BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 7.D.
For Meeting of: June 16, 2026
ITEM TITLE: Project Completion and Contract Acceptance with Total Site Services
LLC for Systemic Pedestrian Safety Improvements Project 2675 (No
Budgetary Impact)
SUBMITTED BY: Robert Washabaugh, City Engineer
SUMMARY EXPLANATION:
City of Yakima Project 2675 provided for reconstruction of the N 5th Avenue &W D Street Intersection.
Including sidewalk, curb and gutter, storm drainage improvements, crossing improvements, RRFB
installation, excavation, grading, and related improvements. Project was funded through Washington
State Department of Transportation with federal funds from HSIP and the Transportation Improvement
Board Complete Streets.
Final inspection for this project has been completed, and project acceptance is recommended. Project
completion is subject to issuance of Certificate of Payment by the Department of Revenue.
Project Manager: Gray & Osborne, Inc.
Contractor: Total Site Services LLC
Contract Award: $517,000.00
Final Contract Cost: $506,928.15
Retainage Due: $0
City Council action is required to accept the project and approve the final construction costs.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY 24-25: A Resilient Yakima
RECOMMENDATION: Accept Project.
ATTACHMENTS:
Notice of Physical Completion
17
Gray 8z Osborne, Inc.
CONSULTING ENGINEERS
March 13, 2026
Ms. Shannon Toranzo
Total Site Services, LLC
2780 Salk Avenue
Richland, Washington 99354
SUBJECT: PHYSICAL COMPLETION, SYSTEMIC PEDESTRIAN SAFETY
IMPROVEMENTS
CITY OF YAKIMA, YAKIMA COUNTY, WASHINGTON
G&O #23863.01 CITY PROJECT NO.: 2675AT
FEDERAL AID NO.: HSIP-000S(662)
Dear Ms. Toranzo:
In accordance with WSDOT Standard Specifications Section 1-08.5, the City is
notifying Total Site Services, LLC, that the Physical Completion date for this project
is October 17, 2025. Physical Completion does not imply the City's acceptance of
the work or the contract.
Sincerely,
GRAY& OSBORNE, INC.
Michael Woodkey, P.E.
MW/j s
By email
cc: Mr. Nick Rogers, Construction Supervisor, City of Yakima
Mr. Seth Walker, WSDOT Local Programs Regional Engineer
Ms. Brenda Fehlhafer, Contract Specialist, City of Yakima
Mr. Dana Kallevig, Senior Engineer, City of Yakima