIPE TRENCH&REMOVE SHORING TESTING. 5 51 OI 06-Nov-26 11-Nov-26 06-Nov-26 11-Nov-26 0 5x12 N I 11-Nov-26,TESTI G A1610 I TEST 42"HDPE PIPE FROM-STA4+25 TO-STA 19+00 5 5 01 06-Nov-26 11-Nov-26 06-Nov-26 11-Nov-26 0 5x12 TEST42"HDPE PE FROM-STA 4+25 TO-STA 19+00 RESTORATION 3 3 0116-Nov-26 17-Nov-26 16-Nov-26 17-Nov-26 0 5x12 1 V 17-Nov-.6,RESTORATION A1650 I RESTORE PIPE TRENCH 3 3 0 16-Nov-26 17-Nov-26 16-Nov-26 17-Nov-26 0 5x12 RESTOF E PIPE TRENCH CLEANUP&DEMOBILIZATION 5 5 0 16-Nov-26 19-Nov-26 16-Nov-26 19-Nov-26 01 5x12 NI 9-Nov-26,CLEANUP&DEMOBILIZATION A1670 GENERAL SITE GRADING&CLEANUP 5 5 0 16-Nov-26 19-Nov-26 16-Nov-26 19-Nov-26 I 0 5x12 GENERAL SITE GRADING&CLEANUP A1690 DEMOBILIZE 0 0 0 19-Nov-26 I19-Nov-26 I 0 5x12 froOEMOBILIZE I I Actual Work 11 Critical Remaining Work VI Summary INTERWEST CONSTRUCTION, INC. Page 1 of 1 I I Remaining Work • • Milestone ©Oracle Corporatio- 49 O u7 SEPTEMB-ER OCTOBER i i 21 22 23 24 25 28 29 30 1 2 I 5 6 7 8 19 112 13 14 15 16 19 20 21122 23 26 27 28 2'0 38 Accelerated 60-hr work weeks- working days Week 1 Week 2 Week 3 Week 4 Weeks Week6 I Ackley fully closed 211l days Phase 1 W5DQT Ackley Closure I 1Qdlk 111 .1 West Powerhouse Road- r=;,?-_E_:_d;Ingle-lane closure during work hour:, 20days Phase 2 West Powerhouse Road fully closed Phase 3 Pipeline Testing-Trench and Road Restoration iRemove TCP Devices r NOVEMBER DEC 2 3 4 5 6 9 10 11 12 13 16 17 18 19120 23 24 25 26 27 30 1 2 3 4 Accelerated 60-hrwork weeks- working days _ Week 7 _ Week 8 Week 9 Week 10 Week 11 Ackley fully closed Phase 1 WSDOTAc:kley Closure I West Powerhouse Road- - . - lk hours Phase 2 West Powerhouse Road;u!:i closed during work hours - UMER - Phase 3 Pipeline Testing-Trench and Road Restoration 5 days ' i Remove TCP Devices&Demobilization I I. ATTACHMENT E WSDOT PROJECT SCHEDULE 51 N 11.0 US12 ACKLEY&ESCHBACH BASELINE SCHEDULE BASELINE SCHEDULE 8.28.26 10-Sep-26 11:11 SEPTEMBER 14,2026 Activity ID Activity Name Original Start I Finish 1 Total Float August2026 September2026 October2026 November2026 I December2026 I January 2027 Duration 02 I 09 I 16 I 23 I 30 I 06 13 I 20 I 27 I 04 I 11 I 18 I 25 01 I 08 I 15 I 22 I 29 I 06 I 13 I 20 I 27 I 03 I 10 I 17 124 "_,§ 110-Nov-26,USI2 ACKLEY&ESCHBACH CAL GENERAL REQUIREMENTS 0 19-Aug-26A 14-Sep-26 0 N • 14-Sep-26,GE NERAL REQUIREMENTS I A1520 Contract Execution 0 19-Fug-26A •Contract Fi,ontion j A1530 Pmconstructon Meeting 0 02-Sep-26 A Preconstrudion Meeting V A1540 NTP 0 14-Sep-26 0 NW CALENDAR DAYS 62 14-Sep-26 10-Nov-26 0 110-Nov-26,CALENDAR DAYS A1480 Construction Start 0 14-Sep-26 0 Construction Start A1481 HIGHWAY12 LANE SHIFTSATACKLEY ROAD 60 15-Sep-26 10-Nov-26 0 1.-11IIGHWAY12 LANE SHIFTSATACKLEY ROAD A1482 ACKLEY ROAD CLOSED 13 01-Oct-26 14-0d-26 0 F-ACKLEY ROAD CLOSED A1484 ESCHBACH-Lane closures and turn lane closure Start 27 01-Oct-26 08-Nov-26 1 I l-ESCHBACH-Lane dosures and turn lane closure Start A1490 Traffic Control Setup and Class A Signing 2 14-Sep-26 15-Sep-26 0 I = Traffic Con •I Setup and Claris A Signing A1500 Survey Control,Layout,Utility Locates and Pothole 2 14-Sep-26 16-Sep-26 1 •-Survey C•nfiol,Layout,Utilitjr Locates and Pothole A1510 Erosion Control,Inlet protection,and SWPPP setup 2 15-Sep-26 17-Sep-26 0 radon I•ntrol,Inlet protection,and SWPPP setup ACKLEY ROAD 39 15-Sep-26 21-Oct-26 0 21-0d-26,ACKLEY OAD A1270 I ACKLEYSaHcut,Asphalt removal,and clearing/grubbing 4 15-Sep-26 21-Sep-26 0 AC I EYSavcut,Asphalt removal,and Bearing/grubbing A1280 ACKLEY-Ilumination trench,bore,foundations 8 21-Sep-26 01-Oct-26 4 1.-A614&EYillurrlination trench,bore,founda4ons A1290 ACKLEY-Highway crossing night work(24",12",CB,CDF) 4 21-Sep-26 25-Sep-26 0 �-� ighway dossing nightvbrk(24",12", B,CDF) 1•11.1A1300 ACKLEY-18",12"Storm pipe,inlets,and drainage work 4 25-Sep-26 01-Oct-26 0 I_C• Y-18";12'Storm pipe,inlets,and brainage work A1310 ACKLEY-Storm testing,adjustments,and connections 4 01-0d-26 07-Oct-26 0 �. CKLEY-Storm testing,adjustments,and connections A1320 ACKLEY-roadway excavation and subgrade prep 4 01-Oct-26 07-Oct-26 0 'CKLcs-roadway excavation and bgrade prep RIM A1330 ACKLEY-0SBC placement and fine grade 4 01-0d-26 07-Oct-26 0 "•'CKLEtir'CSBC placement and fin grade A1340 ACKLEY-Roundabout curb 3 02-Oct-26 07-Oct-26 0 ^ 'CKLEY-Roundabout curb A1350 ACKLEY-HMA paving bottom lifts 2 07-0d-26 09-Oct-26 0 ACKt EY-HMApavirig bottom Ilt A1360 ACKLEY-Planing 2 09-Oct-26 13-Oct-26 0 n ACKLEY-Planing A1370 ACKLEY-Final pave 3 09-Oct-26 14-Oct-26 0 J 'CKLEY-Final pave A1380 ACKLEY-Extruded curb 2 14-0d-26 16-Oct-26 0 -0 ACKLEY-Extruded curb A1390 j ACKLEY-guardrail,hightension cable barrier,and SRGS 3 16-Oct-26 21-Oct-26 0 = ACKLEY-guardrail,h h-tension cable barrier,and SRGS ESCHBACH ROAD 29 01Cd-26 28-Oct-26 0 28-0d-26,E CHBACH ROAD A1405 ESCHBACH-Removal and salvage cable barrier 2 01-Oct-26 103-0d-26 2 ESCHBACH-Removal ant salvage cape barrier A1410 ESCHBACH-sawcut and asphalt removals 5 01-0d-26 08Oct-26 1 I ESCHB-iCH-sawcut bad asphattiemovals A1420 ESCHBACH-roadway excavation and subgrade prep 5 05-Oct-26 09-Oct-26 0 ESCHl1ACH-roadway excavatio and subgrade prep A1430 I ESCHBACH-CSBC placement 4 06-0d-26 09-Oct-26 0 ESCHI.IACHCSBCiplacement• A1440 ESCHBACHfne grade and paving release 3 12-0d-26 14-Oct-26 0 E;CHBACH+me grade arid paving release A1441 ESCHBACH-Bottom lifts HMA 2 14-Oct-26 16-Oct-26 0 ESCHBACH- ottom lifts MA A1450 ESCHBACH-Milling 2 16-0d-26 19-Oct-26 0 I ESCHBACH-Milling A1451 ESCHBACHfnal HMA 2 19-Oct-26 21-Oct-26 0 g ESCHBACH-Final H A A1460 ESCHBACH-Guardrail and high-tension cable barrier restoration 5 21-0d-26 28-Oct-26 0 =7 ESCHBACHjGuardrail and high:-tension cable barrier restoration RESTORATION&FINISHES 14 21-Oct-26 10-Nov-26 I 0 10-Nov-26,RESTORATION&FINISHES A360 Compost,VFS,hydroseed,and roadside restoration 5 30-Oct-26 06-Nov-26 0 I Corrllpost,VFS,hydroseed,and roadside restoration A370 Both Sites-striping,permanent signing,and guide posts 7 21-Oct-26 30-Oct-26 0 1 B(.dh Sites 4stiping,perrnaneht signing,and guide posts A380 Final cleanup,punch list,and corrective work 2 06-Nov-26 10-Nov-26 0 C04inal cleanup,pungi list,and corrective work A390 Physical Completion/Contract Working Day 55 0 1 10-Nov-26 0 i hysical Completion/Contract Working Day 55 Project Baseline Bar O Remaining Work • •Milestone Page 1 of 1 O Actual Work O Critical Remaining Work 1,Summary EquipmentWatch.. Combined hourly rate with attachments=$113.16 www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '02-25 in All Saved Models January 5, 2026 Caterpillar D6K LGP(disc.2015) i• '�i Lgp Crawler Dozers Size Class: Weight:29 hp 29690 lbs Configuration for D6K LGP(disc.2015) Dozer Type VPAT Horsepower 125.0 hp Operator Protection EROPS Power Mode Diesel Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$10,180.00 USD$2,850.00 USD$715.00 USD$110.00 USD$44.39 USD$102.23 Adjustments Region USD$641.34 USD$179.55 USD$45.04 USD$6.93 (Washington:106.3%) Model Year(2015:100%) - - - - AdjustedHourlyOwnership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$10,821.34 USD$3,029.55 USD$760.04 USD$116.93 USD$44.39 USD$105.87 Non-Active Use Rates Hourly Standby Rate USD$30.74 Idling Rate USD$74.31 Rate Element Allocation Element Percentage Value Depreciation(ownership) 25.22% USD$2,567.02/mo Overhaul(ownership) 52.59% USD$5,353.24/mo CFC(ownership) 11.26% USD$1,146.41/mo Indirect(ownership) 10.94% USD$1,113.33/mo Fuel(operating)@ USD 3.83 28.9% USD$12.83/hr Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 53 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '02-25/ripper in All Saved Models January 5, 2026 Miscellaneous MSR-129HP Crawler Tractor Multi-Shank Rippers Size Class: To 260 hp Weight: 1011 2110 lbs Configuration for MSR-129HP Horsepower 85.0 hp Number Of Shanks 3.0 Ripper Type Parallelogram Power Mode Hydraulic Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$690.00 USD$195.00 USD$49.00 USD$7.00 USD$3.19 USD$7.11 Adjustments Region USD$31.74 USD$8.97 USD$2.25 USD$0.32 (Washington:104.6%) Model Year(2018:99.86%) (USD$1.00) (USD$0.28) (USD$0.07) (USD$0.01) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$720.74 USD$203.69 USD$51.18 USD$7.31 USD$3.19 Non-Active Use Rates Hourly Standby Rate USD$2.05 Idling Rate USD$4.10 Rate Element Allocation Element Percentage Value Depreciation(ownership) 48.3% USD$333.24/mo Overhaul(ownership) 31.61% USD$218.10/mo CFC(ownership) 8.69% USD$59.97/mo Indirect(ownership) 11.4% USD$78.69/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 54 EquipmentWatch.. Combined hourly rate with attachments=$141.37 www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-109 in All Saved Models January 5, 2026 Caterpillar 323 , Crawler Mounted Hydraulic Excavators tam- "__NM' v Size Class: 24.5-28.4mt Weight: NIA Configuration for 323 Horsepower 162 hp Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$12,505.00 USD$3,500.00 USD$875.00 USD$130.00 USD$35.55 USD$106.60 Adjustments Region(Washington:106%) USD$750.30 USD$210.00 USD$52.50 USD$7.80 Model Year(2018:99.89%) (USD$14.02) (USD$3.92) (USD$0.98) (USD$0.15) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$13,241.28 USD$3,706.07 USD$926.52 USD$137.65 USD$35.55 USD$110.78 Non-Active Use Rates Hourly Standby Rate USD$37.62 Idling Rate USD$87.02 Rate Element Allocation Element Percentage Value Depreciation(ownership) 31.78% USD$3,973.87/mo Overhaul(ownership) 44.15% USD$5,520.93/mo CFC(ownership) 15.44% USD$1,930.98/mo Indirect(ownership) 8.63% USD$1,079.22/mo Fuel(operating)@ USD 3.83 33.16% USD$11.79/hr Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 55 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-10911 in All Saved Models January 5, 2026 Miscellaneous HD1.750 Heavy Duty Excavator Buckets Size Class: All Weight: 1011 3332 lbs Configuration for HD1.75O Rated Capacity 1.75 cu yd Width 30-55 in Power Mode Manual Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$935.00 USD$260.00 USD$65.00 USD$10.00 USD$3.14 USD$8.45 Adjustments Region USD$98.18 USD$27.30 USD$6.82 USD$1.05 (Washington:110.5%) Model Year(2018:99.87%) (USD$1.37) (USD$0.38) (USD$0.10) (USD$0.01) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,031.80 USD$286.92 USD$71.73 USD$11.04 USD$3.14 LISC4Ek.00 Non-Active Use Rates Hourly Standby Rate USD$2.93 Idling Rate USD$5.86 Rate Element Allocation Element Percentage Value Depreciation(ownership) 20.64% USD$192.99/mo Overhaul(ownership) 66.67% USD$623.37/mo CFC(ownership) 5.62% USD$52.51/mo Indirect(ownership) 7.07% USD$66.12/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 56 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-10912 in All Saved Models January 5, 2026 Miscellaneous HD 2.750 Heavy Duty Excavator Buckets Size Class: All Weight: 1011 4300 lbs Configuration for HD 2.750 Rated Capacity 2.75 cu yd Width 55.0 in Power Mode Manual Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$1,100.00 USD$310.00 USD$78.00 USD$12.00 USD$3.37 USD$9.62 Adjustments Region USD$115.50 USD$32.55 USD$8.19 USD$1.26 (Washington:110.5%) Model Year(2018:99.87%) (USD$1.61) (USD$0.45) (USD$0.11) (USD$0.02) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,213.89 USD$342.10 USD$86.08 USD$13.24 USD$3.37 US['41027. Non-Active Use Rates Hourly Standby Rate USD$3.45 Idling Rate USD$6.90 Rate Element Allocation Element Percentage Value Depreciation(ownership) 20.64% USD$227.05/mo Overhaul(ownership) 66.67% USD$733.38/mo CFC(ownership) 5.62% USD$61.78/mo Indirect(ownership) 7.07% USD$77.79/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 57 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-1O91Thumb in All Saved Models January 5, 2026 Miscellaneous 28HTWL Hydraulic Bucket Thumbs Size Class: All Weight: 1011 NIA Configuration for 28HTWL Power Mode Hydraulic Recommended Machine Weight 24.1-28.0 mt Type Wide Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$1,385.00 USD$390.00 USD$98.00 USD$15.00 USD$2.62 USD$10.49 Adjustments Region USD$148.20 USD$41.73 USD$10.49 USD$1.61 (Washington:110.7%) Model Year(2018:99.87%) (USD$2.04) (USD$0.57) (USD$0.14) (USD$0.02) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,531.16 USD$431.16 USD$108.34 USD$16.58 USD$2.62 USD$11.32 Non-Active Use Rates Hourly Standby Rate USD$4.35 Idling Rate USD$8.70 Rate Element Allocation Element Percentage Value Depreciation(ownership) 18.99% USD$262.99/mo Overhaul(ownership) 68.73% USD$951.86/mo CFC(ownership) 5.44% USD$75.33/mo Indirect(ownership) 6.85% USD$94.82/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 58 EquipmentWatch.. Combined hourly rate with attachments=$179.45 www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-130 in All Saved Models January 5, 2026 Caterpillar 335 , Crawler Mounted Hydraulic Excavators tam "__NM' Size Class: 33.5-40.4 mt Weight: NIA Configuration for 335 Bucket Capacity 2.01 cu yd Horsepower 273 hp Operating Weight 77000 lbs Power Mode Diesel Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$16,090.00 USD$4,505.00 USD$1,125.00 USD$170.00 USD$50.09 USD$141.51 Adjustments Region(Washington:106%) USD$965.40 USD$270.30 USD$67.50 USD$10.20 Model Year(2022:99.94%) (USD$10.37) (USD$2.90) (USD$0.73) (USD$0.11) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$17,045.03 USD$4,772.40 USD$1,191.77 USD$180.09 USD$50.09 USD$146.94 Non-Active Use Rates Hourly Standby Rate USD$48.42 Idling Rate USD$116.72 Rate Element Allocation Element Percentage Value Depreciation(ownership) 31.78% USD$5,113.12/mo Overhaul(ownership) 44.15% USD$7,103.70/mo CFC(ownership) 15.44% USD$2,484.56/mo Indirect(ownership) 8.63% USD$1,388.62/mo Fuel(operating)@ USD 3.83 39.67% USD$19.87/hr Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book@ Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 59 'i EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-13011 in All Saved Models January 5, 2026 Miscellaneous HD 2.00 Heavy Duty Excavator Buckets Size Class: All Weight: 1011 3631 lbs Configuration for HD 2.00 Rated Capacity 2.0 cu yd Width 33-39 in Power Mode Manual Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$955.00 USD$270.00 USD$68.00 USD$10.00 USD$3.16 USD$8.59 Adjustments Region USD$100.28 USD$28.35 USD$7.14 USD$1.05 (Washington:110.5%) Model Year(2022:99.89%) (USD$1.11) (USD$0.31) (USD$0.08) (USD$0.01) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,054.16 USD$298.04 USD$75.06 USD$11.04 USD$3.16 'R, Non-Active Use Rates Hourly Standby Rate USD$2.99 Idling Rate USD$5.99 Rate Element Allocation Element Percentage Value Depreciation(ownership) 20.64% USD$197.12/mo Overhaul(ownership) 66.67% USD$636.71/mo CFC(ownership) 5.62% USD$53.63/mo Indirect(ownership) 7.07% USD$67.54/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 CO EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-13012 in All Saved Models January 5, 2026 Miscellaneous HD 3.750 Heavy Duty Excavator Buckets Size Class: All Weight: 1011 6720 lbs Configuration for HD 3.750 Rated Capacity 3.75 cu yd Width 45-55 in Power Mode Manual Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$1,320.00 USD$370.00 USD$93.00 USD$14.00 USD$3.69 USD$11.19 Adjustments Region USD$138.60 USD$38.85 USD$9.77 USD$1.47 (Washington:110.5%) Model Year(2022:99.89%) (USD$1.54) (USD$0.43) (USD$0.11) (USD$0.02) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,457.06 USD$408.42 USD$102.66 USD$15.45 USD$3.69 USD$11.97 Non-Active Use Rates Hourly Standby Rate USD$4.14 Idling Rate USD$8.28 Rate Element Allocation Element Percentage Value Depreciation(ownership) 20.64% USD$272.46/mo Overhaul(ownership) 66.67% USD$880.06/mo CFC(ownership) 5.62% USD$74.13/mo Indirect(ownership) 7.07% USD$93.35/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 61 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-13OlThumb in All Saved Models January 5, 2026 Miscellaneous 4OHTWL Hydraulic Bucket Thumbs Size Class: All Weight: 1011 NIA Configuration for 4OHTWL Power Mode Hydraulic Recommended Machine Weight 33.1-40.0 mt Type Wide Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$1,395.00 USD$390.00 USD$98.00 USD$15.00 USD$2.63 USD$10.56 Adjustments Region USD$149.26 USD$41.73 USD$10.49 USD$1.61 (Washington:110.7%) Model Year(2022:99.89%) (USD$1.63) (USD$0.46) (USD$0.11) (USD$0.02) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,542.64 USD$431.27 USD$108.37 USD$16.59 USD$2.63 USD$11.39 Non-Active Use Rates Hourly Standby Rate USD$4.38 Idling Rate USD$8.76 Rate Element Allocation Element Percentage Value Depreciation(ownership) 18.99% USD$264.89/mo Overhaul(ownership) 68.73% USD$958.74/mo CFC(ownership) 5.44% USD$75.87/mo Indirect(ownership) 6.85% USD$95.50/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 62 EquipmentWatch.. Combined hourly rate with attachments=$136.09 www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-139 in All Saved Models January 5, 2026 Komatsu PC238USLC-11 Crawler Mounted Hydraulic Excavators lArs tam Size Class: 24.5-28.4mt Weight: NIA Configuration for PC238USLC-11 Horsepower 165.0 hp Operating Weight 54230.0 lbs Power Mode Diesel Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$11,790.00 USD$3,300.00 USD$825.00 USD$125.00 USD$34.48 USD$101.47 Adjustments Region(Washington:106%) USD$707.40 USD$198.00 USD$49.50 USD$7.50 Model Year(2024:99.98%) (USD$2.01) (USD$0.56) (USD$0.14) (USD$0.02) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$12,495.39 USD$3,497.44 USD$874.36 USD$132.48 USD$34.48 USD$105.48 Non-Active Use Rates Hourly Standby Rate USD$35.50 Idling Rate USD$83.01 Rate Element Allocation Element Percentage Value Depreciation(ownership) 31.78% USD$3,746.66/mo Overhaul(ownership) 44.15% USD$5,205.26/mo CFC(ownership) 15.44% USD$1,820.57/mo Indirect(ownership) 8.63% USD$1,017.51/mo Fuel(operating)@ USD 3.83 34.83% USD$12.01/hr Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book@ Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 63 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-13911 in All Saved Models January 5, 2026 Miscellaneous HD1.750 Heavy Duty Excavator Buckets Size Class: All Weight: 1011 3332 lbs Configuration for HD1.75O Rated Capacity 1.75 cu yd Width 30-55 in Power Mode Manual Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$935.00 USD$260.00 USD$65.00 USD$10.00 USD$3.14 USD$8.45 Adjustments Region USD$98.18 USD$27.30 USD$6.82 USD$1.05 (Washington:110.5%) Model Year(2024:99.97%) (USD$0.30) (USD$0.08) (USD$0.02) (USD$0.00) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,032.87 USD$287.22 USD$71.80 USD$11.05 USD$3.14 LISD, Non-Active Use Rates Hourly Standby Rate USD$2.93 Idling Rate USD$5.87 Rate Element Allocation Element Percentage Value Depreciation(ownership) 20.64% USD$192.99/mo Overhaul(ownership) 66.67% USD$623.37/mo CFC(ownership) 5.62% USD$52.51/mo Indirect(ownership) 7.07% USD$66.12/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 64 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for 06-13912 in All Saved Models January 5, 2026 Miscellaneous HD 2.750 Heavy Duty Excavator Buckets Size Class: All Weight: 1011 4300 lbs Configuration for HD 2.750 Rated Capacity 2.75 cu yd Width 55.0 in Power Mode Manual Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$1,100.00 USD$310.00 USD$78.00 USD$12.00 USD$3.37 USD$9.62 Adjustments Region USD$115.50 USD$32.55 USD$8.19 USD$1.26 (Washington:110.5%) Model Year(2024:99.97%) (USD$0.35) (USD$0.10) (USD$0.03) (USD$0.00) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,215.15 USD$342.45 USD$86.16 USD$13.26 USD$3.37 US['41027. Non-Active Use Rates Hourly Standby Rate USD$3.45 Idling Rate USD$6.90 Rate Element Allocation Element Percentage Value Depreciation(ownership) 20.64% USD$227.05/mo Overhaul(ownership) 66.67% USD$733.38/mo CFC(ownership) 5.62% USD$61.78/mo Indirect(ownership) 7.07% USD$77.79/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 65 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-1391thumb in All Saved Models January 5, 2026 Miscellaneous 28HTWL Hydraulic Bucket Thumbs Size Class: All Weight: 1011 NIA Configuration for 28HTWL Power Mode Hydraulic Recommended Machine Weight 24.1-28.0 mt Type Wide Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$1,385.00 USD$390.00 USD$98.00 USD$15.00 USD$2.62 USD$10.49 Adjustments Region USD$148.20 USD$41.73 USD$10.49 USD$1.61 (Washington:110.7%) Model Year(2024:99.97%) (USD$0.45) (USD$0.13) (USD$0.03) (USD$0.00) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,532.75 USD$431.60 USD$108.45 USD$16.60 USD$2.62 USD$11.33 Non-Active Use Rates Hourly Standby Rate USD$4.35 Idling Rate USD$8.71 Rate Element Allocation Element Percentage Value Depreciation(ownership) 18.99% USD$262.99/mo Overhaul(ownership) 68.73% USD$951.86/mo CFC(ownership) 5.44% USD$75.33/mo Indirect(ownership) 6.85% USD$94.82/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 66 EquipmentWatch.. Combined hourly rate with attachments=$241.43 www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-142 in All Saved Models January 5, 2026 Komatsu PC490LC-11 Crawler Mounted Hydraulic Excavators -- to. "__NMI' Size Class: 40.5-50.4mt Weight: NIA Configuration for PC49OLC-11 Horsepower 359 hp Power Mode Diesel Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$22,195.00 USD$6,215.00 USD$1,555.00 USD$235.00 USD$68.89 USD$195.00 Adjustments Region(Washington:106%) USD$1,331.70 USD$372.90 USD$93.30 USD$14.10 Model Year(2024:99.98%) (USD$3.78) (USD$1.06) (USD$0.26) (USD$0.04) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$23,522.92 USD$6,586.84 USD$1,648.04 USD$249.06 USD$68.89 USD$202.54 Non-Active Use Rates Hourly Standby Rate USD$66.83 Idling Rate USD$159.78 Rate Element Allocation Element Percentage Value Depreciation(ownership) 31.78% USD$7,053.18/mo Overhaul(ownership) 44.15% USD$9,799.05/mo CFC(ownership) 15.44% USD$3,427.27/mo Indirect(ownership) 8.63% USD$1,915.50/mo Fuel(operating)@ USD 3.83 37.93% USD$26.13/hr Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book@ Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 67 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-14211 in All Saved Models January 5, 2026 Miscellaneous HD 3.00 Heavy Duty Excavator Buckets Size Class: All Weight: 1011 4942 lbs Configuration for HD 3.00 Rated Capacity 3.0 cu yd Width 45-55 in Power Mode Manual Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$1,140.00 USD$320.00 USD$80.00 USD$12.00 USD$3.44 USD$9.92 Adjustments Region USD$119.70 USD$33.60 USD$8.40 USD$1.26 (Washington:110.5%) Model Year(2024:99.97%) (USD$0.37) (USD$0.10) (USD$0.03) (USD$0.00) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,259.33 USD$353.50 USD$88.37 USD$13.26 USD$3.44 1-13030:60 Non-Active Use Rates Hourly Standby Rate USD$3.58 Idling Rate USD$7.16 Rate Element Allocation Element Percentage Value Depreciation(ownership) 20.64% USD$235.31/mo Overhaul(ownership) 66.67% USD$760.05/mo CFC(ownership) 5.62% USD$64.02/mo Indirect(ownership) 7.07% USD$80.62/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 68 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-14212 in All Saved Models January 5, 2026 Miscellaneous HD4.50 Heavy Duty Excavator Buckets Size Class: All Weight: 1011 7944 lbs Configuration for HD4.5O Rated Capacity 4.5 cu yd Width 65.0 in Power Mode Manual Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$1,565.00 USD$440.00 USD$110.00 USD$17.00 USD$4.03 USD$12.92 Adjustments Region USD$164.32 USD$46.20 USD$11.55 USD$1.78 (Washington:110.5%) Model Year(2024:99.97%) (USD$0.50) (USD$0.14) (USD$0.04) (USD$0.01) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,728.82 USD$486.06 USD$121.51 USD$18.78 USD$4.03 USD$13.85 Non-Active Use Rates Hourly Standby Rate USD$4.91 Idling Rate USD$9.82 Rate Element Allocation Element Percentage Value Depreciation(ownership) 20.64% USD$323.03/mo Overhaul(ownership) 66.67% USD$1,043.40/mo CFC(ownership) 5.62% USD$87.89/mo Indirect(ownership) 7.07% USD$110.67/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 69 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '06-142ITHUMB in All Saved Models January 5, 2026 Miscellaneous 66HTWL Hydraulic Bucket Thumbs Size Class: All Weight: 1011 NIA Configuration for 66HTWL Power Mode Hydraulic Recommended Machine Weight 50.1-66.0 mt Type Wide Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$1,800.00 USD$505.00 USD$125.00 USD$19.00 USD$3.12 USD$13.35 Adjustments Region USD$192.60 USD$54.03 USD$13.38 USD$2.03 (Washington:110.7%) Model Year(2024:99.97%) (USD$0.58) (USD$0.16) (USD$0.04) (USD$0.01) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$1,992.02 USD$558.87 USD$138.33 USD$21.03 USD$3.12 USD$14.44 Non-Active Use Rates Hourly Standby Rate USD$5.66 Idling Rate USD$11.32 Rate Element Allocation Element Percentage Value Depreciation(ownership) 18.99% USD$341.79/mo Overhaul(ownership) 68.73% USD$1,237.08/mo CFC(ownership) 5.44% USD$97.90/mo Indirect(ownership) 6.85% USD$123.23/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 70 EquipmentWatch.. Combined hourly rate with attachments=$84.30 www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '07-39 in All Saved Models January 5, 2026 Caterpillar 938K(disc.2015) 4-Wd Articulated Wheel Loaders Size Class: 150-174hp Weight: 35104Ibs Configuration for 938K(disc.2015) Horsepower 173.0 hp Operator Protection ROPSIFOPS Power Mode Diesel Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$7,405.00 USD$2,075.00 USD$520.00 USD$78.00 USD$34.52 USD$76.59 Adjustments Region USD$333.23 USD$93.38 USD$23.40 USD$3.51 (Washington:104.5%) Model Year(2015:100%) - - - - AdjustedHourlyOwnership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$7,738.23 USD$2,168.38 USD$543.40 USD$81.51 USD$34.52 USD$78.49 Non-Active Use Rates Hourly Standby Rate USD$21.98 Idling Rate USD$53.46 Rate Element Allocation Element Percentage Value Depreciation(ownership) 39.72% USD$2,941.55/mo Overhaul(ownership) 34.61% USD$2,562.82/mo CFC(ownership) 16.96% USD$1,255.70/mo Indirect(ownership) 8.71% USD$644.94/mo Fuel(operating)@ USD 3.83 27.49% USD$9.49/hr Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book@ Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 71 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '07-39IForks in All Saved Models January 5, 2026 Miscellaneous MPB-3.0+ Wheel Loader Multi-Purpose Buckets Size Class: All Weight: NIA Configuration for MPB-3.0+ Capacity 3&Over Power Mode Hydraulic Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$595.00 USD$165.00 USD$41.00 USD$6.00 USD$2.43 USD$5.81 Adjustments Region USD$4.76 USD$1.32 USD$0.33 USD$0.05 (Washington:100.8%) Model Year(2017:99.24%) (USD$4.56) (USD$1.26) (USD$0.31) (USD$0.05) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$595.20 USD$165.06 USD$41.01 USD$6.00 USD$2.43 USD$5.81 Non-Active Use Rates Hourly Standby Rate USD$1.69 Idling Rate USD$3.38 Rate Element Allocation Element Percentage Value Depreciation(ownership) 46.57% USD$277.12/mo Overhaul(ownership) 22.57% USD$134.29/mo CFC(ownership) 13.33% USD$79.31/mo Indirect(ownership) 17.53% USD$104.28/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 72 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '08-179 in All Saved Models January 5, 2026 Miscellaneous 4X2 30KGVW DSL On-Highway Flatbed Trucks Size Class: 26,001-33,000 lbs Weight: 1011 8994 lbs Configuration for 4X2 3OKGVW DSL Axle Configuration 4X2 Horsepower 217.0 hp Maximum Gross Vehicle Weight 30000.0 lbs Power Mode Diesel Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$2,800.00 USD$785.00 USD$195.00 USD$29.00 USD$35.15 USD$51.06 Adjustments Region USD$170.80 USD$47.88 USD$11.90 USD$1.77 (Washington:106.1%) Model Year(2023:99.94%) (USD$1.65) (USD$0.46) (USD$0.11) (USD$0.02) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$2,969.15 USD$832.42 USD$206.78 USD$30.75 USD$35.15 USD$52.02 Non-Active Use Rates Hourly Standby Rate USD$8.44 Idling Rate USD$42.14 Rate Element Allocation Element Percentage Value Depreciation(ownership) 24.44% USD$684.42/mo Overhaul(ownership) 56.81% USD$1,590.77/mo CFC(ownership) 8.54% USD$239.10/mo Indirect(ownership) 10.2% USD$285.71/mo Fuel(operating)@ USD 3.83 71.89% USD$25.27/hr Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 73 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '15-11 in All Saved Models January 5, 2026 Volvo A35D(disc.2008) Articulated Rear Dumps �— Size Class: •` `: ). 34.5 mt&Over Weight: 62390 lbs Configuration for A35D(disc.2008) Axle Configuration 6 X 6 Horsepower 382.0 hp Power Mode Diesel Rated Payload 36.0 mt Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$17,840.00 USD$4,995.00 USD$1,250.00 USD$190.00 USD$84.59 USD$185.95 Adjustments Region USD$1,320.16 USD$369.63 USD$92.50 USD$14.06 (Washington:107.4%) Model Year(2006:99.91%) (USD$17.45) (USD$4.88) (USD$1.22) (USD$0.19) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$19,142.71 USD$5,359.75 USD$1,341.28 USD$203.87 USD$84.59 USD$193.36 Non-Active Use Rates Hourly Standby Rate USD$54.38 Idling Rate USD$134.85 Rate Element Allocation Element Percentage Value Depreciation(ownership) 31.02% USD$5,534.62/mo Overhaul(ownership) 47.94% USD$8,553.07/mo CFC(ownership) 12.22% USD$2,179.78/mo Indirect(ownership) 8.81% USD$1,572.53/mo Fuel(operating)@ USD 3.83 30.83% USD$26.08/hr Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 74 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for 51-06 in All Saved Models January 5, 2026 Kent KHB5OG II(disc.1999) Hydraulic Impact Breakers Size Class: 10,000-11,999 ft-lb Weight: 1011 8660 lbs Configuration for KHB5OG II(disc.1999) Impact Energy 10000.0 ft-lb Power Mode Hydraulic Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$12,770.00 USD$3,575.00 USD$895.00 USD$135.00 USD$21.48 USD$94.04 Adjustments Region USD$1,110.99 USD$311.02 USD$77.86 USD$11.74 (Washington:108.7%) Model Year(1998:100%) - - - - AdjustedHourlyOwnership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$13,880.99 USD$3,886.02 USD$972.86 USD$146.74 USD$21.48 USD$100.35 Non-Active Use Rates Hourly Standby Rate USD$44.46 Idling Rate USD$78.87 Rate Element Allocation Element Percentage Value Depreciation(ownership) 34.07% USD$4,350.48/mo Overhaul(ownership) 43.63% USD$5,571.78/mo CFC(ownership) 11.85% USD$1,513.27/mo Indirect(ownership) 10.45% USD$1,334.47/mo Fuel cost data is not available for these rates. Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 75 EquipmentWatch.. www.equipmentwatch.com All prices shown in US dollars($) Adjustments for '62-08 in All Saved Models January 5, 2026 Miscellaneous 6 DIESEL Self Priming Trash Pumps Size Class: 5 in&Over Weight: 1011 2200 lbs Configuration for 6 DIESEL Power Mode Diesel Horsepower 70.0 hp Pump Capacity 80000.0 gal/hr Pump Size 6.0 in Blue Book Rates **FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Ownership Costs Estimated Operating FHWA Rate** Costs Monthly Weekly Daily Hourly Hourly Hourly Published Rates USD$3,920.00 USD$1,100.00 USD$275.00 USD$41.00 USD$31.11 USD$53.38 Adjustments Region USD$270.48 USD$75.90 USD$18.98 USD$2.83 (Washington:106.9%) Model Year(2011:92.6%) (USD$310.08) (USD$87.01) (USD$21.75) (USD$3.24) Adjusted Hourly Ownership - - - - Cost(100%) Hourly Operating Cost(100%) - Total: USD$3,880.40 USD$1,088.89 USD$272.22 USD$40.59 USD$31.11 USD$53.16 Non-Active Use Rates Hourly Standby Rate USD$11.02 Idling Rate USD$40.82 Rate Element Allocation Element Percentage Value Depreciation(ownership) 28.95% USD$1,134.75/mo Overhaul(ownership) 49.73% USD$1,949.42/mo CFC(ownership) 10.6% USD$415.46/mo Indirect(ownership) 10.72% USD$420.36/mo Fuel(operating)@ USD 3.83 60.33% USD$18.77/hr Revised Date:1st quarter 2026 These are the most accurate rates for the selected Revision Date(s).However,due to more frequent online updates,these rates may not match Rental Rate Blue Book® Print.Visit the Cost Recovery Product Guide on our Help page for more information. The equipment represented in this report has been exclusively prepared for(rory@interwest.biz) All material herein©2003-2026 Randall-Reilly All rights reserved. Page 1 of 1 76 Change Proposal Request No. 008 Project Name: Nelson Dam Removal PH 2 Owner's Project No. (if applicable): IC2010 Project Owner: City of Yakima Regulatory Agency Project No.(if applicable):N/A HDR Project No. 10415845 Initiated by: ® Engineer ❑ Contractor Contractor: Interwest Construction, Inc. Date:01/13/2026 Attention: The following change in the contract on this project is proposed. Please provide your proposed price for the cost of this change. • A full breakdown of labor, equipment, and material costs shall be provided. • Work shall not commence until authorized by the Owner. Description of the Proposed Change: Provide cost proposal for 42-inch pipeline realignment adjacent through West Powerhouse Road in lieu of the alignment shown in the contract documents. See attached plan and profile sheets. By Troy Gibbs, PE All work shall be in accordance with the terms,stipulations,and HDR Recommendation: conditions of the original Contract Documents. If the work herein ❑ Recommend Acceptance provided for is Approved by Change Order,the time of completion will be: ElDo Not Recommend Acceptance ❑ Increased ❑ Decreased ❑ Unchanged By: HDR Engineering, Inc. by calendar days. Date This change will: ❑ Add ❑ Deduct ❑ No Change Owner's Action: $ ❑ Accepted ❑ Not Accepted By: Owner Date Copyright 2015 HDR Engineering,Inc. 77 co N. 1 I 2 I 3 I 4 I 5 I 6 I 7 I 8 \ NOTES: _ / ''. a----,-,,,, 1. THE RETAINING WALL BOTTOM ELEVATION SHOWN ON -'-'-\ 11R PROFILE IS APPROXIMATE FOR LOCATION OF NACHES EXISTING 32" - \ START SLIPLINE OF NEW 32"- GENERAL US 12 WESTBOUND ROAD CROSSING. CONTRACTOR TO VERIFY BOTTOM OF GENERAL PIPELINE PIPELINE WITHIN EXISTING 36" GENERAL """" WALL ELEVATION AT CROSSING LOCATION IN THE FIELD. PIPELINE, SEE DETAIL 1 ON SHEET 02C17. �' __ TIE IN POINT N473311.15 , E1618726.91, LE PROVIDE 4' OF CLEARANCE BETWEEN BOTTOM OF WALL FIELD VERIFY SLIPLINED 32"-GENERAL PIPELINE AND TOP OF STEEL CASING. SEE WEST POWERHOUSE • �•.�`�,_ WITHIN 36" EXISTING GENERAL PIPELINE ROAD BRIDGE NO 786 AS-BUILTS. / ,• � - __NIM �•�. ,o �� EXISTING NACHES / �, /7--- _ COWICHE PIPELINE US 12 EASTBOUND�,, 2. INSTALL CARV PER DETAIL 1/02C20 FOR THE 42" i ; II :\ STA 1+92, ACCESS EXISTING NACHES ALIGNMENT A.1 STA 4+25 = 91�; - - FRUITVALE/OLD UNION PIPELINE. j I�' �• � VAULT, SEE NOTE 3 COWICHE PIPELINE ALIGNMENT A STA 4+25 ���^�. �.,_,,� �,#� p/ \ ���O o •. o • o 3. INSTALL ACCESS VAULT PER DETAIL 2/02C17. D *1;00,/).* # �:• a Ifs s !, R - _ _ _ = I , - _ ERR= �F2e- - I u X-` :IZ&_= IK �T cuLv AND IS •� v -CULV - cULV I Vim C � O ,0 #\*** •*% x00 .. ----------- CU\-°1 SAUCY- - - `� 4. SHAFT LOCATION AND SIZE IS APPROXIMATE _ii 0 SHOWN FOR REFERENCE PURPOSES ONLY. L� �� ,,._ �© CO 6+00 7+0'L100 ------_7„,z, �� PPL 094501 /C/7 CONTRACTOR TO LOCATE SHAFT PROVIDING A MINIMUM ��i�i t - \ 0 �' _ ID__ a 100 '-= 8+00 p Z HORIZONTAL CLEARANCE OF 5 FT CLEARANCE FROM ---G\---\--, ''►/�4. ✓/kph •/ / 7- 4.-CUL o UP Cildt �` ' BHP �a� L101 9+00 7 0 �.. i /-- t° RETAINING WALL. 0 `�j EXISTING 42"-NACHES °° �` ® - Uw / / O 5+00 --"' f OHP 7+00� 8+00 W POWERHOUSE / 41 5. SHAFT LOCATION AND SIZE IS APPROXIMATE AND IS �� COWICHE PIPELINE ■n ,00 f 6+00 _ ROgp �O ® / r 4+00 C100 _ �r - .� F- ---�� -f 9+00. 1plir SHOWN FOR REFERENCE PURPOSES ONLY ° „sa 2+00 3+00 - / - s-- - ""' -� CONTRACTOR TO LOCATE SHAFT, PROVIDING AN \p• - - _ - U MINIMUM OF 5 FT CLEARANCE FROM TOE OF SLOPE FOR • /` N 473291.42, E 1618645.07 ==��M - -�-- Q � '�-� Q N NACHES ROAD. ® 0 TOP EL 1165.6, FIELD VERIFY J -- --J r / �/ r� / �� - �� \ ((/ . / / 0 'p STA 4+70 CARV ��~ `Iill ? LU 6. CONTRACTOR SHALL PROTECT ALL EXISTING " ��DHP -®- STATION, ' -�- -n ��� '"°�- ��_ ® STRUCTURES, ROADWAYS, AND UTILITIES. IF DAMAGED • HP SEE NOTE 2 �� THEY SHALL BE REPAIRED TO THE OWNERS APPROXIMATE LAUNCH00. P,- O2 PPL 093605 ® Q W SATISFACTION AND TO MEET APPLICABLE WSDOT, AND SHAFT LOCATION, SEE NOTE 4 �7 �' -�� 42"-FRUITVALE/ W 8 t; �-"�- C� CITY AND COUNTY OF YAKIMA STANDARDS. „:„ S ��-- ALIGNMENT A.1 OLD UNION PIPELINE FO-9001 S NACHES ROAD START 42"-FRUITVALE/ APPROXIMATE ----/,,--___ �'" ALIGNMENT A (NOT USED THIS SHEET) ems. - ---� 7. CONTRACTOR SHALL USE TRENCH BOXES WHERE OLD UNION PIPELINE RETRIEVAL SHAFT - / NEEDED TO PROTECT EXISTING STRUCTURES, F0-9001 LOCATION, SEE NOTE 5 - - I ROADWAYS, STORM DRAINS, AND UTILITIES. 1185 1190- `` �' 8. ANY ROADWAY SIGNS IMPACTED BY CONSTRUCTION _ PPL 093604 -�"' A SHALL BE SALVAGED AND REINSTALLED PER COUNTY s �`-- '-�`�-' `--�• _--_'-- , -.�- `. �"•. STANDARDS. C A N � - - �°- 9. ANY ROADWAY STRIPING OR MARKINGS DAMAGED BY PIPELINES - ALIGNMEN A. 1 STA 0+00 TO STA 10+00 ri". CONSTRUCTION SHALL BE REPAIRED PER COUNTY SCALE: 1" = 40' It 02C01 02CO2 3 STANDARDS TO MATCH THE EXISTING INSTALLATION. 10. CONTRACTOR MAY PROPOSE ALTERNATIVE ALIGNMENTS TO LIMIT FITTINGS, IMPACTS TO EXISTING SEE FEATURES, OR TO REDUCE ROCK EXCAVATION TYPICAL 11. CONTRACTOR RESPONSIBLE FOR ROCK EXCAVATION TRENCH A BELOW LIMITS SHOWN ON PROFILE AS PART OF LUMP SECTION SUM INSTALLATION COST. A/02C18 1190 O - 1190 4 I SEE TYPICAL TR CH SECTION A/02C18 I - SEE TYPICAL TRENCH SECTION F/02C18 KEYED NOTES: I 37'-6" - - --r _ 1. CONTRACTOR TO REPAIR AND/OR REPLACE STORM \ EXISTING - EXISTING - DRAIN SIMILAR TO EXISTING, TO SATISFACTION OF GRADE \ GRADE - COUNTY ENGINEER. 1180 / / 1180 2. EXISTING POWER POLE, PROTECT IN PLACE. _ COORDINATE WITH UTILITY TO PROVIDE STABILIZATION RETAINING WALL, \ TO THE EXISTING POLE DURING CONSTRUCTION. - SEE NOTE 1 -- / _ - s - - STA 4+70 CARV _ 3. COORDINATE INSTALLATION OF PIPELINES WITH STATION, EXISTING UNDERGROUND POWER. FOR STREET EXISTING 36"-NACHES SEE NOTE 2 3 COWICHE PIPELINE EXISTIN STORM DRAIN ANTICIPATED ROCK - LIGHTING POWER, PROVIDE TEMPORARY WIRING TO APPROX 1176.70 O EXCAVATION LIMIT KEEP LIGHTING OPERATIONAL, THEN REINSTALL 1170 © 1 - 1170 PERMANENT UNDERGROUND POWER FOLLOWING I_ INSTALLATION OF PIPELINES. UNDERGROUND POWER B I I II III �. o �- �. V 7 - - � - _ INSTALLATION SHALL COMPLY WITH NEC I- - r I SL=-0.00% -�' o - -0. •% RRREQUIREMENTS, AND BE A MINIMUM OF 24" BELOW 4. TRENCHLESS TECHNOLOGY IS NEEDED FOR THE !t / ___________ I I ] _ -� SEGMENT OF THE PIPELINE THAT IS CROSSING NACHES 1160 - - 1160 ROAD. SEE SPECIFICATION SECTION 33 05 23.16 42"-FRUITVALE/ w _ TRENCHLESS CONSTRUCTION. EXISTING W OLD UNION PIPELINE z 32"-GENERAL PIPELINE j F0-9001 w - - ' - Ls, o _ w w 5. 54" STEEL CASING. SEE SPECIFICATION SECTION 33 05 cc) �? - w r z 23.20 STEEL CASING PIPE. A - z z w _ _ - H 0_ - L w_ 6. CONTRACTOR SHALL REPAIR CURB AND GUTTER AS J 1150 w w w c� z D ri 1150 REQUIRED ' - `A' v ' •u '1 0 '', ' ' 1 -1 J w LL! > w - 0 - •z •- - NT CONCRETE CURBS AND WSDOT STANDARD Q z z N i - 0 J .- O > J J u) 0 - J O - z /� PLAN F.10.16-00 FOR CEMENT CONCRETE CURB AND _ O /3\ GUTTER. A w w z _ 5d LLJd QUW _ W J - 0 11 (7- J d U W Q Q J "'c\i N ur O `f'• > z U) < U) - N > o I- N - 7. REPAIR APPROXIMATEL 450 NEAR FEET OF L z CO 5 z - - 5 + ct N - J PAVEMENT PER PAVEME� 'ECIFICATIONS AND r EL D - N LL ( w > YAKIMA COUNTY STANDARD PLAN RR-1A. SHOULD HMA 1140 < < 0 < .c`i 0 N i- N w - - = cp , 1140 NOT BE SEASONABLY AVAILABLE AT THE TIME OF O co O co w - o ct c) Q REPAIR, CONTRACTOR SHALL PROVIDE TEMPORARY - ,- COLD PATCH AND MAINTAIN TEMPORARY TRAVEL I (0 iN w SURFACE UNTIL HMA IS AVAILABLE AND FINAL SURFACING CAN BE COMPLETED. - 8. REPLACE ROAD DELINEATORS AHEAD OF SHOULDER A 1130 - 1130 EXPANSION SIMILAR TO EXISTING. 0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 10+00 9. FLANGED CONNECTION TO EXISTING HDPE PIPE. FIELD VERIFY EXISTING PIPE LOCATION AND ADJUST ALIGNMENT IF REQUIRED. A 2A PIPELINES - ALIGNMENT A. 1 STA 0+00 TO STA 10+00 SCALE: 1" = 40' HORIZ, 1" = 8' VERT PROJECT MANAGER MICHAEL GARELLO, PE DESIGNED BY M. GARELLO NELSON DAM REMOVAL PROJECT: CIVIL DESIGNED BY WATER SUPPLY, FISH PASSAGE, AND c CHECKED BY J. CHANDLER y .`.l,'" r=.> ', RIVERINE PROCESS IMPROVEMENTS PIPELINES - ALIGNMENT A.1 `�W„, IM)/ DRAWN BY N. SZIGETI : % '�. STA 0+00 TO STA 10+00 PLAN AND PROFILE C 9/23/2025 ACKLEY ROAD REALIGNMENT '-" ` ' -,,uk • ��. � PHASE II - CONVEYANCE B 9/18/2024 CONFORMED FOR CONSTRUCTION •. Know what's below. 3 9/6/2024 ADDENDUM NO. 3 ',,,',;a.•••.•••• w- ,= SHEET A 8/14/2024 ISSUED FOR BID ,,„";,,,,_, IMPROVEMENTS 0 �" 2„ FILENAME 02CO2.dwg Call before you dig. CITY OF YAKIMA, WASHINGTON SCALE - 02CO2 ISSUE DATE DESCRIPTION PROJECT NUMBER 10173276 ti 1 I 2 I 3 I 4 I 5 I 6 I 7 I 8 NOTES: T 1. PER DETAIL 1/02C20, INSTALL A 4" CARV FOR THE 42"-FRUITVALE/OLD UNION PIPELINE AND A 3" CARV FOR U 12 ES BOUND 9- ACV THE 32" GENERAL PIPELINE. - — SLIPLINED 32"-GENERAL PIPELINE EXISTING 24" - - WITHIN 36" EXISTING GENERAL PIPELINE - �-- I rn 2. INSTALL ACCESS VAULTS, SEE DETAIL 2/02C17. STATION ABANDONED ALIGNMENT A.1 STA 19+44 = r- NUMBER PROVIDED IN PROFILE IS FOR THE I :ITER" I - ALIGNMENT A STA 18+55 Q 42"-FRUITVALE/OLD UNION PIPELINE ACCESS VAULT. (n SEE PLAN FOR VAULT LOCATIONS FOR THE r- 32"-GENERAL PIPE AS THE TWO VAULTS ARE EXISTING NACHES US 12 EASTBOUND Z STAGGERED. OZ COWICHE PIPELINE — 0 — — O INSTALL 22.55° BEND 1. 11-,' _O O ! 1 W I— 3. CONTRACTOR SHALL PROTECT ALL EXISTING __ ,� - - - 8756) I W < STRUCTURES, ROADWAYS, AND UTILITIES. IF DAMAGED D cr~ _Z ~_ R _� / I Z z THEY SHALL BE REPAIRED TO THE OWNERS /�/ `CAL = `_�R �= ° I UP ._� _ (D 1- SATISFACTION AND TO MEET APPLICABLE WSDOT, AND Z � — — _ _ P �:�Q I I -J Z CITY AND COUNTY OF YAKIMA STANDARDS. ce 0/ � _ / QO !� U ``` - \ ^* =13+00 14+00 15+00 �^ uj 0 4. CONTRACTOR SHALL USE TRENCH BOXES WHERE Z r PPL 094502 W O \ \ - \ ACCESSVAULTS - 16+005cr / A♦ p (n, \LWSDOTROW \\\\ v LV // / / \ Q O STANDARDS. W 1p r STA 17+00 Z .� 2 \ SEE NOTE 2 \, H H j a/ _.. �� ... -o O W W 6. ANY ROADWAY STRIPING OR MARKINGS DAMAGED BY =j co 1UxU `i + ALIGNMENT A 1�� / W = CONSTRUCTION SHALL BE REPAIRED PER WSDOT �. Cl) STANDARDS TO MATCH THE EXISTING INSTALLATION. Q W �\ ��� Op y (NOT USED THIS SHEET) �� W W I o�„`' �p W 3 7. CONTRACTOR MAY PROPOSE ALTERNATIVE �i 1 42"-FRUITVALE/ - '� \ \ / ALIGNMENT A.1 '/' �a (n ALIGNMENTS TO LIMIT FITTINGS, IMPACTS TO EXISTING \0 OLD UNION PIPELINE F0-9001 I I ,; �/ W FEATURES, OR TO REDUCE ROCK EXCAVATION ---------------- 1 Z L,_,_.._ �`' �7p3 • ,�-��\ C d -0 8. CONTRACTOR RESPONSIBLE FOR ROCK EXCAVATION xoo BELOW LIMITS SHOWN ON PROFILE AS PART OF LUMP y U \ n ,�p`L la C SUM INSTALLATION COST. 12 INSTALL e---~. \ a 45° BEND �� /43 � KEY NOTES: \ \ / �N� �O 1. ABANDONED 24"WOOD STAVE WATER MAIN. 2 ,3X \ Q Q / A C __., ._,,,,, . y_ p0 n Q ° 2. REPAIR APPROXIMATELY 600 LINEAR FEET OF • o O / INSTALL 22.55 BEND, PAVEMENT IN W POWERHOUSE ROAD AND AC E / -� ALIGNMENT A.1 \ © / 047 END PHASE 2A, C ROAD I I• A \\\ V:77,///' W i BEGIN PHASE 2B TY STANDARD PLAN RR 1A. SHOULD HMA NOT BE I J` 7p4 \ fl D U SEASONABLY AVAILABLE AT THE TIME OF REPAIR, �� n Q oo / CONTRACTOR SHALL PROVIDE TEMPORARY COLD _ti- 7X ° © ,\gk 0 / PATCH AND MAINTAIN TEMPORARY TRAVEL SURFACE / ,-_____ - _ _ p0 INSTALL 45 BENDI - UNTIL HMA IS AVAILABLE AND FINAL SURFACING CAN BE COMPLETED. � .,,, ,,..: INSTALL . / PERMgNENTIMATE 30 3. NOT USED �. �5koo I�r EgSEM ( 4ENT PIPELINES ALIGNMENT A. 1 STA 10+00 TO STA 19+42 ri--.) SCALE: 1" = 40' 02C01 02CO3 (eY 4. REMOVE AND REPLACE BARBED WIRE FENCING AS REQUIRED PER WSDOT STANDARD. A5. REPLACE ALL DISTURBED ROAD SIGNS AND DELINEATORS PER COUNTY STANDARD DETAILS. A1 1 1 1 1 1 1 1 1 1 1 1 1 1 1190 6. PROTECT EXISTING LIGHT POLE IN PLACE. SEE TYPICAL TRENCH SECTION F/02C18 I 7. CONTRACTOR TO REPAIR AND/OR REPLACE STORM DRAIN AND INLET SIMILAR TO EXISTING. CONTRACTOR B NACHES COWICHE CANAL, - TO FIELD VERIFY SIZE. SEE SECTION A/02C17 _ C FOR PROPOSED GRADE -. - PHASING NOTE: 1180 - ACKLEY ROAD 1180 1. PIPELINE INSTALLATION FROM ALIGNMENT A.1 STA [ GRADE PHASE 2B I PHASE 2A- EXISTING _ 10+00 TO STA 16+85 TO BE PERFORMED AS PART OF - — PHASE 2B. ---- - -- - , —1 \ ANTICIPATED ROCK \ - EXCAVATION LIMIT _\ -� 1170 1170 SL=0.26% _ - SL=0.26% _ 1160 _^ — j 1160 I - - 42"-FRUITVALE/ - / _ OLD UNION PIPELINE -1 _ co w - FO-9001 - 0 z p — 0 z _. J W Z W - 0 W c\1 CO _ 1150 2A _1y "? w — c\'. w w m 1150 A oW co - + � Za � w � 10 !: cow � �-, `1-'s .- O rU_�n + W I- N „, .- 0 (n40w 1 — — - - i- N - 2B - - 1 u) N - 1140 1140 10+00 11+00 12+00 13+00 14+00 15+00 16+00 17+00 18+00 19+00 19+44 PIPELINES - ALIGNMENT A. 1 STA 10+00 TO STA 19+42 SCALE: 1" = 40' HORIZ, 1" = 8'VERT PROJECT MANAGER MICHAEL GARELLO, PE DESIGNED BY M. GARELLO NELSON DAM REMOVAL PROJECT: CIVIL A DESIGNED BY WATER SUPPLY, FISH PASSAGE, AND CHECKED BY R. ROBERTS `'�iiiiiiiiiLi-N. RIVERINE PROCESS IMPROVEMENTSPIPELINES - ALIGNMENT A.1 _II .. .i., 110, ._ F)1 DRAWN BY N. SZIGETI `_`` ''" STA 10+00 TO STA 19+44 PLAN AND PROFILE C 9/23/2025 ACKLEY ROAD REALIGNMENT %; ';l �,:> PHASE I I - CONVEYANCE B 9/18/2024 CONFORMED FOR CONSTRUCTION , •. Know what's below. 3 9/6/2024 ADDENDUM NO. 3 ��,` ,,""" `" -'y IMPROVEMENTS 0 _ _1" 2" FILENAME 02CO3.dwg SHEET Call before you dig. A 8/14/2024 ISSUED FOR BID SCALE - 02CO3 ISSUE DATE DESCRIPTION PROJECT NUMBER 10173276 CITY OF YAKIMA, WASHINGTON O co 1 I 2 I 3 I 4 I 5 I 6 I 7 I 8 ALIGNMENT LINE TABLE ALIGNMENT LINE TABLE ALIGNMENT CURVE TABLE LINE NO. LENGTH DIRECTION START POINT (N,E) END POINT (N,E) ALIGNMENT NAME LINE NO. LENGTH DIRECTION START POINT (N,E) END POINT (N,E) ALIGNMENT NAME CURVE NO. PI STATION A RADIUS TANGENT LENGTH CHORD DIRECTION CHORD LENGTH ALIGNMENT NAME L1 181.24' 557°48'46"E 473284.5509, 1618645.7370 473188.0062, 1618799.1238 42-FRUITVALE_OLD UNION PIPELINE L36 665.71' 556°16'37"E 473305.5060, 1618737.0800 472935.9179, 1619290.7720 32-GENERAL PIPELINE C1 5+45.07 178°47'04" 150.00' 1.59' 3.18 558°25'14.25"E 3.18' 42-FRUITVALE_OLD UNION PIPELINE L2 179.65' 557°48'46"E 473188.0062, 1618799.1238 473092.3090, 1618951.1640 42-FRUITVALE_OLD UNION PIPELINE L37 58.78' 559°35'55"E 472935.9179, 1619290.7720 472906.1706, 1619341.4720 32-GENERAL PIPELINE C2 6+91.18 175°27'42" 150.00' 5.94' 11.88 556°45'33.35"E 11.88' 42-FRUITVALE_OLD UNION PIPELINE L3 138.57' 559°01'42"E 473090.6425, 1618953.8750 473019.3333, 1619072.6867 42-FRUITVALE_OLD UNION PIPELINE L38 83.84' 556°37'25"E 472906.1706, 1619341.4720 472860.0488, 1619411.4820 32-GENERAL PIPELINE C3 9+05.30 172°10'34" 150.00' 10.26' 20.48 547°09'40.37"E 20.47' 42-FRUITVALE_OLD UNION PIPELINE L4 69.87' 554°29'24"E 473012.8223, 1619082.6212 472972.2405, 1619139.4940 42-FRUITVALE_OLD UNION PIPELINE L39 98.04' 557°28'56"E 472860.0488, 1619411.4820 472807.3486, 1619494.1480 32-GENERAL PIPELINE C4 13+25.35 174°40'46" 150.00' 6.97' 13.93 562°35'20.23"E 13.92' 42-FRUITVALE_OLD UNION PIPELINE L5 8.94' 571°16'22"E 472972.2405, 1619139.4940 472969.3699, 1619147.9618 42-FRUITVALE_OLD UNION PIPELINE L40 70.96' 557°52'45"E 472807.3486, 1619494.1480 472769.6197, 1619554.2444 32-GENERAL PIPELINE C5 16+43.20 175°34'33" 150.00' 5.79' 11.58 562°08'26.41"E 11.58' 42-FRUITVALE_OLD UNION PIPELINE L6 119.12' 551°04'23"E 472969.3699, 1619147.9618 472894.5208, 1619240.6344 42-FRUITVALE_OLD UNION PIPELINE L41 70.96' 557°52'45"E 472769.6197, 1619554.2444 472731.8907, 1619614.3407 32-GENERAL PIPELINE C6 16+90.77 176°53'24" 150.00' 4.07' 8.14 562°47'51.90"E 8.14' 42-FRUITVALE_OLD UNION PIPELINE L7 163.93' 543°14'57"E 472880.6045, 1619255.6423 472761.1985, 1619367.9653 42-FRUITVALE_OLD UNION PIPELINE L42 306.16' 559°55'43"E 472731.8907, 1619614.3407 472578.4825, 1619879.2891 32-GENERAL PIPELINE C7 17+31.98 178°47'02" 150.00' 1.59' 3.18 560°38'04.94"E 3.18' 42-FRUITVALE_OLD UNION PIPELINE L8 184.16' S88°14'57"E 472761.1985, 1619367.9653 472755.5722, 1619552.0387 42-FRUITVALE_OLD UNION PIPELINE L43 49.72' S63°40'30"E 472575.2388, 1619885.3389 472553.1916, 1619929.8994 32-GENERAL PIPELINE C8 18+80.22 178°12'32" 150.00' 2.34' 4.69 559°05'58.90"E 4.69' 42-FRUITVALE_OLD UNION PIPELINE L9 54.76' 565°14'57"E 472755.5722, 1619552.0387 472732.6451, 1619601.7695 42-FRUITVALE_OLD UNION PIPELINE L44 60.83' S60°49'53"E 472550.7655, 1619934.5113 472521.1180, 1619987.6273 32-GENERAL PIPELINE C9 27+80.58 176°47'37" 150.00' 4.20' 8.39 558°04'03.29"E 8.39' 42-FRUITVALE_OLD UNION PIPELINE L10 305.09' 559°55'43"E 472726.2348, 1619614.1305 472573.3610, 1619878.1558 42-FRUITVALE_OLD UNION PIPELINE L45 70.68' S59°25'25"E 472519.8332, 1619989.8641 472483.8790, 1620050.7166 32-GENERAL PIPELINE C10 32+95.57 178°01'06" 150.00' 2.59' 5.19 555°28'24.87"E 5.19' 42-FRUITVALE_OLD UNION PIPELINE L11 37.72' 564°21'10"E 472567.9500, 1619888.3930 472551.6249, 1619922.3940 42-FRUITVALE_OLD UNION PIPELINE L46 110.86' S58°58'46"E 472483.4622, 1620051.4158 472426.3322, 1620146.4188 32-GENERAL PIPELINE C11 35+96.83 173°07'09" 150.00' 9.02' 18.01 557°55'23.33"E 18.00' 42-FRUITVALE_OLD UNION PIPELINE L47 32.43' 558°12'15"E 472426.3322, 1620146.4188 472409.2444, 1620173.9831 32-GENERAL PIPELINE L12 35.54' S61°14'34"E 472547.9035, 1619929.6343 472530.8042, 1619960.7929 42-FRUITVALE_OLD UNION PIPELINE C12 37+79.26 168°3547 150.00 14.98 29.85 S55°3942.05„E 29.81 42-FRUITVALE_OLD UNION PIPELINE L48 29.27' 559°10'23"E 472409.2444, 1620173.9831 472394.2427, 1620199.1219 32-GENERAL PIPELINE L13 26.16' S60°01'36"E 472529.2429, 1619963.5678 472516.1743, 1619986.2275 42-FRUITVALE_OLD UNION PIPELINE C13 40+93.40 178°5628 150.00 1.39 2.77 S49°2549.53„E 2.77 42-FRUITVALE_OLD UNION PIPELINE L49 62.51' 559°10'38"E 472394.2427, 1620199.1219 472362.2153, 1620252.7996 32-GENERAL PIPELINE L14 72.40' S59°25'26"E 472516.1743, 1619986.2275 472479.3439, 1620048.5635 42-FRUITVALE_OLD UNION PIPELINE C14 44+40.49 172°20'28" 150.00' 10.04' 20.05 S52°43'49.62"E 20.04' 42-FRUITVALE_OLD UNION PIPELINE L50 654.47' 559°40'15"E 472362.2153, 1620252.7996 472031.7265, 1620817.7015 32-GENERAL PIPELINE L15 45.75' S59°59'43"E 472479.3439, 1620048.5635 472456.4667, 1620088.1802 42-FRUITVALE_OLD UNION PIPELINE C15 45+46.01 170°22'17" 93.30' 7.86' 15.68 S52°16'59.13"E 15.66' 42-FRUITVALE_OLD UNION PIPELINE L51 9.90' S14°40'15"E 472031.7265, 1620817.7015 472022.1498, 1620820.2087 32-GENERAL PIPELINE C L16 93.16' S58°12'15"E 472454.0589, 1620092.2033 472404.9725, 1620171.3846 42-FRUITVALE_OLD UNION PIPELINE C16 50+96.10 174°15'07" 150.00' 7.53' 15.05 S45°07'56.48"E 15.04' 42-FRUITVALE_OLD UNION PIPELINE L52 45.81' 559°40'15"E 472022.1498, 1620820.2087 471999.0151, 1620859.7526 32-GENERAL PIPELINE L17 91.34' S59°10'23"E 472404.9725, 1620171.3846 472358.1666, 1620249.8183 42-FRUITVALE_OLD UNION PIPELINE C17 61+39.75 137°00'52" 1713.85' 674.85' 1285.80 S64°57'56.21"E 1255.85' 42-FRUITVALE_OLD UNION PIPELINE L53 350.06' 556°27'52"E 471995.9076, 1620864.7388 471802.5171, 1621156.5257 32-GENERAL PIPELINE L18 652.93' 559°40'15"E 472358.1666, 1620249.8183 472028.4567, 1620813.3890 42-FRUITVALE_OLD UNION PIPELINE C18 95+98.67 176°15'13" 105.00' 3.43' 6.87 561°48'06.78"E 6.86' 32-GENERAL PIPELINE L54 9.90' N78°32'08"E 471802.5171, 1621156.5257 471804.4848, 1621166.2277 32-GENERAL PIPELINE L19 9.90' 514°40'15"E 472028.4567, 1620813.3890 472018.8799, 1620815.8962 42-FRUITVALE_OLD UNION PIPELINE C19 96+54.42 177°09'22" 105.00' 2.61' 5.21 S62°15'11.50"E 5.21' 32-GENERAL PIPELINE L55 102.03' 556°27'52"E 471804.4848, 1621166.2277 471748.1197, 1621251.2712 32-GENERAL PIPELINE ° ° „ L20 46.49' 559°40'15"E 472018.8799, 1620815.8962 471995.4060, 1620856.0199 42-FRUITVALE_OLD UNION PIPELINE C20 97+19.14 178 35 33 105.00 1.29 2.58 S60 07 38.86E 2.58 32-GENERAL PIPELINE L56 344.86' N89°52'13"E 471721.7672, 1620852.3729 471722.5476, 1621197.2294 18W-PIPELINE C21 97+91.52 179°33'21" 105.00' 0.41' 0.81 559°12'05.52"E 0.81' 32-GENERAL PIPELINE L21 350.73' 556°27'52"E 471990.9667, 1620863.1430 471797.2053, 1621155.4898 42-FRUITVALE_OLD UNION PIPELINE L57 55.14' N33°32'08"E 471722.5476, 1621197.2294 471768.5113, 1621227.6932 18W-PIPELINE C22 107+40.13 176°47'37" 105.00' 2.94' 5.88 558°04'03.29"E 5.88' 32-GENERAL PIPELINE L22 9.90' N78°32'08"E 471797.2053, 1621155.4898 471799.1729, 1621165.1917 42-FRUITVALE_OLD UNION PIPELINE L58 5.50' N3°32'30"E 469793.1207, 1624166.0512 469798.6101, 1624166.3910 24-OLD UNION PIPELINE C23 140+59.61 177°58'33" 60.00' 1.06' 2.12 N77°02'34.12"E 2.12' 24-OLD_UNION PIPELINE L23 147.57' 556°27'52"E 471799.1729, 1621165.1917 471717.6473, 1621288.1973 42-FRUITVALE_OLD UNION PIPELINE L59 117.68' 586°27'30"E 469798.6101, 1624166.3910 469791.3404, 1624283.8501 24-OLD UNION PIPELINE C24 141+23.38 177°01'23" 60.00' 1.56' 3.12 N79°32'35.81"E 3.12' 24-OLD_UNION PIPELINE L24 289.64' 554°28'58"E 471714.7070, 1621292.4713 471546.4392, 1621528.2239 42-FRUITVALE_OLD UNION PIPELINE L60 14.22' N69°15'41"E 469791.3404, 1624283.8501 469796.3775, 1624297.1531 24-OLD UNION PIPELINE C25 142+11.78 178°43'47" 60.00' 0.67' 1.33 N81°40'00.92"E 1.33' 24-OLD_UNION PIPELINE L25 158.46' 561°21'49"E 471536.8786, 1621543.4785 471460.9370, 1621682.5547 42-FRUITVALE_OLD UNION PIPELINE L61 12.59' N20°58'12"W 469796.3775, 1624297.1531 469808.1349, 1624292.6469 24-OLD UNION PIPELINE C26 142+72.07 173°52'27" 60.00' 3.21' 6.41 N79°14'21.34"E 6.41' 24-OLD_UNION PIPELINE L26 297.88' 549°57'35"E 471444.1242, 1621707.1658 471252.4924, 1621935.2187 42-FRUITVALE_OLD UNION PIPELINE L62 58.55' N76°01'51"E 470221.8378, 1624133.8680 470235.9727, 1624190.6899 24-OLD_UNION PIPELINE C27 143+70.21 176°04'58" 60.00' 2.05' 4.10 N74°13'04.28"E 4.10' 24-OLD_UNION PIPELINE L27 335.67' 548°54'04"E 471250.6897, 1621937.3243 471030.0356, 1622190.2740 42-FRUITVALE_OLD UNION PIPELINE L63 61.15' N78°03'17"E 470236.4479, 1624192.7554 470249.1047, 1624252.5825 24-OLD_UNION PIPELINE C28 144+93.61 178°26'46" 60.00' 0.81' 1.63 N71°28'56.54"E 1.63' 24-OLD_UNION PIPELINE L28 87.65' 556°33'36"E 471017.9026, 1622206.2184 470969.6040, 1622279.3556 42-FRUITVALE_OLD UNION PIPELINE L64 86.17' N81°01'54"E 470249.6704, 1624255.6478 470263.1032, 1624340.7639 24-OLD_UNION PIPELINE C29 146+53.30 174°23'34" 60.00' 2.94' 5.87 N73°30'32.65"E 5.87' 24-OLD_UNION PIPELINE L29 534.74' 548°00'23"E 470960.0234, 1622291.7439 470602.2563, 1622689.1726 42-FRUITVALE_OLD UNION PIPELINE L65 56.42' N82°18'08"E 470263.2960, 1624342.0802 470270.8530, 1624397.9886 24-OLD_UNION PIPELINE C30 147+73.36 152°39'46" 60.00' 14.59' 28.63 N89°58'52.79"E 28.36' 24-OLD_UNION PIPELINE B L30 361.28' 543°28'41"E 470591.6444, 1622699.8336 470329.4871, 1622948.4219 42-FRUITVALE_OLD UNION PIPELINE L66 92.89' N76°10'35"E 470272.0501, 1624404.2876 470294.2446, 1624494.4869 24-OLD_UNION PIPELINE L31 211.06' 586°27'30"E 469798.0569, 1624086.2941 469785.0191, 1624296.9514 42-FRUITVALE_OLD UNION PIPELINE L67 120.53' N72°15'33"E 470295.3600, 1624498.4335 470332.0860, 1624613.2296 24-OLD_UNION PIPELINE L32 13.58' 562°35'44"E 469785.0191, 1624296.9514 469778.7703, 1624309.0041 42-FRUITVALE_OLD UNION PIPELINE L68 155.94' N70°42'20"E 470332.6028, 1624614.7725 470384.1286, 1624761.9520 24-OLD_UNION PIPELINE L33 65.35' 520°11'58"E 469778.7703, 1624309.0041 469717.4402, 1624331.5685 42-FRUITVALE_OLD UNION PIPELINE L69 102.54' N76°18'46"E 470385.7947, 1624767.5801 470410.0579, 1624867.2074 24-OLD_UNION PIPELINE L34 39.34' 564°34'01"E 473326.1666, 1618695.3312 473309.2730, 1618730.8560 32-GENERAL PIPELINE L70 37.60' 576°21'00"E 470410.0671, 1624895.5642 470401.1932, 1624932.1051 24-OLD_UNION PIPELINE L35 7.28' 558°48'58"E 473309.2730, 1618730.8560 473305.5060, 1618737.0800 32-GENERAL PIPELINE A ALIGNMENT A.1 LINE TABLE ALIGNMENT A.1 CURVE TABLE LINE NO. LENGTH DIRECTION START POINT (N,E) END POINT (N,E) CURVE NO. PI STATION A RADIUS TANGENT LENGTH CHORD DIRECTION CHORD LENGTH L100 114.00' 552°59'01"E 473058.68, 1619059.89 472990.05, 1619150.91 C100 4+75.30 164°50'02" 377.80' 50.30' 100.00 567°56'42.94"E 99.71' 2A L101 137.66' S51°31'25"E 472990.05, 1619150.91 472904.40, 1619258.68 C101 5+91.40 160°06'05" 378.51' 66.40' 131.45 563°02'21.20"E 130.80' L102 200.73' S44°06'26"E 472904.40, 1619258.68 472760.27, 1619398.39 C102 17+10.98 168°21'33" 200.00' 20.39' 40.63 N83°12'57.46"E 40.56' L C103 19+13.24 171°16'39" 250.00' 19.07' 38.06 S86°36'08.47"E 38.02' 2B A 103 145.63' 535°30'40"E 472760.27, 1619398.39 472641.72, 1619482.98 L104 226.04' 535°21'00"E 472641.72, 1619482.98 472457.36, 1619613.76 L105 146.70' 580°06'16"E 472457.36, 1619613.76 472432.15, 1619758.27 2C L106 58.23' N54°53'44"E 472432.15, 1619758.27 472465.63, 1619805.91 L107 162.94' N89°02'11"E 472471.55, 1619851.22 472474.29, 1620014.14 L108 5.00' N77°23'44"E 472465.63, 1619805.91 472466.72, 1619810.79 L109 12.05' 582°14'28"E 472472.04, 1620052.09 472470.41, 1620064.04 PROJECT MANAGER MICHAEL GARELLO, PE DESIGNED BY M. GARELLO NELSON DAM REMOVAL PROJECT: CIVIL 8 1 0 DESIGNED BY _ WATER SUPPLY, FISH PASSAGE, AND CHECKED BY R. ROBERTS •`l�',_ , �', RIVERINE PROCESS IMPROVEMENTS PIPELINE C 9/23/2025 ACKLEY ROAD REALIGNMENT DRAWN BY N. SZIGETI A LINE AND CURVE TABLES r..; �•..' PHASE II - CONVEYANCE imslfro, IM)1 •. Know what's below. B 9/18/2024 CONFORMED FOR CONSTRUCTION ��,' " �w" =' IMPROVEMENTS 0 _ _1" 2" FILENAME 02C22.dwg SHEET Call before you dig. A 8/14/2024 ISSUED FOR BID SCALE - 02C22 ISSUE DATE DESCRIPTION PROJECT NUMBER 10173276 CITY OF YAKIMA, WAS H I N GTO N SALES TAX ADJUSTMENT CALCULATION Project Phase 2B Contract Amount w/o Sales Tax or Change Modifications $2,520,002.00 Sales Tax(Rate-8.3%)@ Time of Bid (Yr.2024) $209,160.17 Project Phase 2B Original Contract Amount(w/Sales Tax) @ 8.3% $2,729,162.17 Current Sales Tax(Rate-8.6%) $216,720.17 Amount to be added to the Contract(Difference between the Sales Tax @ Time of Bid and Current Sales Tax) $7,560.01 co