BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 7.B.
For Meeting of: March 4, 2025
ITEM TITLE: Project Completion and Contract Acceptance for the Snow Removal
Equipment (SRE) Procurement AIP# 3-53-0089-054-2023
SUBMITTED BY: Robert Hodgman, Yakima Airport Director
SUMMARY EXPLANATION:
This project included the procurement of Snow Removal Equipment (SRE) which were two high speed
runway plows. The airport had two 1992 Oshkosh runway plows that had exceeded their useful life and
the aging equipment continued to have major maintenance problems. The high-speed runway plows are
essential to keep operations and the airport open during the winter months. Project cost was about $1.5
million of which the Federal Aviation Administration (FAA) paid for 90°/o through Bipartisan Infrastructure
Law (BIL) grant and 10°/o from the airport's Passenger Facility Charge account
ITEM BUDGETED: Yes
STRATEGIC PRIORITY 24-25: A Resilient Yakima
RECOMMENDATION: Accept Project
ATTACHMENTS:
Substantial Completion Form_Signed.pdf
L- Project Substantial Completion 2-12-25.pdf
53
CITY OF YAKIMA
YAKIKMA AIR TERMINAL, MCALLISTER FIELD
SNOW REMOVAL EQUIPMENT(SRE) PROCUREMENT
AIP#3-53-0089-054-2023
CERTIFICATE OF SUBSTANTIAL COMPLETION
PROJECT: Snow Removal Equipment(SRE) Procurement
DATE OF ISSUANCE: January 15, 2025
OWNER: City of Yakima
OWNER's Contract No.: N/A ENGINEER's Contract No.: 45-22-036
CONTRACTOR: M-B Companies, Inc. ENGINEER: J-U-B ENGINEERS,,Inc.
This Certificate of Substantial Completion applies to all Work under the Contract Documents or to the following
specified parts thereof:
All Work
To: City of Yakima //,-/
And To: M-B Companies, Inc.
CONTRACTOR
The Work to which this Certificate applies has been inspected by authorized representatives of OWNER,
CONTRACTOR and ENGINEER, and that Work is hereby declared to be substantially complete in accordance
with the Contract Documents on
DATE OF SUBSTANTIAL COMPLETION: December 27th, 2024
A tentative list of items to be completed or corrected is attached hereto.This list may not be all-inclusive, and
the failure to include an item in it does not alter the responsibility of the CONTRACTOR to complete all the
Work in accordance with the Contract Documents.
45-22-036/Yakima Air Terminal,McAllister Field
J-U-B Master Revision Date 04-26-17
54
CITY OF YAKIMA
YAKIKMA AIR TERMINAL, MCALLISTER FIELD
SNOW REMOVAL EQUIPMENT (SRE) PROCUREMENT
AIP#3-53-0089-054-2023
The responsibilities between OWNER and CONTRACTOR for security, operation, safety, maintenance, heat,
utilities, insurance and warranties and guarantees shall be as follows:
RESPONSIBILITIES:
OWNER City of Yakima
CONTRACTOR: M-B Companies, Inc.
The following documents are attached to and made a part of this Certificate:
Project Punch List dated January 13, 2025
This certificate does not constitute an acceptance of Work not in accordance with the Contract Documents nor
is it a release of CONTRACTOR's obligation to complete the Work in accordance with the Contract Documents.
Executed by ENGINEER on January 15, 2025
J-U-B ENGINEERS, Inc.
ENGINEER
By: .
(Authorized Signature)
CONTRACTOR accepts this Certificate of Substantial Completion on 1/16 _ , 2025
M-B Companies,Inc.
CONTRACTOR
By:
(Authorized Signature)Joshua Abler
OWNER accepts this Certificate of Substantial Completion on .., 20_
'ty of Yaki
By: a-------
( h ()Zed Sign
45-22-036/Yakima Air Terminal,McAllister Field
J-U-B Master Revision Date 04-26-17
55
HELPING EACH OTHER
CREATE BETTER COMMUNITIES
® THE GATEWAY
LAAYDON GATEWAY
GROUP INC.
J-U-B FAMILY OF COMPANIES
January 15,2025
Mark Meaders, General Manager
M-B Companies, Inc.
201 MB Lane
Chilton,WI 53014
RE CITY OF YAKIMA—YAKIMA AIR TERMINAL/MCALLISTER FIELD
SNOW REMOVAL EQUIPMENT (SRE) PROCUREMENT AIP#3-53-0089-054-2023
Dear Mark,
The work on the above referenced project has been determined to be Substantially Complete as of Friday
December 27, 2024.As of this date, M-B Companies, Inc. has used four hundred and ninety-eight (498) of the
five hundred (500)working days made available per the contract documents.
This notice does not relieve M-B Companies, Inc.of any responsibilities or guarantees stated within the
original contract.
The attached punch list items were identified during an overview on January 13, 2025, and will need to be
completed prior to final acceptance of the project.The punch list items may not be all-inclusive,and the failure
to include an item in it does not alter the responsibility of the M-B Companies to complete all obligations in
accordance with the Contract Documents. You will be notified if any additional documentation or contract
requirements are identified which require completion before acceptance.
In the event that the remaining items are not completed in a timely manner, the Owner reserves the right to
restart the charging of working days.
Sincerely,
L
Spencer L. Stephens, P.E.
J-U-B ENGINEERS, Inc.
West 999 Riverside, Suite 700, Spokane,WA 99201 www.jub.com 509.458.3727
56
T- -�' -
:-„-_
r ' .7' 12
r\C\CW7,tr%1
Z . r _ ! 1 !a n1e
h I C I _ I_I. I !. I
THE GATEWAY
e O, 1. I stir �j� LANGDON MAPPING
• 1 •� - C�•U•� �/" GROUP INC.
J U B ENGINEERS,INC. J-U•B FAMILY OF COMPANIES
EQUIPMENT OVERVIEW JANUARY 13, 2025
AND PUNCH LIST ITEMS
COMPLETION ITEM DATE COMPLETED
Equipment Training 12/30/2024
Delivery of Spare/Service Parts 2/4/2025
Delivery of Manuals, Preventative 2/4/2025
Maintenance Schedule, Certifications, Etc.
Address Hydraulic/Transmission Fluid Leak 2/11/2025
2
57